PDF문서(090810)_미국_새로운_우주시스템_개발에_따른_국방부의_과제-원문_PDF.pdf

닫기

background image

 
 
 
 
 
 
 
 
 
 
 

GAO 

 

United States Government Accountability Office

Testimony 
Before the Subcommittee on Strategic 
Forces, Committee on Armed Services,    
U.S. Senate

SPACE ACQUISITIONS

DOD Faces Substantial 
Challenges in Developing 
New Space Systems 

Statement of Cristina T. Chaplain, Director 
Acquisition and Sourcing Management 
 
 
 

For Release on Delivery 
Expected at 2:00 p.m. EDT 
Wednesday, May 20, 2009 

 
 

 

GAO-09-705T 


background image

What GAO Found

United States Government Accountability Office

Why GAO Did This Study

Highlights

Accountability Integrity Reliability

May 20. 2009

 
 

SPACE ACQUISITIONS

DOD Faces Substantial Challenges in Developing 
New Space Systems 

Highlights of GAO-09-705T, a testimony 
before the Subcommittee on Strategic 
Forces, Committee on Armed Services, 
U.S. Senate 

T

Despite a growing investment in 
space, the majority of large-scale 
acquisition programs in the 
Department of Defense’s (DOD) 
space portfolio have experienced 
problems during the past two 
decades that have driven up cost 
and schedules and increased 
technical risks. The cost resulting 
from acquisition problems along 
with the ambitious nature of space 
programs has resulted in 
cancellations of programs that 
were expected to require 
investments of tens of billions of 
dollars. Along with the cost 
increases, many programs are 
experiencing significant schedule 
delays—at least 7 years—resulting 
in potential capability gaps in areas 
such as positioning, navigation, and 
timing; missile warning; and 
weather monitoring. 
  
This testimony focuses on 
 

 

the condition of space 
acquisitions,  

 

causal factors, and 

 

recommendations for better 
positioning programs and 
industry for success.  

 
In preparing this testimony, GAO 
relied on its body of work in space 
and other programs, including 
previously issued GAO reports on 
assessments of individual space 
programs, common problems 
affecting space system acquisitions, 
and DOD’s acquisition policies. 
 

Estimated costs for major space acquisition programs have increased by 
about $10.9 billion from initial estimates for fiscal years 2008 through 2013. As 
seen in the figure below, in several cases, DOD has had to cut back on 
quantity and capability in the face of escalating costs.  
 

Total Cost Differences from Program Start to Most Recent Estimates 
 

Legend: SBIRS = Space Based Infrared System, GPS = Global Positioning System, WGS = 
Wideband Global SATCOM, AEHF = Advanced Extremely High Frequency, NPOESS = National 
Polar-orbiting Operational Environmental Satellite System, and MUOS = Mobile User Objective 
System. 

 
Several causes behind the cost growth and related problems consistently 
stand out. First, DOD starts more weapon programs than it can afford, 
creating competition for funding that, in part, encourages low cost estimating 
and optimistic scheduling. Second, DOD has tended to start its space 
programs before it has the assurance that the capabilities it is pursuing can be 
achieved within available resources.  
 
GAO and others have identified a number of pressures associated with the 
contractors that develop space systems for the government that have 
hampered the acquisition process, including ambitious requirements and 
shortages of technical expertise in the workforce. Although DOD has taken a 
number of actions to address the problems on which GAO has reported, 
additional leadership and support are still needed to ensure that reforms that 
DOD has begun will take hold.  
 

View GAO-09-705T or key components. 
For more information, contact Cristina T. 
Chaplain, 202-512-4841, chaplainc@gao.gov. 


background image

 
 
 
 

Page 1 

GAO-09-705T   

  

Mr. Chairman and Members of the Subcommittee: 

I am pleased to be here today to discuss the Department of Defense’s 
(DOD) space acquisitions. The topic of today’s hearing is critically 
important. Despite a growing investment in space, the majority of large-
scale acquisition programs in DOD’s space portfolio have experienced 
problems during the past two decades that have driven up cost and 
schedules and increased technical risks. The cost resulting from 
acquisition problems along with the ambitious nature of space programs 
has resulted in cancellations of programs that were expected to require 
investments of tens of billions of dollars, including the recently proposed 
cancellation of the Transformational Satellite Communications System 
(TSAT). Moreover, along with the cost increases, many programs are 
experiencing significant schedule delays—at least 7 years—resulting in 
potential capability gaps in areas such as positioning, navigation, and 
timing; missile warning; and weather monitoring. 

