Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

General Terms and Condition 


background image

KARI &       

   

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

Contents 

 

 

General Terms and Conditions 

Preamble & Witnesseth .......................................................................................................................1 

Article 1. Definition ............................................................................................................................2 

Article 2. Objective .............................................................................................................................5 

Article 3. Contract Documents ............................................................................................................6 

Article 4. Responsibilities of the Parties ..............................................................................................7 

Article 5. Contract Price ......................................................................................................................8 

Article 6. Terms of Payment ................................................................................................................9 

Article 7. Performance Bond ............................................................................................................. 11 

Article 8. Deliveries .......................................................................................................................... 12 

Article 9. Delay ................................................................................................................................ 14 

Article 10. Taxes and Duties ............................................................................................................. 16 

Article 11. Intellectual Property......................................................................................................... 17 

Article 12. Factory Acceptance ......................................................................................................... 18 

Article 13. Final Acceptance and Inspection ...................................................................................... 19 

Article 14. Spare Parts and Erection Tools ......................................................................................... 20 

Article 15. Defect and Non-conformity ............................................................................................. 21 

Article 16. Indemnification ............................................................................................................... 22 

Article 17. Licenses, Clearances and Permits..................................................................................... 23 

Article 18. Confidentiality................................................................................................................. 24 

Article 19. Warranty .......................................................................................................................... 25 

Article 20. Termination ..................................................................................................................... 26 

Article 21. Resolution of Disputes and Governing Law ..................................................................... 28 

Article 22. Language and Units ......................................................................................................... 29 

Article 23. Effective Date of Contract ............................................................................................... 30 

Article 24. Changes........................................................................................................................... 31 

Article 25. Notices ............................................................................................................................ 33 

Article 26. Miscellaneous .................................................................................................................. 34 

Appendix B-1. Statement of Works ................................................................................................... 37 

 

Appendix 

B-1.  Statement  of  Works   


background image

KARI &                                                                                                                                        Page 1 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

Preamble 
 

This  Contract  made  on  December          ,  2014  and  will  be  valid  until  May  31,  2017  b

y  and  between  Korea  Aerospace  Research  Institute,  established  under  the  law  of  the  R

epublic  of  Korea  with  its  principal  office  at  169-84  Gwahakro,  Yuseong-Gu,  Daejeon 

305-806,  Korea,  hereinafter  referred  to  as  “KARI”  and                            established  unde

r  the  law  of  the                          ,  with  its  principal  office  at                                               

        ,  hereinafter  referred  to  as  “Contractor”. 

 

 

Witnesseth 
 

WHEREAS, KARI has a satellite assembly, integration and test center (hereinafter referred to 

as  ‘AITC’)  for  the  purpose  of  the  effective  development  of  domestic  satellites  and  basic 

facilities and equipment for satellite assembly and test have been supplied, installed and used; 

 

WHEREAS, the primary objective of this  procurement is to design, manufacture, procure and 

install  qualified  functional  Vibration  shakers  &  Interface  equipment  which  performs  the 

functions required in Large Vibration Test Facility specification for AITC; 

 

WHEREAS,  Contractor  represents that  it  has  direct  knowledge  and  first-hand  experience  in 

manufacturing and supplying the Vibration  shakers  &  Interface  equipment  for  Large  Vibr

ation  Test  Facility of this Contract; 

 

WHEREAS, Contractor shall perform the design, qualification, production,  installation, test, 

delivery and warranty of the Vibration  shakers  &  Interface  equipment  for  Large  Vibration 

Test  Facility  and  provide  technical  support  which  KARI  needs  in  the  phase  of  assembly, 

integration, test and maintenance for this Contract; 

 

NOW  THEREFORE,  in  consideration  of  the  premises  and  the  mutual  covenants  hereinafter 

contained, KARI and Contractor have agreed as follows: 


background image

KARI &                                                                                                                                        Page 2 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

Article 1. Definition 
 

In this Contract, the following words and phrases shall have the meanings as indicated below, 

unless the context wherein they are used clearly indicates another meaning: 

 

1.1 

AITC means satellite assembly, integration and test center. 

 

1.2 

Amplifier means electrical parts(one amplifier) in the large vibration system. 

 

1.3 

Associates mean all individual or legal entities organized under public or private law, 

who  shall  act,  directly  or  indirectly,  on  behalf  of  KARI  or  Contractor,  or  at  the 

direction of either Party to this  Contract to fulfill the obligations undertaken by  such 

Party in this Contract, including, without limitation, the employees of each Party, their 

suppliers and Subcontractors. 

