Korea Aerospace Research Institute
RFP/1
Request for Proposal for
the Development of
Reference Source System for GOCI-II
(Geostationary Ocean Color Imager-II)
January, 2016
Korea Aerospace Research Institute
169-84 Gwahak-ro, Yuseong-gu, Daejeon 305-806, Korea
http://www.kari.re.kr
Korea Aerospace Research Institute
RFP/2
Korea Aerospace Research Institute
RFP/3
Table of Contents
1.
TERMINOLOGY....................................................................................................... 5
2. INSTRUCTION TO BIDDER ............................................................................................... 6
2.1
STRUCTURE OF THE RFP ....................................................................................... 6
2.2
QUALIFICATION OF BIDDERS .................................................................................. 6
2.3
SUBMISSION OF PROPOSAL ..................................................................................... 6
2.3.1
Proposal Documents ................................................................................... 6
2.3.2
Number of Copies ....................................................................................... 6
2.3.3
Bid Closing Date ......................................................................................... 7
2.3.4
Method of Submittal .................................................................................... 7
2.3.5
Point of Contact .......................................................................................... 7
2.3.6
Statement of Compliance ............................................................................. 7
2.4
BIDDING SCHEDULE ............................................................................................... 7
2.5
VALIDITY OF PROPOSAL ......................................................................................... 8
2.6
BID BOND ............................................................................................................... 8
2.6.1
Amount of Bid Bond .................................................................................... 8
2.6.2
Bid Bond Establishment Method.................................................................. 8
2.6.3
Bid Bond Return.......................................................................................... 9
2.6.4
Contractor’s Bid Bond ................................................................................ 9
2.7
MODIFICATIONS ..................................................................................................... 9
2.8
NO CONTRACTUAL OBLIGATION ............................................................................ 9
2.9
ACCEPTANCE/REJECTION OF BIDS ......................................................................... 9
2.10
EVALUATION OF PROPOSAL .................................................................................... 9
2.11
SELECTION OF SUCCESSFUL BIDDER .................................................................... 10
2.12
LANGUAGE AND MEASUREMENT UNIT ................................................................. 10
2.13
PRICING REQUIREMENTS ..................................................................................... 10
2.14
WITHDRAWAL OF PROPOSAL ................................................................................ 10
2.15
PROPERTY OF PROPOSAL ..................................................................................... 10
3. DESCRIPTIONS AND REQUIREMENTS OF CHARACTERIZATION
SOURCE SYSTEM ........................................................................................ 11
3.1
DESCRIPTION OF CHARACTERIZATION SOURCE SYSTEM FOR SOLAR DIFFUSER
CHARACTERIZATION OF
GOCI-II .................................................................................... 11
3.2
REQUIREMENTS OF REFERENCE SOURCE SYSTEM FOR SOLAR DIFFUSER OF GOCI-
II
12
4. STATEMENT OF WORK ......................................................................... 14
4.1 SCOPE OF WORK ........................................................................................................ 14
4.2 MANUFACTURING SCHEDULE..................................................................................... 14
4.3 DELIVERY ITEMS ........................................................................................................ 15
4.4 TRAINING PROGRAM .................................................................................................. 15
4.5 FINAL ACCEPTANCE TEST (FAT) ................................................................................ 15
4.6 INCOMING TEST.......................................................................................................... 15
4.7 WARRANTY ................................................................................................................ 15
Korea Aerospace Research Institute
RFP/4
ANNEX
A1. CONTENTS OF SUGGESTED PROPOSAL ........................................ 18
A2. THE EVALUATION OF THE PROPOSAL .......................................... 22
5. GENERAL TERMS AND CONDITIONS ................................................ 24
Korea Aerospace Research Institute
RFP/5
1.
Terminology
Unless otherwise specified elsewhere, the following terms as used herein shall have the
meaning as assigned to them:
Bid means a solicitation of KARI for the submittal of the Proposal in response to the
RFP.
Bidder(s) means person(s) or corporation(s) who submits the Proposal in response to
the RFP.
Contract means a legal agreement to be executed between KARI and Contractor for
the Joint-development of the GOCI-II for the GEO-KOMPSAT-2B pursuant to the RFP.
Contractor or GOCI-II Contractor means the party selected by the KARI from among
the Bidders who has entered into the Bid.
GOCI-II or Geostationary Ocean Color Imager II means the GOCI-II System to be
jointly developed by the awarded Contractor and KARI for the GEO-KOMPSAT-2B
satellite.
KARI means Korea Aerospace Research Institute.
Proposal means any set of documents effectively submitted by a Bidder in response to
this RFP.
RFP or Request for Proposal means all documents, including those attached or
incorporated by reference, used for soliciting Proposal.
Successful Bidder means the Bidder selected by the evaluation committee who is
expected to proceed with the Contract negotiations and any other subsequent activities
for the formalization of the Contract.
System is a functioning entity comprising two or more subsystems, and described by a
system specification. GOCI-II System.
TBC means “To Be Confirmed” by KARI.
TBD means “To Be Determined” by KARI.
TBR means “To Be Resolved” mutually by KARI and the Contractor.
Korea Aerospace Research Institute
RFP/6
2. Instruction to Bidder
2.1
Structure of the RFP
This RFP consists of the following Parts:
1. Terminology
2. Instruction to Bidders
3. Descriptions and Requirements of the characterization source system
4. Statement of Work
Annex
A1
Contents of Suggested Proposal
A2
Evaluation of the Proposal
2.2
Qualification of Bidders
2.2.1
Bidder should have direct knowledge and first-hand experience in designing,
manufacturing, integrating, testing of RSS including solar simulator. Bidder shall
have at least five (5) years of experience in the above fields as a prime contractor.
Bidder shall be able to lead and take responsibility of all the RSS development
activities. Consortium cannot be allowed in this bidding.
2.2.2
The qualification of Bidders is solely KARI's decision, and disqualified or
unsuccessful Bidders shall not raise any objection regarding KARI's decision
thereupon.
2.3
Submission of Proposal
2.3.1
Proposal Documents
Bidders shall submit their Proposals in the following five (5) Volumes as presented in Annex
A1, Contents of Suggested Proposal, with any other required certificate and evidences under
the RFP.
Volume 1. Executive Summary
Volume 2. Technical Proposal
Volume 3. Statement of Work Proposal
Volume 4. Management Proposal
Volume 5. Price Proposal
A4 or letter-size paper shall be used (foldout is counted as 2 pages).
2.3.2
Number of Copies
Bidder’s proposal except for the Volume 5 (Price Proposal) shall be submitted in seven (7)
hardcopies. In addition, one (1) DVD-ROM disk or USB memory stick containing the
electronic files of the Proposal in Portable Document Format (PDF) shall be submitted.
For the Volume 5 (Price Proposal), one (1) hardcopy shall be submitted in separate sealed
envelope.
Korea Aerospace Research Institute
RFP/7
2.3.3
Bid Closing Date
The closing date and time for the Proposal is specified in the cover letter of this RFP. If any part
of the Proposal required under this RFP is submitted after the closing time, the entire Proposal
will not be accepted and will be excluded from further consideration.
2.3.4
Method of Submittal
The Proposal shall be hand-carried to the following KARI personnel or his designee:
Mr. Jung-Nam Cho
Procurement Team
Korea Aerospace Research Institute
169-84 Gwahak-ro, Yuseong-gu,
Daejeon 34133, Korea
Tel) 82-42-860-2613
E-mail) jncho@kari.re.kr
The Price Proposal shall be in a separate envelope.