My testimony today will focus on the condition of space acquisitions, 
causal factors, and recommendations for better positioning programs for 
success. Many of these have been echoed by the Allard Commission,

 

which studied space issues in response to a requirement in the John 
Warner National Defense Authorization Act for Fiscal Year 2007, and by a 
study by the House Permanent Select Committee on Intelligence (HPSCI),

 

among other groups. The two studies highlighted concerns about diffuse 
leadership for military and intelligence space efforts and declining 
numbers of space engineering and technical professionals. Members of the 
Allard Commission were unanimous in their conviction that without 
significant improvements in the leadership and management of national 
security space programs, U.S. space preeminence will erode “to the extent 
that space ceases to provide a competitive national security advantage.” 

 

                                                                                                                                    

1 Institute for Defense Analyses, Leadership, Management, and Organization for National 
Security Space: Report to Congress of the Independent Assessment Panel on the 
Organization and Management of National Security Space 

(Alexandria, Va.: July 2008). 

2 House Permanent Select Committee on Intelligence, Report on Challenges and 
Recommendations for United States Overhead Architecture 

(Washington, D.C.: October 

2008). 


background image

 
 
 
 

Figure 1 compares original cost estimates and current cost estimates for 
the broader portfolio of major space acquisitions for fiscal years 2008 
through 2013. The wider the gap between original and current estimates, 
the fewer dollars DOD has available to invest in new programs. As shown 
in the figure, estimated costs for the major space acquisition programs 
have increased by about $10.9 billion from initial estimates for fiscal years 
2008 through 2013. The declining investment in the later years is the result 
of the Evolved Expendable Launch Vehicle (EELV) program’s no longer 
being considered a major acquisition program and the cancellation and 
proposed cancellation of two development efforts that would have 
significantly increased DOD’s major space acquisition investment. 

Space Acquisition 
Problems Persist 

Figure 1: Comparison between Original Cost Estimates and Current Cost Estimates 
for Selected Major Space Acquisition Programs for Fiscal Years 2008 through 2013 

 

Note: The acquisition programs include Advanced Extremely High Frequency, Global Broadcast 
Service, Global Positioning System II, Global Positioning System IIIA, Mobile User Objective System, 
National Polar-orbiting Operational Environmental Satellite System, Space Based Infrared System, 
and Wideband Global SATCOM. 

 

Figures 2 and 3 reflect differences in total life-cycle and unit costs for 
satellites from the time the programs officially began to their most recent 

Page 2 

GAO-09-705T   


background image

 
 
 
 

cost estimate. As figure 2 notes, in several cases, DOD has had to cut back 
on quantity and capability in the face of escalating costs. For example, two 
satellites and four instruments were deleted from National Polar-orbiting 
Operational Environmental Satellite System (NPOESS) and four sensors 
are expected to have fewer capabilities. This will reduce some planned 
capabilities for NPOESS as well as planned coverage. 

Figure 2: Differences in Total Life-Cycle Program Costs from Program Start and 
Most Recent Estimates 

 

 
Legend: SBIRS = Space Based Infrared System, GPS = Global Positioning System, WGS = 
Wideband Global SATCOM, AEHF = Advanced Extremely High Frequency, NPOESS = National 
Polar-orbiting Operational Environmental Satellite System, and MUOS = Mobile User Objective 
System. 

 

Page 3 

GAO-09-705T   


background image

 
 
 
 

Figure 3: Differences in Unit Costs from Program Start to Most Recent Estimates 

 

Legend: SBIRS = Space Based Infrared System, GPS = Global Positioning System, WGS = 
Wideband Global SATCOM, AEHF = Advanced Extremely High Frequency, NPOESS = National 
Polar-orbiting Operational Environmental Satellite System, and MUOS = Mobile User Objective 
System. 

 

Figure 4 highlights the additional estimated months needed to complete 
programs. These additional months represent time not anticipated at the 
programs’ start dates. Generally, the further schedules slip, the more DOD 
is at risk of not sustaining current capabilities. For this reason, DOD began 
a follow-on system effort, now known as Third Generation Infrared 
Surveillance, to run in parallel with the Space Based Infrared System 
(SBIRS) program. 