 

1.4 

Contract  means  this  Contract  for  the  procurement  and  acquisition  of  Vibration 

shakers & Interface equipment for Large Vibration Test Facility including Appendix as 

attached  hereto,  and  all  amendments  that  may  be  agreed  to  by  the  Parties  in 

accordance with the terms and conditions of this Contract. 

 

1.5 

Contractor means                                                                  . 

 

1.6 

Contract Price means the amount of Contract. If there is any change in Contract Price 

due to any reason, then the Contract Price means current total amount of Contract.   

 

1.7 

Deliverable Data means any technical data as enlisted in Appendix B-1 “Statement of 

Works” that Contractor shall deliver to KARI and any related data thereof under this 

Contract. 

 

1.8 

Deliverable  (Delivery)  Item(s)  means  any  hardware  or  software,  Deliverable  Data, 

Technical  Data,  and  information  as  enlisted  in  Appendix  B-1  “Statement  of  Works” 

that Contractor shall deliver to KARI. 

 

1.9 

EDC means the Effective Date of this Contract. 

 

1.10 

Equipment  means  all  parts,  accessories,  facilities,  hardware,  and  software  to  be 

supplied by Contractor to KARI pursuant to this Contract. 


background image

KARI &                                                                                                                                        Page 3 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

1.11 

Event(s) of Force Majeure  means  any  act of  God, war, whether  or  not  declared,  act 

or  failure  to  act of  any  government  in  its  sovereign  capacity,  fire,  earthquake,  flood, 

epidemic, quarantine, nuclear incident, or any other act beyond the reasonable control 

and without the fault of either Party or its Subcontractors. 

 

1.12 

Factory  Acceptance  means  KARI’s  inspection  or  audit  to  Contractor’s  facility,  area 

or  equipment  during  the  development,  testing  activities  for  any  plan,  procedure, 

specification or other documentation relevant to the work. 

 

1.13 

Final  Acceptance  means  final  acceptance  by  KARI  of  each  Deliverable  Item  in 

accordance with Article 13 “Final Acceptance and Inspection”. 

 

1.14 

Interface  Equipment  means  vibration  system  interface  which  is  composed  of  2.0m 

Head expander, 1.2m Head expander and 1.2m Slip table. 

 

1.15 

KARI means Korea Aerospace Research Institute. 

 

1.16 

Large  Vibration  System  means  one  vibration  system  which  is  composed  of  shaker 

and amplifier. 

 

1.17 

Party or Parties means KARI or Contractor, or both, according to the context. 

 

1.18 

Quad Amplifiers means electrical parts(four amplifiers) in the quad vibration system.   

 

1.19 

Quad Shakers means mechanical parts(four vibrators) in the quad vibration system.     

   

1.20 

Quad  Vibration  System  means  four  vibration  system  which  operate  simultaneously 

in multi-shaker option. It is composed of quad shakers and quad amplifiers. 

 

1.21 

Shaker means mechanical part(one vibrator) in the large vibration system. 

 

1.22 

Subcontract  means  any  subcontract,  including  purchase  orders  and  all  similar  forms 

of agreements at any tier under this Contract. 

 

1.23 

Subcontractor means a contractor under any Subcontract including suppliers. 

 

1.24 

Third  Party(ies)  means  any  individual  or  legal  entity  other  than  the  Associates  and 


background image

KARI &                                                                                                                                        Page 4 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

the Parties. 

 

1.25 

Work(s)  means  whole  or  part  of  the  work  to  be  executed  by  a  Contractor  in 

accordance with this Contract. 

 

1.26 

2.0m Head Expander means 2.0m diameter interface which is installed at shaker and 

allow vertical axis testing. 

 

1.27 

1.2m Head Expander means 1.2 ~1.3m diameter interface which is installed at shaker 

and allow vertical axis testing. 

 

1.28 

1.2m Slip Table  means 1.2 x 1.2m  interface which  is connected to shaker and allow 

the lateral axis testing. 