2.3.5
Point of Contact
KARI’s point of contact for contractual matter is the same as in section 2.3.4.
KARI’s point of contact for technical matter is as follows;
Dr. Gmsil KANG
Payload Electronics Team
Korea Aerospace Research Institute
169-84 Gwahak-ro, Yuseong-gu,
Daejeon 34133, Korea
Tel) 82-42-860-2713
E-mail) wimikgs@kari.re.kr
2.3.6
Statement of Compliance
Bidders shall state any compliance or non-compliance with respect to the requirements and
instructions of this RFP.
2.4 Bidding Schedule
2.4.1 The following schedule is a tentative milestone for the eventual Contract and may be
changed at KARI’s sole discretion:
[1] Any questions on the RFP shall be directed to the contractual point of contact as specified
in paragraph 2.3.4 and 2.3.5. KARI will provide answers within a week by e-mail. For
Korea Aerospace Research Institute
RFP/8
the issues questioned by a bidder but every bidders should be aware of, KARI will
answer not only to the bidder who raised the question but also to all the other bidders.
[2] Bid Closing Date: Refer to the announcement of the RFP release
[3] Selection of the Successful Bidder and next ranking Bidder:
KARI will notify the successful bidder and the next ranking bidder just after selection of
the successful bidder by the special committee for the evaluation.
[4] Contract Negotiation:
KARI will notify the date when the negotiation starts. KARI and successful bidder shall
have a negotiation at KARI site for 7 days (calendar day), then KARI and successful
bidder shall come to agreement. If the negotiation cannot be agreed within 7 days of
calendar day, KARI will not negotiate anymore and will start negotiation with the next
ranking bidder.
2.4.2
If KARI and Successful Bidder fail to agree on the terms and conditions for the
eventual Contract, KARI will proceed the Contract negotiations with the Bidder of
the second rank without any obligations to the Successful Bidder. The negotiation
process will be continued with the Bidders of the next rank under the same condition
defined in the paragraph 2.4.1 [4] until the terms and conditions acceptable to KARI
are reached.
2.5
Validity of Proposal
Proposals shall be valid for one (1) year from the Bid Closing Date. Upon KARI’s written
request the validity of the proposal shall be extended by six (6) months.
2.6
Bid Bond
2.6.1
Amount of Bid Bond
Bidder shall establish a bid bond in favor of KARI not later than the Bid Closing Date and
submit the certificate to KARI along with its Proposal. The total amount of the bid bond shall
be at least five (5) percent of the total bidding price. The bond shall remain valid until three (3)
months from the Bid Closing Date.
2.6.2
Bid Bond Establishment Method
The bid bond in Section 2.6.1 hereinabove shall be in the form of an irrevocable letter of credit
by the Woori Bank Daejeon Branch (address: 29 Munye-ro, Seo-gu, Daejeon, 35241 Korea,
Tel: +82-42-488-9704). The bond shall be available by KARI's draft at sight drawn on the Bank,
accompanied by the statement of KARI stating that Bidder has refused to enter into a Contract
with the terms and conditions in the Proposal as amended, if any, that Bidder has hindered the
fair bidding by fraud or misrepresentation, or that Bidder has withdrawn its Proposal after the
Bid Closing Date. The bid bond shall contain the substantial part of the terms and conditions of
the bond, date of establishment, account, amount, payment terms, and date of expiry, etc.
Korea Aerospace Research Institute
RFP/9
2.6.3
Bid Bond Return
The bid bonds except for those of the Successful Bidders within the rank determined by the
special committee will be released upon the instructions of KARI to the unsuccessful Bidders,
without interest, promptly after the special committee’s determination of the Successful Bidders
rank. The bid bonds of the Successful Bidders within the rank shall be likewise released only
when KARI decides not to enter into a Contract after negotiation.
2.6.4
Contractor’s Bid Bond
When the Contract is executed, the bid bond shall be included in the performance bond.
2.7
Modifications
2.7.1
After the Bid Closing Date, Bidders shall not amend, modify, or supplement the
Proposal, or submit any other documents to KARI without KARI's written request.
2.8
No Contractual Obligation
2.8.1
This RFP shall not be interpreted as an offer for a Contract or any type of guarantee
by KARI. It is KARI's sole discretion whether or not to allow the Contract award to
any Bidder. KARI owes no responsibility or obligation to select the Contractor
among Bidders.
2.8.2
This solicitation for the Proposal shall neither be construed to create an obligation on
KARI to enter into a contractual instrument, nor shall it serve as a basis for any claim
for reimbursement of costs for the effort to prepare, submit, amend, revise or
supplement the Proposal, and other related documents, expended by Bidder
regardless of whether or not Bidder is successful in receiving an award as a result of
the solicitation.
2.9
Acceptance/Rejection of Bids
KARI reserves the right to accept or reject any Bid, and to amend the Bidding process and reject
all Bids at any time prior to the award of the Contract without thereby incurring any liability to
the affected Bidder(s), nor is KARI under any obligation to inform the affected Bidder(s) of the
background for its action.
2.10 Evaluation of Proposal
The evaluation of the Proposals will be made by Korean evaluation committee. The guideline
of the evaluation is described in Annex A2, which are for information only, and the evaluation
committee reserves the right to modify the guidelines without any prior notification to Bidders.
Korea Aerospace Research Institute
RFP/10
2.11 Selection of Successful Bidder
2.11.1
The Successful Bidder will be selected by the evaluation committee among the
Bidders subject to the evaluation of the Proposals.
2.11.2
When the Successful Bidder is notified, the Bidder in the next ranking and
unsuccessful Bidders will also be notified. Contract negotiation will be started with
the Successful Bidder, and in the event mutually agreeable terms and conditions are
not reached with the Successful Bidder in 7 days (calendar day), KARI may proceed
with the Contract negotiations with the next ranking Bidder without undertaking a
new bidding process.
2.11.3
In case KARI initiates the Contract negotiations with the next ranking Bidder as
specified in Section 2.11.2 above, the Bidder shall occupy the position as Successful
Bidder and assume any obligations imposed upon the Successful Bidder under this
RFP.
2.12 Language and Measurement Unit
2.12.1
The Proposal and any documents submitted to KARI under the RFP and
communication shall be made in English and measurements and quantities shall be
in "Système Internationale" (SI) system of units.
2.12.2
The primary language for the Contract shall be in English.
2.13 Pricing Requirements
2.13.1
Any currency quoted in the Proposal shall be expressed in U.S. dollars and shall be
broken down.
2.14 Withdrawal of Proposal
Bidder may withdraw its Proposal at any time before the Bid Closing Date. Withdrawal shall
be made in written form, and shall be received by KARI before the Bid Closing Date.
2.15 Property of Proposal
All documents including proposal, data or information in any type of media submitted in
response to the RFP shall become the property of KARI even when the bidder may withdraw
its proposal specified in section 2.14.
Korea Aerospace Research Institute
RFP/11
3. Descriptions and Requirements of Characterization Source System
3.1
Description of characterization source system for solar diffuser
characterization of GOCI-II
GOCI-II, which is under development, is a next generation of GOCI (Geostationary Ocean
Color Imager), the 1st ocean color imager in the world operating on the geostationary orbit.
GOCI has been monitoring ocean color around the Korean Peninsula in order to detect, monitor,
quantify, and predict short term changes of coastal ocean environment for marine science
research and application purpose.
In-orbit solar calibration using on-board calibration device
There are on-board calibration devices which are called SD (Solar diffuser) in the GOCI-II for
in-orbit solar calibration.
Purpose of the on-board calibration device is to acquire the SUN image which will be used as
known reference uniform source for radiometric calibration.
