Item Requirements

Article Name: Additive Manufacturing of Copper Alloy Test Article Using 

Single-mode   Continuous   Green   Laser   Powder   Bed 
Fusion (PBF) Equipment

1. Overview

This task involves manufacturing a test article using copper al oy powder 
through powder bed fusion (PBF) additive manufacturing technology 
employing a single-mode continuous green laser, and conducting material 
property evaluations on the fabricated specimen.

2. Contract Method

Contract Period: Ninety (90) days after Effective Date of Contract (EDC)

Estimated Budget: USD 18,350.00

Method of Contract: restricted competitive bid (the lowest bid price)

Qualification bidding documents (must be submitted by the bidding deadline 
and verified prior to bid opening/qualification review)

o

Evidence of technical capabilities for task execution (patents related to 
Green Laser PBF equipment)

o

Test report for copper alloy (CuCrZr) manufactured using in-house 
equipment (meeting Requirement 1 specified in Section 3.3) 3. 
Detailed Task Description

3.1 Design/Manufacturing Plan Preparation & Kick-off Meeting 

(within 2 weeks after contract)

Submit production design and schedule after discussing task details. 

Specify inspection items, methods (including equipment and standards), and 
performing agencies (or company) for test article and specimens.

Hold a kick-off meeting to discuss details after establishing the manufacturing 
process and schedule. 

Proposed Master Plan

 (The manufacturer must submit a detailed plan)

o

26.07
- Prepare detailed Design/Manufacturing plan prior to contract signing.
- Conduct kick-off meeting immediately after contract signing (discuss 
proposed Design/Manufacturing plan).
- Document and report DfAM/analysis results, fol owed by meeting.
- Start additive manufacturing after finalizing the printing geometry.

o

26.08
- Perform inspection and measurement after additive manufacturing 
completion, submit results report.
- Begin post-processing and prepare for strength/leak testing (share 
progress by stage).
- Perform specimen testing and submit results analysis report.


background image

o

26.09
- Perform strength/leak testing (request client's on-site visit and 
observation) and ship delivery items to client.

3.2 DfAM Geometry and Process Design

Review AM feasibility using 3D CAD model provided by the client.

Perform DfAM(design for additive manufacturing) geometric design for the 
final design proposal and share model file (.prt, .stp, .stl, etc.).

Predict deformation via simulation prior to printing.

Establish strategies to minimize deformation (support, orientation, process 
parameters, compensation design, etc.).

Create machining drawings for interface work after printing.

The DfAM process and results must be documented and approved by the 
client before proceeding with additive manufacturing. Additive manufacturing 
must be able to initiate within two weeks of receiving approval for the 
documented DfAM design. The start of additive manufacturing must occur 
within one month of contract execution.

Discuss design changes required for AM and finalize the design.

3.3 Additive Manufacturing(L-PBF)

Deliverable: test article, 1 set

Dimensions: ~340 mm x Dia. 170 mm (Detailed drawings provided after 
contract).

Material: CuCrZr (for PBF)

o

Secure material certificates and perform basic inspections (shape, 
composition, size distribution, flowability, etc.).

Requirements:

1.

Must be manufactured as a single piece using single-mode continuous 
green laser PBF equipment, through a process satisfying the fol owing 
conditions: density 99.98%, tensile strength 510MPa, yield strength 
410MPa, elongation at break 20% (test in accordance with ASTM E8).

2.

Using a single-mode continuous green laser PBF printer, print 4 round 
bars for tensile testing (same height as the test article) simultaneously 
with the test article (2 inside, 2 outside the test article).

3.

Submit photos and videos documenting the entire process (printing, 
machining, inspection, measuring, test, etc.), with the video submitted 
as a time-lapse video (30~60 seconds).

3.4 Post-Processing

Powder Removal & Inspection:

o

Completely remove internal powder before additional work, verify via 
RT (Radiographic Test) and CT (Computed Tomography).

o

Submit powder removal results (RT, CT video-based report) for 
approval. Check for defects like Shrinkage Lines (SL) or Pin Holes via 
visual inspection.


background image

o

Proceed with re-manufacturing or fol ow-up processes upon agreement 
with the client depending on defects.

o

Measure dimensions in the as-printed state and submit a comparison 
report against the 3D CAD model used for printing and build simulation 
result. 