Page 4 

GAO-09-705T   


background image

 
 
 
 

Figure 4: Differences in Total Number of Months to Initial Operational Capability 
(IOC) from Program Start and Most Recent Estimates 

 

Legend: SBIRS = Space Based Infrared System, GPS = Global Positioning System, WGS = 
Wideband Global SATCOM, AEHF = Advanced Extremely High Frequency, NPOESS = National 
Polar-orbiting Operational Environmental Satellite System, and MUOS = Mobile User Objective 
System. 

 

This fiscal year, DOD launched the second Wideband Global SATCOM 
(WGS) satellite. WGS had previously been experiencing technical and 
other problems, including improperly installed fasteners and data 
transmission errors. When DOD finally resolved these issues, it 
significantly advanced capability available to warfighters. Additionally, the 
EELV program had its 23rd consecutive successful operational launch in 
April. However, other major space programs have had setbacks. For 
example: 

Page 5 

GAO-09-705T   


background image

 
 
 
 

  In September 2008, the Air Force reported a Nunn-McCurdy unit cost 

breach of the critical cost growth threshold

 for the Advanced Extremely 

High Frequency (AEHF) communications satellite because of cost growth 
brought on by technical issues, schedule delays, and increased costs for 
the procurement of a fourth AEHF satellite. The launch of the first satellite 
has slipped further by almost 2 years from November 2008 to as late as 
September 2010. Further, the program office estimates that the fourth 
AEHF satellite could cost more than twice the third satellite because some 
components that are no longer manufactured will have to be replaced and 
production will have to be restarted after a 4-year gap. Because of these 
delays, initial operational capability has slipped 3 years—from 2010 to 
2013. 

  The Mobile User Objective System (MUOS) communications satellite 

estimates an 11-month delay—from March 2010 to February 2011—in the 
delivery of on-orbit capability from the first satellite. Further, contractor 
costs for the space segment have increased about 48 percent because of 
the additional labor required to address issues related to satellite design 
complexity, satellite weight, and satellite component test anomalies and 
associated rework. Despite the contractor’s cost increases, the program 
has been able to remain within its baseline program cost estimate. 

  The first Global Positioning System (GPS) IIF satellite is now expected to 

be delayed almost 3 years from its original launch date to November 2009. 
Also, the cost of GPS IIF is now expected to be about $1.6 billion—about 
$870 million over the original cost estimate of $729 million. (This 
approximately 119 percent cost increase is not that noticeable in figures 2 
and 3 because the GPS II modernization program includes the 
development and procurement of 33 satellites, only 12 of which are IIF 
satellites.) The Air Force has had difficulty in the past building GPS 
satellites within cost and schedule goals because of significant technical 
problems—which still threaten its delivery schedule—and challenges it 
faced with a different contractor for the IIF program, which did not 
possess the same expertise as the previous GPS contractor. Further, while 
the Air Force is structuring the new GPS IIIA program to prevent mistakes 
made on the IIF program, the Air Force is aiming to deploy the GPS IIIA 
satellites 3 years faster than the IIF satellites. We believe the IIIA schedule 
is optimistic given the program’s late start, past trends in space 
acquisitions, and challenges facing the new contractor. 

                                                                                                                                    

3 10 U.S.C. § 2433 establishes the requirement for unit cost reports. If certain unit cost 
thresholds are exceeded (known as Nunn-McCurdy breaches), DOD is required to report to 
Congress and, in certain circumstances, if DOD determines that specific criteria are met, 
certify the program to Congress. 

Page 6 

GAO-09-705T   


background image

 
 
 
 

  Total program cost for the SBIRS program is estimated around $12.2 

billion, an increase of $7.5 billion over the original program’s cost, which 
included 5 geosynchronous earth orbit (GEO) satellites. The first GEO 
satellite has been delayed at least 7 years in part because of poor 
oversight, technical complexities, and rework. Although the program 
office set December 2009 as the new launch goal for the satellite, it is 
currently assessing the satellite launch schedule and expects to have a 
new plan in place by June 2009. Subsequent GEO satellites have also 
slipped as a result of flight software design issues. 