 


background image

KARI &                                                                                                                                        Page 5 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

Article 2. Objective 
 

The objective of this Contract is to procure the qualified Vibration  shakers  &  Interface  equi

pment  for  Large  Vibration  Test  Facility through the effort of the Contractor. To accomplish 

this objective, Contractor shall perform all the Works under this Contract required for design, 

manufacture, qualification, test, installation, warranty and maintenance as well as delivery of 

Deliverable Item to meet the requirements and specification of this Contract. Also, if there is 

any anomaly related with Contract, Contractor shall assist KARI to understand the anomaly in 

a  reasonable  Work  scope  such  as  teleconference  and/or  electronic  communication  without 

additional charge to KARI. 

 


background image

KARI &                                                                                                                                        Page 6 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

Article 3. Contract Documents 
 

3.1 

This Contract shall comprise the following documents, as amended from time to time 

by written agreement by and between both Parties: 

 

 

    [A] General Terms and Conditions 

 

    [B] Appendix 

 

 

B-1. Statement of Works   

 

3.2 

In  the  event  of  any  inconsistency  or  discrepancy  between  or  among  the  Contract 

documents as listed in Article 3.1 above, the Contract documents shall be applied. 

 

3.3 

In the event of any dispute or difference  between the Parties  in the  interpretation of 

this  Contract  as  a  result of  the  application  of  the Appendices  as  specified  in  Article 

3.1,  Contractor's  Proposal  dated  December          ,  2014  submitted  to  KARI  in 

anticipation  of  this  Contract  in  response  to  KARI's  Request  for  Proposal  dated 

December          , 2014 shall  be used as a reference document to identify and clarify 

the  intention  and  understanding  of  the  Parties  as  contemplated  in  this  Contract,  and 

both Parties shall in good faith seek an agreement or a compromise acceptable to both 

Parties without modifications to this Contract. 

 


background image

KARI &                                                                                                                                        Page 7 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

Article 4. Responsibilities of the Parties 
 

4.1 

Responsibilities of KARI 

 

4.1.1 

KARI  shall  make  a  payment  to  Contractor  in  accordance  with  Article  6  “Terms  of 

Payment”. 

 

4.1.2 

In  accordance  with  Appendix  B-1  “Statement  of  Works”,  KARI  shall  provide  any 

reasonable  support  and  information  in  order  for  Contractor  to  fulfill  any  necessary 

Work. 

 

4.2 

Responsibilities of Contractor 

 

4.2.1  Contractor shall have all responsibilities to KARI in a timely manner as required and 

defined under this Contract without any charges to KARI.   

 

4.2.2  Contractor shall provide all technical  support required and stated under this Contract 

to  KARI,  warranty  and  maintenance  for  all  Deliverable  Items  and  the  installation  in 

accordance with Article 19 “Warranty”. 

 

 


background image

KARI &                                                                                                                                        Page 8 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

Article 5. Contract Price 
 

5.1 

For  the  full,  satisfactory  and  timely  performance  of  the  Work  by  the  Contractor  in 

accordance  with  the  provisions  of  the  Contract,  KARI  hereby  agrees  to  pay  to  the 

Contractor                          Euros  (€                            ),  in  accordance  with  the  terms 

of payment as stipulated in Article 6 “Terms of Payment”. 

 

5.2 

The Contract Price as specified in Article 5.1 above shall be firm and fixed price that 

is  not  subject  to  any  escalation  or  to  any  adjustment  or  revision  by  reason  of  the 

increase of actual costs incurred by Contractor in the performance of the Work under 

this Contract, unless otherwise agreed to by both Parties under Article 24 “Changes”. 

 

5.3 

The  Contract  Price  as  specified  in  Article  5.1  above  shall  be  comprised  of  the 

following items. 

 

Items 

Qty 

Price (€) 

One shaker & amplifier system for Quad Vibration System

 

 

Improvement of existing three (3) shakers & amplifiers of 

LDS V984LS   

 

One shaker & amplifier system for Large Vibration System 

 

Shaker Interface equipment 

 

Total 

 

 

5.4 

All  banking  charges  incurred  in  Korea  shall  be  borne  by  KARI  and  those  charges 

incurred outside Korea shall be borne by Contractor. 

 

 


background image

KARI &                                                                                                                                        Page 9 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

Article 6. Terms of Payment 
 

6.1        Payment Schedule 

 

6.1.1  Payment shall be executed after the establishment of performance bond in accordance 

with Article 7 “Performance Bond”. 

 

6.1.2  KARI  shall  pay  to  Contractor  the  Contract  Price  as  stipulated  in  Article  5.1  in 

accordance with the following schedule: 

 

No. 