Characterization of on-board calibration device using the GOCI-II
Scattering characteristics of the on-board calibration device will be measured along solar
incident angle defined in Fig. 3.1.1.
For characterization of scattering of SD, the GOCI-II will acquire the image of solar simulator
with open view and SD view. The image of solar simulator captured by GOCI is provided in
Fig. 2.
Figure 3.1.1. Definition of incident angle
Y
Z
Sun direction
X
Coordinates of sun
direction in
Reference Pointing
Frame
X = cos().sin()
Y = sin().sin()
Z= cos()
Korea Aerospace Research Institute
RFP/12
3.2
Requirements of reference source system for solar diffuser of GOCI-
II
[RSS-100] Reference source system (RSS) for SD (solar diffuser) characterization shall consist
of solar simulator and moving system of solar simulator.
[RSS-110] RSS shall be compatible with ISO5 (Class 100) defined in ISO 14644-1 cleanroom
standards in ambient condition.
[RSS-120] It shall be possible to detach the solar simulator from the moving system and the
solar simulator shall be possible to operate solely.
[RSS-130] Power for solar simulator and moving system : 200V ~ 240V, 50Hz/60Hz
[RSS-140] Minimum length of power cables for RSS shall be 10 meter.
[RSS-150] Control system for RSS (solar simulator and moving system) shall be provided.
(such as computer on moving desk)
[RSS-200] The solar simulator of RSS shall simulate the solar spectral irradiance at
Geostationary orbit. Therefore its output shall be 1 SUN with AM0 filter.
[RSS-210] The solar simulator of RSS shall provide spectral region from 300 nm ~ 1100 nm
with Ozon free.
[RSS-220] The solar simulator of RSS shall provide the geometrical sun with 0.5 degree (full
angle) angular size which means field angle of output image.
[RSS-230] The solar simulator of RSS shall illuminate a target larger than 400mm diameter
circle.
[RSS-240] The solar simulator of RSS shall have attenuation function of output irradiance from
1 ~ 1000 continuously. Minimum number of distinct attenuation level shall be larger than 100
step. (1,20,30, …., 980, 990,1000)
[RSS-250] Non-uniformity of spatial irradiance of the solar simulator shall comply with Class
A according to ASTM 927-05 standard. Therefore, non-uniformity of spatial irradiance of the
solar simulator shall be less than 3%. This requirement shall be verified with respect to ASTM
E927-50 Standard Class.
[RSS-251] Non-uniformity of spatial irradiance defined by RSS-250 shall be kept with
attenuation.
[RSS-270] Spectral match of the solar simulator shall be class A according to ASTM 927-05
standard. This requirement shall be verified with respect to ASTM E927-50 Standard Class.
Korea Aerospace Research Institute
RFP/13
[RSS-271] Spectral match of the solar simulator shall be kept with attenuation.
[RSS-280] Temporal instability of irradiance shall comply with Class A according to ASTM
927-05 standard. This requirement shall be verified with respect to ASTM E927-50 Standard
Class.
[RSS-281] Short term temporal instability of irradiance shall be less than 0.2% during 30
minutes. This requirement shall be verified with respect to ASTM E927-50 Standard Class.
[RSS-282] Mid term temporal instability of irradiance shall be less than 0.5% during 12 hours.
This requirement shall be verified with respect to ASTM E927-50 Standard Class.
[RSS-283] Long term temporal instability of irradiance shall be less than 1% during 24 hours.
This requirement shall be verified with respect to ASTM E927-50 Standard Class.
[RSS-284] Repeatability of irradiance shall be less than 1%.
[RSS-290] The solar simulator of RSS shall provide a monitoring function of output power
variation. The output power stability (irradiance) shall be monitored within 0.1% accuracy.
[RSS-300] The solar simulator of RSS shall provide the shutter configuration to acquire dark
measurement with the lamp ON.
[RSS-310] Aiming cube on the solar simulator shall be implemented on the top of solar
simulator and LOS (Line of Sight) shall be characterized with respect to this cube.
[RSS-320] Protecting cover for aiming cube shall be provided.
[RSS-320] Working distance for the solar simulator is 3m (TBC).
[RSS-500] Moving system for RSS shall provide automatic movement of solar simulator along
3 axis as follows;
Korea Aerospace Research Institute
RFP/14
Fig. 3.2.1 Overview of test configuration of solar diffuser using the RSS
Zo: nominal position of Z axis, 1.5m (TBC)
Xo: nominal position of X axis which will be center of the solar simulator
Yo: nominal position of X axis which will be center of the solar simulator
Z: displacement with respect to Zo, 0.2m (TBC)
X: displacement with respect to Xo, 0.3m (TBC)
Y: displacement with respect to Yo, 0.3m (TBC)
Rotation around Z axis: 15 degree (TBC)
Rotation around X axis: 15 degree (TBC)
Fig.2 Example of image capture of solar simulator by the GOCI at zero theta angle (around
0.52 degree)
[RSS-510] Moving system for RSS shall be equipped with caster and fixation system.
4. Statement of Work
4.1 Scope of Work
Contractor shall provide design description of RSS before manufacturing in order to check
compliance for requirement specifications.
Contractor shall provide test methods with detailed description for requirement specifications.
4.2 Manufacturing Schedule
Contractor shall provide overall schedule for RSS development.
Final design for RSS shall be reviewed by KARI before manufacturing in CDR phase.
Korea Aerospace Research Institute
RFP/15
4.3 Delivery items
All H/W, S/W and documents related to the operation of RSS shall be delivered to KARI.
Table 1. H/W and S/W Deliverables
No.
Description
Quant
ity
Delivery Date
(Week)
1
RSS (Solar simulator + Moving system)
1 set
EDC + 28 W
2
S/W for solar simulator operation
1 set
EDC + 28 W
3
S/W for moving system
1 set
EDC + 28 W
4
Reusable shuttle case for transporting
1 set
EDC + 28 W
5
Lamp spare
2 set
EDC + 28 W
6
Control system including moving desk
1 set
EDC + 28 W
Table 2. CDRL (Contract Data Requirements List)
No.
Description
Delivery Date
(Week)
1
Design documents for CDR review
CDR – two weeks
2
EIDP (3D drawings for interface)
EDC + 28 W
3
Operation manual for Solar simulator
EDC + 28 W
4
Operation manual for moving system
EDC + 28 W
5
Test reports for all requirement specifications
EDC + 28 W
6
Procedure for packing/unpacking transport configuration
EDC + 28 W
4.4 Training program
Contractor shall provide training program for RSS operation for three persons.
4.5 Final Acceptance Test (FAT)
RSS shall be fully verified through FAT in manufacturer site before delivery. Tests results shall
be presented by the Contractor, and the EIDP (End Item Data Package) shall be approved by
KARI.
4.6 Incoming test
Contract shall define test items for incoming test and shall perform incoming test in KARI site.
4.7 Warranty
Notwithstanding the prior inspection or Final Acceptance by KARI, Contractor warrants that:
4.7.1
RSS system shall be in good working order and free from all defects in workmanship
and materials and shall comply with the requirements of this Contract. Such warranty
shall continue during two years (TBC) after final delivery.
Korea Aerospace Research Institute
RFP/16
4.7.2
Upon the receipt of written notification from KARI that any Deliverable Item
provided by Contractor is defective of non-conforming, Contractor shall repair or
replace, at Contractor’s expense within a month.