  The NPOESS program has experienced problems with replenishing the 

current constellation of aging weather satellites and was restructured in 
July 2007 in response to a Nunn-McCurdy unit cost breach of the critical 
cost-growth threshold. The program was originally estimated to cost about 
$6.5 billion for six satellites from 1995 through 2018. The restructured 
program called for reducing the number of satellites from six to four and 
included an overall increase in program costs, delays in satellite launches, 
and deletions or replacements of satellite sensors. Although the number of 
satellites has been reduced, total costs have increased by almost 108 
percent since program start. Specifically, the current estimated life-cycle 
cost of the restructured program is now about $13.5 billion for four 
satellites through 2026. This amount is higher than what is reflected in 
figure 2 as it represents the most recent GAO estimate as opposed to the 
DOD estimates used in the figure. We reported last year that poor 
workmanship and testing delays caused an 8-month slip in the delivery of 
a complex imaging sensor. This late delivery caused a delay in the 
expected launch date of a demonstration satellite, moving it from late 
September 2009 to early January 2011. 

This year it is also becoming more apparent that space acquisition 
problems are leading to potential gaps in the delivery of critical 
capabilities. For example, DOD faces a potential gap in protected military 
communications caused by delays in the AEHF program and the proposed 
cancellation of the TSAT program, which itself posed risks in schedule 
delays because of TSAT’s complexity and funding cuts designed to ensure 
technology objectives were achievable. DOD faces a potential gap in ultra 
high frequency (UHF) communications capability caused by the 
unexpected failures of two satellites already in orbit and the delays 
resulting from the MUOS program. DOD also faces potential gaps or 
decreases in positioning, navigation and timing capabilities because of late 
delivery of the GPS IIF satellites and the late start of the GPS IIIA 
program. There are also concerns about potential gaps in missile warning 
and weather monitoring capabilities because of delays in SBIRS and 
NPOESS. 

Page 7 

GAO-09-705T   


background image

 
 
 
 

Addressing gaps in any one of these areas is not a simple matter. While 
there may be opportunities to build less complex “gap filler” satellites, for 
example, these still require time and money that may not be readily 
available because of commitments to the longer-term programs. There 
may also be opportunities to continue production of “older” generation 
satellites, but such efforts also require time and money that may not be 
readily available and may face other challenges such as restarting 
production lines and addressing issues related to obsolete parts and 
materials. Further, satellites on orbit can be made to last longer by turning 
power off at certain points in time, but this may also present unacceptable 
trade-offs in capability. 

 
Our past work has identified a number of causes behind the cost growth 
and related problems, but several consistently stand out. First, on a broad 
scale, DOD starts more weapon programs than it can afford, creating a 
competition for funding that encourages low cost estimating, optimistic 
scheduling, overpromising, suppressing bad news, and, for space 
programs, forsaking the opportunity to identify and assess potentially 
more executable alternatives. Programs focus on advocacy at the expense 
of realism and sound management. Invariably, with too many programs in 
its portfolio, DOD is forced to continually shift funds to and from 
programs—particularly as programs experience problems that require 
additional time and money to address. Such shifts, in turn, have had costly, 
reverberating effects. 

Underlying Reasons 
for Cost and Schedule 
Growth 

Second, DOD has tended to start its space programs too early, that is, 
before it has the assurance that the capabilities it is pursuing can be 
achieved within available resources and time constraints. This tendency is 
caused largely by the funding process, since acquisition programs attract 
more dollars than efforts concentrating solely on proving technologies. 
Nevertheless, when DOD chooses to extend technology invention into 
acquisition, programs experience technical problems that require large 
amounts of time and money to fix. Moreover, when this approach is 
followed, cost estimators are not well positioned to develop accurate cost 
estimates because there are too many unknowns. Put more simply, there is 
no way to accurately estimate how long it would take to design, develop, 
and build a satellite system when critical technologies planned for that 
system are still in relatively early stages of discovery and invention. 

While our work has consistently found that maturing technologies before a 
program’s start is a critical enabler of success, it is important to keep in 
mind that this is not the only solution. Both the TSAT and the Space Radar 

Page 8 

GAO-09-705T   


background image

 
 
 
 

development efforts, for example, were seeking to mature critical 
technologies before program start, but they faced other risks related to the 
systems’ complexity, affordability, and other development challenges. 
Ultimately, Space Radar was cancelled, and DOD has proposed the 
cancellation of TSAT. Last year, we cited the MUOS program’s attempts to 
mature critical technologies before the program’s start as a best practice, 
but the program has since encountered technical problems related to 
design issues and test anomalies. 