Payment milestone 

(in Month) 

Payment due date 

Payment   

(€) 

Percentage of 

Contract Price (%) 

EDC 

EDC+ 1M 

 

25% 

FR for Quad vibration 

FR + 1M 

 

25% 

FAR for Quad 

vibration 

FAR +1M 

 

7% 

FR for Large vibration 

FR + 1M 

 

20% 

FAR for Large 

vibration 

FAR +1M 

 

8% 

FAR for Interface 

equipment 

FAR +1M 

 

15% 

Total 

 

100 % 

*    “EDC”  means  the  Effective  Date of  this  Contract  in  accordance with  Article  23 

“Effective Date of Contract”. 

*    “FR” means the Factory Acceptance Review. 

*    “FAR” means the Final Acceptance Review. 

[Note] KARI’s Payment Schedule for this Contract can be adjusted by Government budget profile. 

 

6.2 

Billing Procedure 

 

6.2.1  All  invoices  Contractor  submits  for  payment  shall  be  in  duplicate  signed  by  an 

authorized company official and received by KARI at least thirty (30) days before the 

payment due dates as specified in Article 6.1.   

 

6.2.2  All  payments  shall  be  made  in  Euros  by  telegraphic  transfer  to  the  bank  account  as 

designated  by  Contractor  in  its  invoices.  And  KARI  shall  remit  the  payment  within 

thirty (30) days after KARI’s receipt of Contractor’s invoice.   


background image

KARI &                                                                                                                                        Page 10 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

6.3 

Suspension of Payment 

 

6.3.1  Notwithstanding any provisions of this Contract, if any payment milestone as set forth 

in Article 6.1.2 has not been accomplished for any reasons attributable to Contractor, 

KARI may, with an advance notice, suspend such payment due until both Parties agree 

that the delayed payment milestone has been accomplished. 

 

6.3.2  In  the  event  of  KARI's  suspension  of  payment  under  Article  6.3,  Contractor  shall 

nevertheless  continue  to  perform  its  obligations  under  this  Contract  regardless  of 

whether KARI is entitled to suspend the payment.   

 

6.4 

Deduction of Payment 

 

6.4.1  All  losses,  costs,  charges,  damages  and  expenses  which  KARI  incurs  or  sustains  by 

reason  of  any  act,  default  or  omission  of  the  Contractor  in  the  performance  of  the 

Contract and any other amounts which KARI is entitled to receive from the Contractor 

may be deducted from any payment that may be or become due to the Contractor from 

KARI. 

 

6.4.2 

A  prior  written  notice  given  by  KARI  accompanied  with  documents  stating  the 

amount due to KARI referred to in Article 6.4.1 and the reason of deduction shall be 

prima facie evidence of the matters stated herein. 

 


background image

KARI &                                                                                                                                        Page 11 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

Article 7. Performance Bond 
 

7.1 

Contractor  shall  establish  a  performance  bond  within  three  (3)  weeks  after  EDC  in 

favor of KARI in the value of ten percent (10 %) of the Contract Price, in the form of 

an irrevocable and unconditional standby letter of credit available by KARI’s draft at 

sight. 

 

7.2 

The  entire  amount  covered  by  the  performance  bond  shall  be  payable  to  KARI  on 

demand together with KARI’s written statement to the effect: 

(a)  that  there  was  a  default  of  the  Contractor  in  the  performance  of  the  Contract 

(including Subcontractor’s default under the Subcontract), or 

(b) that any amount KARI is entitled to receive from Contractor has not been paid by 

Contractor to KARI through any other means, or 

(c)  that  this  Contract  was  terminated  by  Contractor’s  breach  as  specified  in  Article 

20.2. 

Whenever any amount has been withdrawn by KARI due to such cases of (a) and (b) 

as above, performance bond shall be replenished. 

 

7.3 

The  letter  of  credit  shall  be  issued  by  first  class  international  bank  acceptable  to 

KARI. The letter of credit shall be drawn in favor of KARI and advised through the 

Woori Bank (Daejeon Branch at 1495 Dunsan-dong, Seo-gu, Daejeon, 302-173 Korea, 

Tel:  +82-42-488-9704,  Ext.  312/  Fax  :  +82-505-003-0759_banker@wooribank.com) 

and shall remain valid until the end of this Contract plus one (1) month. The letter of 

credit  shall  not  be  amended,  modified  or  canceled  without  KARI's  prior  written 

consent. 