Korea Aerospace Research Institute
RFP/17
ANNEX
Korea Aerospace Research Institute
RFP/18
A1. Contents of Suggested Proposal
Korea Aerospace Research Institute
RFP/19
A1.1 Volume 1 : Executive Summary
This volume shall include the summary of the Volumes 2, 3 and 4. The summary of “Statement
of Compliance” in table A1-1 shall be provided in tabular form. It shall include all requirements
and instructions in section 3 and 4.
For the PC and NC of Terms and Conditions requirements, detailed explanation shall be
described in the Remarks column. The depth of description will directly affect the evaluation
score.
No price information shall be included in Volume I. And the bidder shall submit E/L(Export
License) acquiring plans, if needed.
Table A1-1 Statement of Compliance Format
RFP
Sections
Descriptions Proposal
Sections
Compliance
Status
Remarks
RFP section
Title or
contents
Proposal
section and
page number
C: Fully comply
NC: Not comply
PC: Partial
comply
Key
performance,
summary shall be
Described
A1.2 Volume 2 : Technical Proposal
Bidder shall describe this chapter in compliance with RFP requirements.
Bidder shall describe this technical proposal with as many illustrations as possible to
make it clear.
2.1
Suggested RSS Design Description
2.2
Compliance Description to the RSS Requirements
2.4
RSS Test Plans
2.5
RSS Verification Matrix
Table 1. CSS Verification matrix
RFP req. Verification
Item
Description
Verification Method
(Inspection, Similarity,
Remark
Korea Aerospace Research Institute
RFP/20
A1.3 Volume 3 : Statement of Work Proposal (Joint Development Proposal)
3.1 Scope of Work
3.2 Manufacturing schedule
3.3 Delivery items
3.4 Training Program
3.5 FAT
3.6 Incoming Test
3.7 Warranty
A1.4 Volume 4 : Management Proposal
4.1 General
4.1.1 Introduction of the Company
- General organization and company’s resources including financial structures and
status
4.2 Technical Management
4.2.1 RSS Project Management Plan
4.3 Human Resources Management
4.3.1 Human Resources Management Plan
4.4 Technical Heritage Directly Related to RSS
4.5 Schedule Plan
Analysis,
Test,
Demonstration)
Korea Aerospace Research Institute
RFP/21
A1.5 Volume 5 : Price Proposal
This volume shall contain a firm and fixed price offer to perform the work specified in
"Statement of Work Scope" supported by a detailed cost breakdown.
5.1
Suggestion of the Payment Schedule
Bidders shall propose Progress Payment Schedule conforming to major milestones on the
Program Schedule.
Korea Aerospace Research Institute
RFP/22
A2. The Evaluation of the Proposal
Korea Aerospace Research Institute
RFP/23
A2.1 General
The evaluation of the Proposals will be performed by the evaluation committee in KARI.
The following evaluation guidelines are for information only and the evaluation committee
reserves the right to modify the guidelines without any prior notification to Bidders.
A2.2 Principles of Evaluation
A2.2.1 The evaluation shall be made based only on the Proposal. The submitted proposal will
be evaluated for both the technical part and the price part as a whole according to a firm and fix
policy (No BAFO: Best And Final Offer). The technical parts shall be evaluated first, and then
only proposals which meet the minimum requirements confirmed by the evaluation committee
shall be selected. The price proposals of the selected proposals shall be opened and the points
which are evaluated with respect to the lowest price proposal and the technical points shall be
summed. The ratio between the technical points and the price points shall be between 70:30 to
90:10, and the exact ratio shall be decided by KARI.
A2.2.2 The result of the evaluation is at the proposal evaluation committee’s discretion based
on the evaluation process and any Bidders shall not raise any objection regarding proposal
evaluation committee’s decision thereupon.
Korea Aerospace Research Institute
RFP/24
5. General Terms and Conditions
Korea Aerospace Research Institute
RFP/25
Preamble
This Contract is made on , 2016 by and between Korea Aerospace Research
Institute (“KARI”) established under the law of the Republic of Korea with its principal office at
169-84 Gwahak-ro, Yuseong-gu, Daejeon 34133 Korea, and (“Contractor”)
established under the law of with its principal office
at .
Witnesseth
WHEREAS, KARI has undertaken the task of implementing the GOCI-II payload system
development program;
WHEREAS, KARI acknowledged the necessity of design and installation of the reference
source system which is equipped with a solar simulator for characterization of on-board
calibration devices of the GOCI-II;
WHEREAS, Contractor represents that it has direct knowledge and first-hand experience in
developing, manufacturing and supplying the reference source system.
NOW THEREFORE, in consideration of the premises and the mutual covenants hereinafter
contained, KARI and Contractor have agreed as follows:
Korea Aerospace Research Institute
RFP/26
Article 1. Definition
In this Contract, the following words and phrases shall have the meanings as indicated below,
unless the context wherein they are used clearly indicates another meaning:
1.1 Associates mean all individual or legal entities organized under public or private law,
who shall act, directly or indirectly, on behalf of KARI or Contractor, or at the direction
of either Party to this Contract to fulfill the obligations undertaken by such Party in this
Contract, including, without limitation, the employees of each Party, their suppliers and
Subcontractors.
1.2
Contract means this Contract for the development of the reference source system for
characterization of on-board calibration devices of GOCI-II including Appendices as
attached hereto, and all amendments that may be subsequently agreed to by the
Parties in accordance with the terms and conditions of this Contract.
1.3
Contractor means .
1.4
Contract Price means the amount of Contract. If there is any change in Contract Price
due to any reason, then the Contract Price means current total amount of Contract.
1.5
Deliverable Data means any technical data as enlisted in Appendix B-1 “Statement of
Work” that Contractor shall deliver to KARI and any related data thereof under this
Contract.
1.6
Deliverable (Delivery) Item(s) means RSS including Solar simulator and Moving
system, Deliverable Data, and information as enlisted in Appendix B-1 “Statement of
Work” that Contractor shall deliver to KARI.
1.7
EDC means the Effective Date of this Contract.
1.8
Event(s) of Force Majeure means any act of God, war, whether or not declared, act
or failure to act of any government in its sovereign capacity, fire, earthquake, flood,
epidemic, quarantine, nuclear incident, or any other act beyond the reasonable control
and without the fault of either Party or its Subcontractors.
1.9
Factory Acceptance means KARI’s pre-shipment inspection or audit including the
testing activities for Deliverable Item at Contractor’s facility.
Korea Aerospace Research Institute
RFP/27
1.10
KARI means Korea Aerospace Research Institute.
1.11
RSS means Reference source system including solar simulator and moving system
of solar simulator.
1.12
Party or Parties means KARI or Contractor, or both, according to the context.
1.13
Incoming Test and Acceptance means final acceptance by KARI of the Deliverable
Item at KARI site in accordance with Article 12 “
Incoming Test and Acceptance”.
1.14
Subcontract means any subcontract, including purchase orders and all similar forms
of agreements at any tier under this Contract.
1.15
Subcontractor means a contractor under any Subcontract including suppliers and
vendor.
1.16
Third Party(ies) means any individual or legal entity other than the Associates and
the Parties.
1.17
Work(s) means whole or any part of the work, but not limited to review meeting,
delivery, installation, test, training, warranty and maintenance, to be executed by a
Contractor in accordance with this Contract.
Korea Aerospace Research Institute
RFP/28
Article 2. Objective
2.1
The objective of this Contract is to procure the reference source system including solar
simulator for characterization of on-board calibration devices of GOCI-II. To
accomplish this objective, Contractor shall perform all the Works under this Contract
required for design, manufacture, test, installation, training, warranty and maintenance
as well as the delivery of Deliverable Item to meet the requirements and specification
of this Contract.