Stress Relief & Wire Cutting:

o

Perform sandblasting, stress relief heat treatment, and wire cutting 
according to the manufacturer's standards.

o

Remove supports from the test article before/after wire cutting. 

Strengthening Heat Treatment & Tensile Testing:

o

Perform heat treatment on the test article and round bars according to 
the manufacturer's standard for CuCrZr heat treatment. 

o

Machine 4 tensile specimens per one round bar (number may vary 
based on SL location).

o

Machine the specimens so that the layer where SL or other defects are 
identified becomes the measurement location for the tensile test.

o

Perform the tensile test (at room temperature).

o

Test tensile specimens using tensile testing equipment within its 
inspection validity period, as specified in the manufacturing plan 
proposal and confirmed at the manufacturing kick-off meeting (If 
equipment is changed, a written justification must be submitted and 
approved by the client.).

o

The tensile test results are submitted to the client in report format 
(including tables and graphs).

o

Criteria: Individual tensile test results must achieve at least 90% of the 
reference values. Results below 90% are deemed manufacturing 
defects, requiring agreement with the client to determine subsequent 
process actions. Reference values may be adjusted to target values 
provided by the manufacturer with the client's approval.

Test Article Inspection & Machining:

o

Perform additional visual inspection (including inner wal ) and 
sandblasting for surface roughness improvement after separation from 
BP.

o

Perform dimensional measurements (using a coordinate measuring 
machine, CMM) on wire-cut test article to verify machining reference 
surfaces.

o

Based on the measured dimensions, revise the machining drawings 
(including tool drawings), obtain approval from the client, and perform 
the shape machining. After machining is complete, perform 
dimensional measurement (using a 3D measuring machine, CMM) on 
the machined areas.

o

If measurements are to be performed using equipment possessing 
equivalent precision instead of CMM, approval from the client must be 
obtained.


background image

3.5 Assembly & Testing

Assembly:

o

Secure fittings and caps, and mount them on the test article after 
machining is complete to enable testing.

o

The contractor must also prepare al  necessary fittings, plugs, gaskets, 
pressure strength/leak test plugs and fixtures for the test article, and 
fastening bolts/nuts for the test article ports.

Strength & Leak Testing:

o

Strength Test: Pressurize both flow path to 10 bar each (maintain at 
10 bar intervals for 60 seconds each, avoid rapidly increasing pressure 
in one flow path to prevent hardware damage), then pressurize to 90 
bar and maintain at 90 bar for 5 minutes. Attach dial gauges to 
measure deformation.

o

Leak Test 1: Pressurize both flow path to 10 bar each (maintain at 10 
bar increments for 60 seconds each, avoid rapid pressure increases in 
one channel to prevent hardware damage), then pressurize to 60 bar 
and hold for 5 minutes to verify leak tightness (check internal pressure 
measurement or presence of bubbles in the water tank, etc.).

o

Leak Test 2: Pressurize flow path to 10 bar (maintain at 10 bar 
increments for 60 seconds each, avoid rapid pressure increases in flow 
path to prevent hardware damage), then pressurize to 30 bar and hold 
for 5 minutes to verify leak tightness (check internal pressure 
measurement or presence of bubbles in the water tank, etc.). This test 
is performed individually for each flow path (to verify the absence of 
leakage between flow paths).

o

Strength/leak tests shal  be conducted in principle by preparing a test 
procedure sheet, obtaining approval prior to the test date, and 
performing the test in the presence of the client(preferably visit the 
manufacturer during 3D printing or strength/leak testing). If client 
attendance is not possible, the test process shal  be captured and 
recorded, and the video provided.

o

The strength test involves placing the test article on a stable surface 
and attaching dial gauges or similar devices to areas susceptible to 
deformation to measure the amount of deformation.

3.6 Delivery

After production and testing are completed, the test article must be completely 
dried to remove al  internal and external moisture. It must then be fil ed with 
helium (or nitrogen) or equivalent protective measures must be taken to 
prevent moisture ingress.

Pack securely to prevent damage during transport.

Deliver all components used in the strength/leak test, including the caps and 
fasteners. 

Submit original manufacturing drawings and photographic documentation as 
original files.


background image

Submit the original data for al  measurements, instrumentation, and tests.