Third, programs have historically attempted to satisfy all requirements in a 
single step, regardless of the design challenge or the maturity of the 
technologies necessary to achieve the full capability. DOD has preferred to 
make fewer but heavier, larger, and more complex satellites that perform a 
multitude of missions rather than larger constellations of smaller, less 
complex satellites that gradually increase in sophistication. This has 
stretched technology challenges beyond current capabilities in some cases 
and vastly increased the complexities related to software. Programs also 
seek to maximize capability because it is expensive to launch satellites. A 
launch using a medium- or intermediate-lift EELV, for example, would cost 
roughly $65 million. 

Fourth, several of today’s high-risk space programs began in the late 
1990s, when DOD structured contracts in a way that reduced government 
oversight and shifted key decision-making responsibility onto contractors. 
This approach—known as Total System Performance Responsibility, or 
TSPR—was intended to facilitate acquisition reform and enable DOD to 
streamline its acquisition process and leverage innovation and 
management expertise from the private sector. Specifically, TSPR gave a 
contractor total responsibility for the integration of an entire weapon 
system and for meeting DOD’s requirements. However, because this 
reform made the contractor responsible for day-to-day program 
management, DOD did not require formal deliverable documents—such as 
earned value management reports—to assess the status and performance 
of the contractor. The resulting erosion of DOD’s capability to lead and 
manage the space acquisition process magnified problems related to 
requirements creep and poor contractor performance. Further, the 
reduction in government oversight and involvement led to major 
reductions in various government capabilities, including cost-estimating 
and systems-engineering staff. The loss of cost-estimating and systems-
engineering staff in turn led to a lack of technical data needed to develop 
sound cost estimates. 

 

Page 9 

GAO-09-705T   


background image

 
 
 
 

Over the past decade, we have identified best practices that DOD space 
programs can benefit from. DOD has taken a number of actions to address 
the problems on which we have reported. These include initiatives at the 
department level that will affect its major weapons programs, as well as 
changes in course within specific Air Force programs. Although these 
actions are a step in the right direction, additional leadership and support 
are still needed to ensure that reforms that DOD has begun will take hold. 

Actions Needed to 
Address Space and 
Weapon Acquisition 
Problems 

Our work—which is largely based on best practices in the commercial 
sector—has recommended numerous actions that can be taken to address 
the problems we identified. Generally, we have recommended that DOD 
separate technology discovery from acquisition, follow an incremental 
path toward meeting user needs, match resources and requirements at 
program’s start, and use quantifiable data and demonstrable knowledge to 
make decisions to move to next phases. We have also identified practices 
related to cost estimating, program manager tenure, quality assurance, 
technology transition, and an array of other aspects of acquisition-program 
management that could benefit space programs. Table 1 highlights these 
practices. 

Page 10 

GAO-09-705T   


background image

 
 
 
 

Table 1: Actions Needed to Address Space and Weapon Acquisition Problems  

Before undertaking new programs  

 

Prioritize investments so that projects can be fully funded and it is clear where 
projects stand in relation to the overall portfolio.  

 

Follow an evolutionary path toward meeting mission needs rather than attempting to 
satisfy all needs in a single step.  

 

Match requirements to resources—that is, time, money, technology, and people—
before undertaking a new development effort.  

 

Research and define requirements before programs are started and limit changes 
after they are started.  

 

Ensure that cost estimates are complete, accurate, and updated regularly.  

 

Commit to fully fund projects before they begin.  

 

Ensure that critical technologies are proven to work as intended before programs 
are started.  

 

Assign more ambitious technology development efforts to research departments 
until they are ready to be added to future generations (increments) of a product.  

 

Use systems engineering to close gaps between resources and requirements before 
launching the development process.  

During program development  

 

Use quantifiable data and demonstrable knowledge to make go/no-go decisions, 
covering critical facets of the program such as cost, schedule, technology readiness, 
design readiness, production readiness, and relationships with suppliers.  

 

Do not allow development to proceed until certain thresholds are met—for example, 
a high proportion of engineering drawings completed or production processes under 
statistical control.  

 

Empower program managers to make decisions on the direction of the program and 
to resolve problems and implement solutions.  

 

Hold program managers accountable for their choices.  

 

Require program managers to stay with a project to its end.  