Article 3. Contract Documents
3.1
This Contract shall comprise the following documents, as amended from time to time
by written agreement by and between both Parties:
[A] Terms and Conditions
[B] Appendices
B-1. Statement of Work
B-2. TBD
B-3. TBD
B-4. TBD
3.2
In the event of any inconsistency or discrepancy between or among the Contract
documents as listed in Article 3.1 above, the Contract documents shall be applied in
the decreasing order of precedence.
3.3
In the event of any dispute or difference between the Parties in the interpretation of
this Contract as a result of the application of the Appendices as specified in Article 3.1,
Contractor's Proposal dated ____________ submitted to KARI in anticipation of this
Contract in response to KARI's Request for Proposal dated ____________ shall be
used as a reference document to identify and clarify the intention and understanding
of the Parties as contemplated in this Contract, and both Parties shall in good faith
seek an agreement or a compromise acceptable to both Parties without modification
or amendment to this Contract.
Korea Aerospace Research Institute
RFP/29
Article 4. Contract Price
4.1
For the full, satisfactory and timely performance of the Work by the Contractor in
accordance with the provisions of the Contract, KARI hereby agrees to pay to the
Contractor USD (TBD), in accordance with the terms of payment
as stipulated in Article 5 “Terms of Payment”.
4.2
The Contract Price as specified in Article 4.1 above shall be firm and fixed price that is
not subject to any escalation or to any adjustment or revision by reason of the increase
of actual costs incurred by Contractor in the performance of the Work under this
Contract, unless otherwise agreed to by both Parties under Article 20 “Changes”.
4.3
The Contract Price as specified in Article 4.1 above shall be comprised of the following
items.
Items
Qty
Price (USD)
RSS(Solar simulator + Moving system
1set
S/W for solar simulator operation
1set
S/W for moving system
1set
Reusable shuttle case for transporting
1set
Lamp spare
2set
Control system including moving desk
1set
Total
4.4
All banking charges incurred in Korea shall be borne by KARI and those charges
incurred outside Korea shall be borne by Contractor.
Korea Aerospace Research Institute
RFP/30
Article 5. Terms of Payment
5.1 Payment Schedule
5.1.1
Payment shall be executed after the establishment of performance bond in accordance
with Article 6 “Performance Bond”.
5.1.2
KARI shall pay to Contractor the Contract Price as stipulated in Article 5.1 in
accordance with the following schedule:
No.
Payment milestone
(in Month)
Payment due date
Payment
(USD/€)
Percentage of
Contract Price (%)
1
EDC
EDC+ 1M
2
3
4
5
Total
100 %
* “EDC” means the Effective Date of this Contract in accordance with Article 22.1
“Effective Date of Contract”.
5.2
Billing Procedure
5.2.1
All invoices Contractor submits for payment shall be in duplicate signed by an
authorized company official and received by KARI at least thirty (30) days before the
payment due dates as specified in Article 5.1.
5.2.2
All payments shall be made in US dollars by telegraphic transfer to the bank account
as designated by Contractor in its invoices. And KARI shall remit the payment within
thirty (30) days after KARI’s receipt of Contractor’s invoice.
5.3
Suspension of Payment
5.3.1
Notwithstanding any provisions of this Contract, if any payment milestone as set forth
in Article 5.1.2 has not been accomplished for any reasons attributable to Contractor,
KARI may, with an advance notice, suspend such payment due until both Parties agree
that the delayed payment milestone has been accomplished.
5.3.2
In the event of KARI's suspension of payment under Article 5.3, Contractor shall
nevertheless continue to perform its obligations under this Contract regardless of
whether KARI is entitled to suspend the payment.
Korea Aerospace Research Institute
RFP/31
5.4
Deduction of Payment
5.4.1
All losses, costs, charges, damages and expenses which KARI incurs or sustains by
reason of any act, default or omission of the Contractor in the performance of the
Contract and any other amounts which KARI is entitled to receive from the Contractor
may be deducted from any payment that may be or become due to the Contractor from
KARI.
5.4.2
A prior written notice given by KARI accompanied with documents stating the amount
due to KARI referred to in Article 5.4.1 and the reason of deduction shall be prima facie
evidence of the matters stated herein.
Korea Aerospace Research Institute
RFP/32
Article 6. Performance Bond
6.1
Contractor shall establish a performance bond within three (3) weeks after EDC in
favor of KARI in the value of ten percent (10 %) of the Contract Price, in the form of an
irrevocable and unconditional standby letter of credit available by KARI’s draft at sight.
6.2
The entire amount covered by the performance bond shall be payable to KARI on
demand together with KARI’s written statement to the effect:
(a) that there was a default of the Contractor in the performance of the Contract
(including Subcontractor’s default under the Subcontract), or
(b) that any amount KARI is entitled to receive from Contractor has not been paid by
Contractor to KARI through any other means, or
(c) that this Contract was terminated by Contractor’s breach as specified in Article
18.2.
Whenever any amount has been withdrawn by KARI due to such cases of (a) and
(b) as above, performance bond shall be replenished.
6.3
The letter of credit shall be issued by first class international bank acceptable to KARI.
The letter of credit shall be drawn in favor of KARI and advised through the Woori Bank
(Daejeon Branch at 29 Munye-ro, Seo-gu, Daejeon, 35241 Korea, Tel: +82-42-488-
9704, (Ext. 312)/ Fax: +82-505-003-0759) and shall remain valid until the end of
warranty expiration. The letter of credit shall not be amended, modified or canceled
without KARI's prior written consent.
6.4
It is hereby agreed between the Parties that payment from the Performance Bond
under this Article 6 shall not affect any other KARI's rights, privileges, interests or
remedies under this Contract or the applicable law.
Korea Aerospace Research Institute
RFP/33
Article 7. Deliveries
7.1
General
7.1.1
Contractor shall deliver Deliverable Item in accordance with the defined schedule and
method as set forth in Appendix B-1 “Statement of Work” and the delivery shall be
deemed to have occurred only when the Incoming Test and Acceptance has been
successfully completed at KARI site.
7.1.2 Contractor shall bear any charges or costs of whatsoever nature that are incurred in
relation to such delivery or provision until such delivery or provision is duly made under
this Contract without any non-conformity and accepted in accordance with Article12
“Incoming Test and Acceptance” hereof, and shall keep KARI free from any such
charges and costs.
7.1.3
Contractor agrees that delivery or provision of time and place under this Contract,
whether specifically provided for or not, or in subsequent amendments thereto, are of
the essence of this Contract.
7.1.4
Contractor shall be responsible for all applicable taxes imposed outside Korea
including any customs duties and charges of any nature levied on Deliverable Item,
spare parts, spare materials, tools, consumables and ancillary equipment as well as
any charges associated with the transportation.
7.2
Delivery to KARI
7.2.1
Contractor shall deliver Deliverable Item under the rule of DAP (Delivery At Place in
accordance with the Incoterms 2010) KARI in accordance with the delivery schedule
of this Contract.
7.2.2
To obtain import certification, Contractor shall notify KARI by e-mail (address is
“wimikgs@kari.re.kr” for Ms. Gm-Sil KANG and “jncho@kari.re.kr” for Mr. Jung-Nam
CHO) fourteen (14) calendar days prior to each shipment with one set of proforma
invoice and packing list specifying the number of boxes, name of Items, unit price, and
size and volume of each container or box to be shipped. As soon as each shipment as
provided for in this Article is made, Contractor shall send one (1) copy of the following
shipping documents to KARI by e-mail;
(a) Clean on board vessel bill of lading/or airway bill of lading,
Korea Aerospace Research Institute
RFP/34
(b) Commercial invoice,
(c) Packing list,
(d) Weight and measurement list,
(e) Manufacturer's Inspection Report,
(f) Certificate of Origin, and
(g) Export License (if possible).
Korea Aerospace Research Institute
RFP/35
Article 8. Delay
8.1
Excusable Delay
8.1.1
Neither Party shall be responsible to the other Party for any delay in performing its
obligations under this Contract due to any Events of Force Majeure.
8.1.2
The Party whose performance of obligations hereunder has been affected by any
Events of Force Majeure shall notify the other Party within ten (10) days thereafter by
sending a detailed statement and sufficient evidence with respect thereto, and
promptly of any subsequent change in the circumstances, if any. The affected Party
shall exercise its best efforts under the circumstances to remove or remedy the Events
of Force Majeure and the effects thereof and resume full performance hereof as soon
as possible.
8.1.3
Notwithstanding Article 8.1.1 hereof, any such delay that has not been notified to the
other Party or any delay of performance of the affected Party falling due after delay,
failure or incompleteness in exercising the pertinent best efforts to remove or remedy
the pertinent Events of Force Majeure or the effects thereof pursuant to Article 8.1.2
hereof shall not be excused for any reason whatsoever.
8.1.4
The Party who has received or is entitled to duly receive the notice of Events of Force
Majeure under Article 8.1.2 hereof may suspend performance of its obligations which
shall be due subsequent to such Events of Force Majeure, until the other Party has
effected such delayed performance to the full extent after and in view of such Events
of Force Majeure.
8.2
Non-Excusable Delay
8.2.1
In the event that, unless otherwise excused by virtue of this Contract, any reason
attributable to KARI or the governing or applicable law, Contactor delays the provision
or delivery of Deliverable Items as stipulated under this Contract, Contractor shall pay
for damages as defined in the Article 8.2.2 to KARI as a result of such delay.
8.2.2
Contractor acknowledges and agrees that the timely provision or delivery of the
Deliverable Item as stipulated under this Contract or its performance of other
obligations under this Contract is essential to KARI, and that such delay as provided
for in Article 8.2.1 hereof may cause substantial financial loss or damage to KARI’s
Korea Aerospace Research Institute
RFP/36
rights, interests, privileges and benefits, which may not be assessable or recoverable.
Both Parties therefore specifically agree that in the event of such loss or damage
caused by delay attributable to Contractor, its Subcontractor or any of its agents,
Contractor shall pay KARI as liquidated damages zero point one five percent (0.15%)
of Contract Price per day of such delay. In no case, however, shall the aggregated
liquidated damages exceed ten percent (10%) of Contract Price. It is also agreed by
both Parties that KARI shall be entitled to terminate this Contract for Contractor’s
breach, only if the aggregated liquidated damages under this Article, excluding those
days of delay excused by KARI in writing, exceeds ten percent (10%) of the Contract
Price.
8.2.3
This Article shall not affect other remedies, rights, privileges, interests, benefits of KARI
under this Contract or the governing or applicable law. Contractor agrees that any right
of KARI under this Article is not an alternative or substitute to other remedies, rights,
privileges, or interests of KARI, and that Contractor’s correction of such defect or non-
conformity under this Article does not relieve Contractor from any liability to KARI which
may arise under this Contract of the governing or applicable law as a result of such
defect or non-conformity.
8.2.4
For the purpose of this Article, any action or omission of Contractor’s Subcontractor,
agent, or servant, de facto or de jure, shall be deemed to be Contractor’s own.
Korea Aerospace Research Institute
RFP/37
Article 9. Taxes and Duties
9.1
In the event taxes are charged in Korea, KARI shall be fully responsible for payment
of such taxes. Contractor shall be fully responsible for the payment of all applicable
taxes imposed outside Korea including any customs duties and charges.
9.2
Neither Party shall be responsible for paying the customs duties, and related taxes,
fees, or charges for the personnel and the personal belongings of the other Party.
9.3
The Contractor shall further comply with instructions KARI may issue from time to time
in order to facilitate any exemptions or reductions from customs duties and other taxes
that might be levied on KARI and shall impose the same obligations on its
Subcontractors.
Korea Aerospace Research Institute
RFP/38
Article 10. Intellectual Property
10.1
KARI shall own and have a right to use, without any obligation, all the Deliverable Items
provided by Contractor in its performing this Contract. Contractor shall take all
necessary precautions so that all the Deliverable Items supplied hereunder shall be
free from infringement of any patent, design patent, trademark, utility model or any
other industrial property right, copyright, license or any other right thereunder of any
Third Party.
10.2 In the event that any Party other than Contractor claims or threatens to claim
infringement by KARI with respect to such use of the Deliverable Items, Contractor
shall defend, hold harmless, and indemnify KARI from such infringement claims.
10.3 This Article will survive the completion of the Contract, any termination, cancellation or
expiration of the Contract in any manner whatsoever.
Korea Aerospace Research Institute
RFP/39
Article 11. Factory Acceptance
11.1 The Factory Acceptance of RSS shall occur only after:
(a) all specified tests to be performed by the Contractor under the Contract for the
RSS have been completed in accordance with the Contract; and
(b) the Contractor has demonstrated to KARI that the RSS meets the specifications
and requirements in this Contract; and
(c) all Works and conditions under the Contract to be fulfilled by the Contractor prior
to the shipment of RSS have been met,
in which case KARI shall accept, in writing, the RSS subject to the provisions set
forth below.
11.2
Subject to the conditions as set forth in Article 11.1 above, a Factory Acceptance of
shall be occurred only when the FAT (Final Acceptance Test) has successfully
completed at Contractor site in accordance with Appendix B-1 “Statement of Work”.
After the FAT, KARI’s authorized representative shall notify the result of FAT in writing.
If KARI determines that RSS is unacceptable, it shall notify the Contractor, in writing,
the reasons therefore.
11.3
If RSS is determined to be unacceptable, Contractor shall, at its expense, promptly
repair or replace RSS so that it shall comply with the Contract specifications and
requirements, and Contractor shall hold the additional FAT of such repaired or replaced
RSS for KARI’s confirmation. The Contractor shall present to KARI the root cause and
the result of such repair or replacement on the additional FAT. Such repaired or
replaced RSS shall be accepted in accordance with the requirements of Article 11.1.
11.4
For the FAT, KARI, at all times during the performance of this Contract, shall have the
right to do the following activities at the Contractor’s facilities or other relevant facilities
under this Contract;
(a) Access the Items, testing activities and data, related to, used for, prepared or
generated in connection with this Contract, and
(b) Witness all qualification and acceptance testing of the Deliverable Items to be
delivered or provided under this Contract including all tests used for the purpose
of demonstrating qualification.
11.5 Contractor shall make such data and documentation, equipment and facilities available
to KARI upon KARI’s request and KARI’s selection for such purposes. Contractor shall
Korea Aerospace Research Institute
RFP/40
deliver copies of design and test data and other technical data, excluding financial data,
required to evaluate technical problems or non-performance that may occur during the
performance of this Contract. Such documentation and data shall also be available for
KARI to make copies thereof.