 

Hold suppliers accountable to deliver high-quality parts for their products through 
such activities as regular supplier audits and performance evaluations of quality and 
delivery, among other things.  

 

Encourage program managers to share bad news, and encourage collaboration and 
communication.  

Source: GAO. 

 

DOD is attempting to implement some of these practices for its major 
weapon programs. For example, as part of its strategy for enhancing the 
roles of program managers in major weapon system acquisitions, the 
department has established a policy that requires formal agreements 
among program managers, their acquisition executives, and the user 
community that set forth common program goals. These agreements are 
intended to be binding and to detail the progress a program is expected to 
make during the year and the resources the program will be provided to 

Page 11 

GAO-09-705T   


background image

 
 
 
 

reach these goals. DOD is also requiring program managers to sign tenure 
agreements so that their tenure will correspond to the next major 
milestone review closest to 4 years. Over the past few years, DOD has also 
been testing portfolio management approaches in selected capability 
areas—command and control, net-centric operations, battlespace 
awareness, and logistics—to facilitate more strategic choices for resource 
allocation across programs. 

Within the space community, cost estimators from industry and agencies 
involved in space have been working together to improve the accuracy and 
quality of their estimates. In addition, on specific programs, actions have 
been taken to prevent mistakes made in the past. For example, on the GPS 
IIIA program, the Air Force is using an incremental development 
approach, where it will gradually meet the needs of its users, use military 
standards for satellite quality, conduct multiple design reviews, exercise 
more government oversight and interaction with the contractor and spend 
more time at the contractor’s site, and use an improved risk management 
process. On the SBIRS program, the Air Force acted to strengthen 
relationships between the government and the SBIRS contractor team, and 
to implement more effective software development practices as it sought 
to address problems related to its flight software system. Correspondingly, 
DOD’s Office of the Under Secretary of Defense for Acquisition, 
Technology, and Logistics is asking space programs to take specific 
measures to better hold contractors accountable through linking award 
and incentive fees to program milestones. DOD interim space guidance 
also asks space programs to make independent technology readiness 
assessments at particular points in the acquisition process and to hold 
requirements stable. 

Furthermore, the Air Force, U.S. Strategic Command, and other key 
organizations have made progress in implementing the Operationally 
Responsive Space (ORS) initiative. This initiative encompasses several 
separate endeavors with a goal to provide short-term tactical capabilities 
as well as identifying and implementing long-term technology and design 
solutions to reduce the cost and time of developing and delivering simpler 
satellites in greater numbers. ORS provides DOD with an opportunity to 
work outside the typical acquisition channels to more quickly and less 
expensively deliver these capabilities. In 2008, we found that DOD has 
made progress in putting a program management structure in place for 
ORS as well as executing ORS-related research and development efforts, 
which include development of low cost small satellites, common design 
techniques, and common interfaces. 

Page 12 

GAO-09-705T   


background image

 
 
 
 

Legislation introduced in recent years has also focused on improving 
space and weapon acquisitions. In March, the Senate Committee on Armed 
Services introduced an acquisition reform bill which contains provisions 
that could significantly improve DOD’s management of space programs. 
For instance, the bill focuses on various measures, including increasing 
emphasis on systems engineering and developmental testing, instituting 
earlier preliminary design reviews and strengthening independent cost 
estimates and technology readiness assessments. Taken together, these 
measures could instill more discipline in the front end of the acquisition 
process when it is critical for programs to gain knowledge. The bill also 
requires greater involvement by the combatant commands in determining 
requirements and requiring greater consultation among the requirements, 
budget, and acquisition processes. In addition, several of the bill’s 
sections, as currently drafted, would require in law what DOD policy 
already encourages, but it is not being implemented consistently in 
weapon programs. In April, the House Committee on Armed Services 
introduced a bill to similarly reform DOD’s system for acquiring weapons 
by providing for, among other things, oversight early in product 
development and for appointment of independent officials to review 
acquisition programs. Both bills are moving forward in the Senate and 
House. 