Korea Aerospace Research Institute
RFP/41
Article 12. Incoming Test and Acceptance
12.1
Notwithstanding the successful FAT, the Contractor shall carry out Incoming Test of the
Deliverable Item in KARI site. In the event that KARI discovers that any Deliverable
Item provided or delivered pursuant to Article 7 “Deliveries” are defective or non-
conformity during the Incoming Test, KARI shall promptly notify Contractor thereof and
provided that such defect or non-conformity is not attributable to KARI, Contractor shall
promptly remedy such defect or non-conformity and retest. In addition, if remedying
such defect or non-conformity would substantially delay as compared to the period
required to complete such substitution, Contractor shall promptly provide substitute
Items. Upon the remedy of such defect or non-conformity that the requirements of this
Contract are satisfied in all respects or upon the provision of substitute Items,
Contractor shall notify KARI of the details of the remedy undertaken by Contractor.
12.2
After the Incoming Test, KARI’s authorized representative shall notify the result of
Incoming Test in writing. If KARI determines that RSS is unacceptable, it shall notify
the Contractor, in writing, the reasons therefore. If such written Incoming Acceptance
letter is not given to Contractor, within thirty (30) days after the Incoming Test of
Deliverable Item, the Deliverable Item shall be deemed to have been accepted by
KARI.
12.3
If RSS is determined to be unacceptable, both Parties shall jointly investigate the root
cause and if the root cause is attributable to the Deliverable Item, then it shall be
considered as non-delivery and Contractor shall, at its expense, promptly repair or
replace RSS so that it shall comply with the Contract specifications and requirements.
Such repaired or replaced Item shall be accepted in accordance with the requirements
of Article 12.1 and 12.2.
12.4 The Parties agree that the acceptance of the Deliverable Item under this Article shall
not be interpreted or construed to mean that such Item is free of all defects and
conform in all respects with the requirements of this Contract, and Contractor shall not
be entitled to any additional costs incurred or to recover any damages suffered due to
defects in the Item or KARI’s rejection of the Item.
Korea Aerospace Research Institute
RFP/42
Article 13. Training
13.1
Contractor shall provide KARI a training program of RSS operation for three (3)
persons without additional cost and notify KARI of the details of a training program
prior to execution. KARI shall notify Contractor of acceptance or impossibility within
thirty (30) days from the receipt date of notice.
13.2
In case KARI notify Contractor of its impossibility, Contractor shall notify KARI of
reschedule after agreement between both Parties.
Article 14. Indemnification
14.1
Contractor shall indemnify and hold KARI, its officers, agents, servants, employees,
subsidiaries, successors, and assignees, or any of them, harmless from any and all
loss, damage, liability or expense resulting from damage to all tangible property and
injuries including death, to all persons, in the circumstances caused by its act or
omission in the performance of the Work, and shall pay all expenses, including
reasonable attorneys’ fees, and satisfy all judgments as may be incurred by or
rendered against them, or any of them.
Korea Aerospace Research Institute
RFP/43
Article 15. Licenses, Clearances and Permits
15.1
Unless otherwise specified in this Contract, each Party is responsible for obtaining all
government approvals from any government authority which has jurisdiction and
authority to require such approvals, including, but not limited to, licenses, visas, and
permits necessary to carry out such Party’s obligations in accordance with this
Contract. KARI is responsible for obtaining any necessary Korean government
approvals, and Contractor is responsible for all other government approvals.
15.2
The Parties shall cooperate and provide each other, upon request of and without cost
to the other Party, all reasonable and necessary assistance in obtaining any and all
governmental approvals, which they respectively are required to obtain pursuant to
this Contract.
15.3
Each Party shall be solely responsible for any expenses incurred in obtaining the
approvals, which are required under this Article. The Parties shall provide to each other,
upon request of and without cost to the other Party, suitable documents or other
reasonable evidence to show that they have obtained any and all governmental
approvals, which they respectively are required to obtain pursuant to this Contract.
Article 16. Confidentiality
16.1
Each Party shall confidentially treat all documents, data, materials and information
supplied by one to the other, and shall not disclose the above to any Third Party, and
shall not use the above for any other purpose than for the performance of this Contract
without prior written consent from the other Party. However, this Confidentiality
obligation shall not be apply to the information which is made available to the general
public.
Korea Aerospace Research Institute
RFP/44
Article 17. Warranty
17.1
Any patent, utility, design, copyright, technical know-how and any other type of
intellectual property used by Contractor, its Subcontractors, servants, or agents, or
delivered or provided to KARI directly or indirectly in connection with this Contract shall
be free of any infringement actions by any Third Party claiming its rights or interests
with regard thereto in disposing with in accordance with this Contract.
17.2
The Deliverable Item supplied and performed by Contractor or its Subcontractors
hereunder shall be in good working order and free from all defects in workmanship and
materials and shall comply with the requirements of this Contract. Warranty period for
the Deliverable Item shall be two (2) years from Incoming Test and Acceptance.
17.3
Upon the receipt of written notification from KARI that the Deliverable Item delivered
by Contractor or its Subcontractors is defective or non-confirming, the Contractor shall
repair or replace, at Contractor’s option and its own expense, such Deliverable Item
so as to comply with the above warranties.
17.4
The Contractor shall not be entitled to any additional costs (for instance, the cost for
the repair or replacement of faulty parts at its option, the labor cost required for repair,
traveling cost, per diem and all associated necessary costs) incurred or to recover any
damages suffered due to defect in the Deliverable Item or rejection of the Deliverable
Item by KARI.
17.5
Contractor shall submit the written plan for repair after the reception of KARI’s
notification of fault and shall completely finish the repair within thirty (30) days after the
receipt of KARI’s written notification of fault.
17.6
Both Parties acknowledge that the breach of a warranty may result in serious damages
to KARI’s right, interests, privileges, and benefits, de facto or de jure, or loss of KARI’s
profits. If a breach of warranty has not been cured within
thirty (30) days from the
date of KARI’s written notification to Contractor of such breach, Contractor shall pay
all the damages to KARI due to the breach of any warranty.
17.7
The right and remedies provided under this Article 17 are in addition to any other rights
or remedies available to KARI under the Contract or applicable laws.
Korea Aerospace Research Institute
RFP/45
Article 18. Termination
18.1
Termination for Events of Force Majeure
18.1.1 In the event that the excusable delay under Article 8 “Delay” exceeds three (3) months
for any single Events of Force Majeure or six (6) months in the aggregate for all Events
of Force Majeure, KARI, at its sole discretion, may declare frustration of this Contract,
and terminate the whole or any part of this Contract by sending a three (3) days prior
notice to the Contractor.
18.1.2 In the event this Contract is terminated by Article 18.1.1 above, each Party shall effect
the restitution to the other Party of whatever is provided, delivered, or paid to it in the
same manner and types as such provision, delivery or payment was made.
18.2
Termination for Breach
18.2.1 KARI may, by written notice to the Contractor, terminate the whole or any part of the
Contract, if any of the following circumstances occurs;
(a) Contractor fails to deliver any Deliverable Item under Contract in accordance with
the delivery schedule; or
(b) Contractor fails to perform any Work under this Contract or fails to progress with
the Work in a manner which satisfies KARI that Contractor will perform the
Contract within the time specified and in accordance with the terms of the
Contract; or
(c) Contractor fails to remedy any or all defects and non-conformity on the
Deliverable Item in accordance with Article 12.
18.2.2 In the event of the circumstances in Article 18.2.1, KARI may notify the Contractor and
may suspend any further performance of its obligation under this Contract. If the
Contractor fails, within ten (10) days from the dispatch of the notice, to produce and
notify KARI of reasonable evidence of its intent and ability to effect due performance
of the obligation in breach within thirty (30) days from due dispatch of written notice,
then KARI may terminate this Contract with three (3) days’ prior notice of termination.