The actions that the Air Force and Office of the Secretary of Defense have 
been taking to address acquisition problems are good steps. However, 
there are still more significant changes to processes, policies, and support 
needed to ensure reforms can take hold. With requirements, resource 
allocation, and acquisition processes led by different organizations, it is 
difficult to hold any one person or organization accountable for saying no 
to a proposed program or for ensuring that the department’s portfolio of 
programs is balanced. This makes it difficult for DOD to achieve a 
balanced mix of weapon systems that are affordable and feasible. For 
example, diffused leadership has been problematic with the GPS program 
in terms of DOD’s ability to synchronize delivery of space, ground, and 
user assets. GPS has a separate budget, management, oversight, and 
leadership structures for the space, ground, and user equipment segments.  
Several recent studies have also concluded that there is a need to 
strengthen leadership for military and intelligence space efforts. The 
Allard Commission reported that responsibilities for military space and 
intelligence programs are scattered across the staffs of the DOD and the 
Intelligence Community and that it appears that “no one is in charge” of 
national-security space. The HPSCI expressed similar concerns in its 
report, focusing specifically on difficulties in bringing together decisions 
that would involve both the Director of National Intelligence and the 

Page 13 

GAO-09-705T   


background image

 
 
 
 

Secretary of Defense. Prior studies, including those conducted by the 
Defense Science Board and the Commission to Assess United States 
National Security Space Management and Organization (Space 
Commission)

 have identified similar problems, both for space as a whole 

and for specific programs. While these studies have made 
recommendations for strengthening leadership for space acquisitions, no 
major changes to the leadership structure have been made in recent years. 
In fact, an “executive agent” position within the Air Force that was 
designated in 2001 in response to a Space Commission recommendation to 
provide leadership has not been filled since the last executive resigned in 
2007. 

In addition, more actions may be needed to address shortages of 
personnel in program offices for major space programs. We recently 
reported that personnel shortages at the EELV program office have 
occurred, particularly in highly specialized areas, such as avionics and 
launch vehicle groups. Program officials stated that 7 of 12 positions in the 
engineering branch for the Atlas group were vacant. These engineers work 
on issues such as reviewing components responsible for navigation and 
control of the rocket. Moreover, only half of the government jobs in some 
key areas were projected to be filled. These and other shortages in the 
EELV program office heightened concerns about DOD’s ability to use a 
cost-reimbursement contract acquisition strategy for EELV since that 
strategy requires greater government attention to the contractor’s 
technical, cost, and schedule performance information. In previous 
reviews, we cited personnel shortages at program offices for TSAT as well 
as for cost estimators across space. While increased reliance on contractor 
employees has helped to address workforce shortages, it could ultimately 
create gaps in areas of expertise that could limit the government’s ability 
to conduct oversight. 

Further, while actions are being undertaken to make more realistic cost 
estimates, programs are still producing schedule estimates that are 
optimistic while promising that they will not miss their schedule goals. The 
GPS IIIA program, for example, is asking the contractor to develop a larger 
satellite bus to accommodate the future GPS increments and to increase 
the power of a new military signal by a factor of ten, but the schedule is 3 
years shorter than the one achieved so far on GPS IIF. We recognize that 

                                                                                                                                    

4 Department of Defense. Report of the Commission to Assess United States National 
Security Space Management and Organization 

(Washington, D.C.: Jan. 11, 2001). 

Page 14 

GAO-09-705T   


background image

 
 
 
 

the GPS IIIA program has built a more solid foundation for success than 
the IIF program.  This foundation offers the best course to deliver on time, 
but meeting an ambitious schedule goal should not be the Air Force’s only 
measure for mitigating potential capability gaps. Last year, we also 
reported that the SBIRS program’s revised schedule estimates for 
addressing software problems appeared too optimistic. For example, 
software experts, independent reviewers, as well as the government 
officials we interviewed agreed that the schedule was aggressive, and the 
Defense Contract Management Agency has repeatedly highlighted the 
schedule as high risk. 

 
In conclusion, senior leaders managing DOD’s space portfolio are working 
in a challenging environment. There are pressures to deliver new, 
transformational capabilities, but problematic older satellite programs 
continue to cost more than expected, constrain investment dollars, pose 
risks of capability caps, and thus require more time and attention from 
senior leaders than well-performing efforts. Moreover, military space is at 
a critical juncture. There are critical capabilities that are at risk of falling 
behind their current level of service. To best mitigate these circumstances 
and put future programs on a better path, DOD needs to focus foremost on 
sustaining current capabilities and preparing for potential gaps. In 
addition, there is still a looming question of how military and intelligence 
space activities should be organized and led. From an acquisition 
perspective, what is important is that the right decisions are made on 
individual programs, the right capability is in place to manage them, and 
there is someone to hold accountable when programs go off track. 

Concluding Remarks 

 

 

Mr. Chairman, this concludes my prepared statement. I would be happy to 
answer any questions you or members of the subcommittee may have at 
this time. 

 
For further information about this statement, please contact Cristina 
Chaplain at (202) 512-4841 or chaplainc@gao.gov. Contact points for our 
Offices of Congressional Relations and Pubic Affairs may be found on the 
last page of this statement. Individuals who made key contributions to this 
statement include Art Gallegos, Assistant Director; Maria Durant; Arturo 
Holguin; Laura Holliday; Rich Horiuchi; Karen Sloan; Alyssa Weir; and 
Peter Zwanzig. 

Contacts and 
Acknowledgements 

Page 15 

GAO-09-705T   


background image

 
 
 
 

Appendix I: Scope and Methodology 

In preparing this testimony, we relied on our body of work in space 
programs, including previously issued GAO reports on assessments of 
individual space programs, common problems affecting space system 
acquisitions, and the Department of Defense’s (DOD) acquisition policies. 
We relied on our best practices studies, which comment on the persistent 
problems affecting space acquisitions, the actions DOD has been taking to 
address these problems, and what remains to be done. We also relied on 
work performed in support of our 2009 annual weapons system 
assessment. The individual reviews were conducted in accordance with 
generally accepted government auditing standards. Those standards 
require that we plan and perform the audit to obtain sufficient, appropriate 
evidence to provide a reasonable basis for our findings and conclusions 
based on our audit objectives. We believe that the evidence obtained 
provides a reasonable basis for our findings and conclusions based on our 
audit objectives. 

(120839) 

Page 16 

GAO-09-705T   


background image

 
 
 

 

This is a work of the U.S. government and is not subject to copyright protection in the 
United States. The published product may be reproduced and distributed in its entirety 
without further permission from GAO. However, because this work may contain 
copyrighted images or other material, permission from the copyright holder may be 
necessary if you wish to reproduce this material separately. 

 


background image

 
 
 
 
 
 
 
 
 
 
 
 
 

 
 
 
 
 

 

 

GAO’s Mission 

The Government Accountability Office, the audit, evaluation, and 
investigative arm of Congress, exists to support Congress in meeting its 
constitutional responsibilities and to help improve the performance and 
accountability of the federal government for the American people. GAO 
examines the use of public funds; evaluates federal programs and policies; 
and provides analyses, recommendations, and other assistance to help 
Congress make informed oversight, policy, and funding decisions. GAO’s 
commitment to good government is reflected in its core values of 
accountability, integrity, and reliability. 

The fastest and easiest way to obtain copies of GAO documents at no cost 
is through GAO’s Web site (www.gao.gov). Each weekday afternoon, GAO 
posts on its Web site newly released reports, testimony, and 
correspondence. To have GAO e-mail you a list of newly posted products, 
go to www.gao.gov and select “E-mail Updates.” 

Obtaining Copies of 
GAO Reports and 
Testimony 

Order by Phone 

The price of each GAO publication reflects GAO’s actual cost of 
production and distribution and depends on the number of pages in the 
publication and whether the publication is printed in color or black and 
white. Pricing and ordering information is posted on GAO’s Web site, 
http://www.gao.gov/ordering.htm.  

Place orders by calling (202) 512-6000, toll free (866) 801-7077, or  
TDD (202) 512-2537. 

Orders may be paid for using American Express, Discover Card, 
MasterCard, Visa, check, or money order. Call for additional information. 

Contact: 

Web site: www.gao.gov/fraudnet/fraudnet.htm 
E-mail: fraudnet@gao.gov 
Automated answering system: (800) 424-5454 or (202) 512-7470 

Ralph Dawn, Managing Director, dawnr@gao.gov, (202) 512-4400 
U.S. Government Accountability Office, 441 G Street NW, Room 7125 
Washington, DC 20548 

To Report Fraud, 
Waste, and Abuse in 
Federal Programs 

Congressional 
Relations 

Chuck Young, Managing Director, youngc1@gao.gov, (202) 512-4800 
U.S. Government Accountability Office, 441 G Street NW, Room 7149  
Washington, DC 20548 

Public Affairs 

 

Please Print on Recycled Paper