18.2.3 In the event this Contract is terminated for Contractor’s breach, the Contractor shall
return all the amounts paid by KARI under the Contract and also pay the termination
charge of ten percent (10%) of the total Contract Price. KARI shall return the
Deliverable Item to Contractor, if any.
Korea Aerospace Research Institute
RFP/46
Article 19. Resolution of Disputes and Governing Law
19.1
In cases any controversy or claim arises out of or in relation to this Contract or with
respect to a breach hereof, the Parties shall seek to resolve the matter amicably
through discussions between themselves. In the event of any disagreement between
KARI and Contractor about the interpretation of the provisions or definitions used in
this Contract, the interpretation of KARI shall govern until and unless otherwise
decided by arbitration conducted pursuant to the following provisions.
19.2
If the Parties cannot resolve such controversy or claim in accordance with Article 19.1
above, it shall be finally settled by arbitration in Seoul, Korea, before the Korean
Commercial Arbitration Board in accordance with its rules. The proceedings shall be
conducted in English. The award rendered by the board shall be final and binding on
the Parties and may be entered in any court of competent jurisdiction for execution.
19.3
The validity, performance, construction, and effect of this Contract shall be governed
by the laws of Korea.
Korea Aerospace Research Institute
RFP/47
Article 20. Changes
20.1
Changes Requested by KARI
20.1.1 Any changes requested by KARI during the performance of this Contract, within the
general scope of this Contract, which would add or delete Work, affect the design of
Work, change the method of shipment or packing, place or time of delivery, duration of
Contract, or would affect any other requirement of this Contract, shall be submitted in
writing to Contractor. Contractor shall respond to any changes KARI requested in
writing within thirty (30) days after receipt of such request. If such change requested
by KARI causes an increase or decrease in the Contract Price and/or an impact of
schedule, Contractor shall submit to KARI at the time the response to the requested
change is submitted, the details of such increase or decrease.
20.1.2 KARI shall notify Contractor in writing, within thirty (30) days after receipt of
Contractor’s response, whether it agrees with and accepts Contractor’s response. If
KARI agrees with and accepts Contractor’s response, an amendment to the Contract
reflecting such change, Contract Price and/or schedule adjustment, if any, shall be
issued, and Contractor shall proceed with the performance of the Contract as changed.
Contractor shall provide updated information that reflects the final agreed price of the
change, if KARI requests. In the event the Parties are unable to agree on a change
requested by KARI or price adjustment, if any, or both, Contractor shall proceed with
the performance of the Contract as unchanged.
20.2
Changes Requested by Contractor
20.2.1 Any changes requested by Contractor during the performance of this Contract, within
the general scope of this Contract, that would add or delete Work, affect the design of
Work, change the method of shipment or packing, place or time of delivery, duration of
Contract, or would affect any other requirement of this Contract, shall be submitted in
writing to KARI thirty (30) days prior to the proposed date of the change. If such change
requested by Contractor causes an increase or decrease in the Contract Price,
Contractor shall submit to KARI at the time the requested change is submitted, the
details of such increase or decrease.
20.2.2 KARI shall notify Contractor in writing within thirty (30) days after receipt of the
requested change and Contract Price adjustment, if any, whether or not it agrees with
and accepts such change. If KARI agrees with and accepts change requested by
Korea Aerospace Research Institute
RFP/48
Contractor, an amendment to the Contract reflecting such change, and Contract Price
adjustment, if any, shall be issued, and Contractor shall proceed with the performance
of the Contract as changed. Contractor shall provide updated information which
reflects the final agreed price of the change, if KARI requests. In the event the Parties
are unable to reach an agreement on a change requested by Contractor, or Contract
Price adjustment, if any, or both, Contractor shall proceed with the performance of the
Contract as unchanged.
Korea Aerospace Research Institute
RFP/49
Article 21. Notices
21.1
All notices, requests, demands, approvals, reports, invoices, and other
correspondence to be provided pursuant to this Contract shall be in writing and shall
be deemed to have been duly given to the Party to be notified: (i) on the date of delivery
if delivered in person, (ii) on the date of dispatch if by facsimile, telex or e-mail, or (iii)
on the date of receipt if by registered airmail or overnight courier.
All notices shall be addressed to the appropriate Party at its address as follows:
For KARI: Korea Aerospace Research Institute
169-84 Gwahakro, Yuseong-gu, Daejeon 34133, Korea
Commercial matters
Technical matters
Mr. Jung-Nam CHO
Tel: +82-42-860-2613
Fax:+82-42-860-2666
E-mail: jncho@kari.re.kr
Ms. Gm-Sil KANG
Tel: +82-42-860-2713
Fax:+82-42-860-2560
E-mail: wimikgs@kari.re.kr
For Contractor: [Company]
[Address]
Commercial matters
Technical matters
[Name]
Tel: +
Fax: +
E-mail:
[Name]
Tel: +
Fax: +
E-mail:
21.2
Each Party may change its address for notice by notice given to the other Party in the
manner set forth above. And any notices given as provided herein shall be considered
effective seven (7) days after the registered postage pre-paid airmailing thereof or the
day of actual receipt thereof, whichever occurs first, or on the day of personal delivery,
or the day of sending if by facsimile, telex or e-mail.
Korea Aerospace Research Institute
RFP/50
Article 22. Miscellaneous
22.1
Effective Date of the Contract
The effective date of this Contract ("EDC") is the date on which the duly authorized
representatives of both Parties have signed this Contract, and any amendment to this
Contract shall be effective only upon signature by the authorized representatives of
both Parties.
22.2
Entire Agreement
This Contract embodies the entire agreements of the Parties with respect to the
subject matter hereof and supersedes and cancels any and all prior understandings
or agreements, oral or written, in relation hereto, which may exist between the Parties.
No oral explanation or oral information by any of the Parties shall alter the meaning or
interpretation of this Contract.
22.3
Assignability
This Contract and each and every covenant, term and condition hereof shall be binding
upon and inure to the benefit of the Parties and their respective successors, and
neither this Contract nor any rights and obligations hereunder shall be assignable or
delegable directly or indirectly by either Party without the prior written consent of the
other Party.
22.4
Unenforceable Terms
If any term or provision of this Contract shall for any reason be invalid, illegal or
unenforceable in any respect, this Contract shall be interpreted and construed as if
such term or provision had never been included herein.
22.5
Non-waiver
The failure or delay of any Party to require performance by the other Party of any
provision of, or of any right or obligation under this Contract, shall not constitute a
waiver thereof, nor shall such affect that Party’s right to thereafter require performance
of such or any other provision, right or obligation.
22.6
Disclaimer of Agency
Korea Aerospace Research Institute
RFP/51
This Contract shall not be deemed to constitute any Party to become the agent of the
other Party.
22.7
Headings
The headings in this Contract have been inserted for convenience of reference only
and are not to be used in consulting or interpreting this Contract.
22.8
Language and Unit
All documents, drawings, plans and other writings as well as communications between
both Parties under this Contract shall be in English and measurements and quantities
for Deliverable Data shall be recorded in units of Système Internationale.
22.9
Time Limits
Unless otherwise indicated, any time limits to which this Contract binds Contractor or
KARI shall be counted in calendar days from the day following that of the event
marking the start of the time limit, and shall end on the last day of the period specified.
When the last day of a time limit is a Saturday or Sunday, or a legal holiday in the
country in which the particular contractual performance is required, such time limit
shall be extended to the first working day following.
22.10
Subcontractors
Each Party shall be fully responsible for the work of its Subcontractors under this
Contract, and such subcontracting shall not relieve that Party of its obligation under
this Contract.
Korea Aerospace Research Institute