 

7.4 

It  is  hereby  agreed  between  the  Parties  that  payment  from  the  Performance  Bond 

under  this  Article  7  shall  not  affect  any  other  KARI's  rights,  privileges,  interests  or 

remedies under this Contract or the applicable law. 

 


background image

KARI &                                                                                                                                        Page 12 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

Article 8. Deliveries 
 

8.1 

General 

 

8.1.1 

Contractor shall deliver Deliverable Item in accordance with the defined schedule and 

method as set forth in Appendix B-1 “Statement of Works” and the delivery shall be 

deemed  to  have  occurred  only  when  the  Final  Acceptance  has  been  successfully 

completed at KARI site. 

 

8.1.2    Contractor  shall  bear  any  charges  or  costs of  whatsoever  nature that  are  incurred  in 

relation  to  such  delivery  or  provision  until  such  delivery  or  provision  is  duly  made 

under  this  Contract  without  any  non-conformity  and  accepted  in  accordance  with 

Article13 “Final  Acceptance and Inspection” hereof, and shall keep KARI free  from 

any such charges and costs. 

 

8.1.3 

Contractor  agrees  that  delivery  or  provision  of  time  and  place  under  this  Contract, 

whether specifically provided for or not, or in subsequent amendments thereto, are of 

the essence of this Contract. 

 

8.1.4 

Contractor  shall  be  responsible  for  all  applicable  taxes  imposed  outside  Korea 

including  any  customs  duties  and  charges  of  any  nature  levied  on  Deliverable  Item, 

spare  parts,  spare  materials,  tools,  consumables  and  ancillary  equipment  as  well  as 

any charges associated with the ocean freight and the inland transportation. 

 

8.2 

Delivery to KARI 

 

8.2.1 

Contractor shall deliver Deliverable Item FOB (Free On Board in accordance with the 

Incoterms  2010)                seaport  in  accordance  with  the  delivery  schedule  of  this 

Contract.   

 

8.2.2 

Contractor shall hand over to KARI’s Forwarding Agent (                  ) after shipment 

in accordance with above delivery condition.   

 

8.2.3 

To  obtain  import  certification,  Contractor  shall  notify  KARI  by  e-mail  (address  is 

“acoust@kari.re.kr” for Mr. Jong-Min IM and “jncho@kari.re.kr” for Mr. Jung-Nam 

CHO)  fourteen  (14)  calendar  days  prior  to  each  shipment  with  one  set  of  proforma 

invoice  and  packing  list  specifying  the  number  of  boxes,  name  of  Items,  unit  price, 


background image

KARI &                                                                                                                                        Page 13 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

and  size  and  volume  of  each  container  or  box  to  be  shipped.  As  soon  as  each 

shipment as provided for in this Article is made, Contractor shall send one (1) copy of 

the following shipping documents to KARI by e-mail; 

 

(a)  Clean  on  board  vessel  bill  of  lading/or  airway  bill  of  lading, 

(b)  Commercial  invoice, 

(c)  Packing  list, 

(d)  Weight  and  measurement  list,   

(e)  Manufacturer's  Inspection  Report,  and 

(f)  Export  License. 

 

8.2.4 

Contractor  shall  meet  the  key  points  schedule  as  below: 

Items 

Due date 

Quad Vibration System 

(Quad-shakers, Quad-Amplifier)

 

-Arrival at KARI : by January 31, 2016 

-Installation & Finish site acceptance : by February 29, 2016 

-Existing three shakers will be available to Contractor from 

November 2015 

Large Vibration System 

(One Shaker, One Amplifier)

 

-Arrival at KARI : by January 31, 2017 

-Installation & Finish site acceptance : by February 28, 2017 

Interface equipment 

(2.0m Head expander, 1.2m Head 

expander, 1.2m Slip table)

 

-Arrival at KARI : by April 30, 2017 

-Installation & Finish site acceptance : by May 31, 2017 

 

 

 

 


background image

KARI &                                                                                                                                        Page 14 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

Article 9. Delay 
 

9.1 

Excusable Delay 

 

9.1.1  Neither  Party  shall  be  responsible  to  the  other  Party  for  any  delay  in  performing  its 

obligations under this Contract due to any Events of Force Majeure. 

 

9.1.2  The  Party  whose  performance  of  obligations  hereunder  has  been  affected  by  any 

Events of Force Majeure shall notify the other Party within ten (10) days thereafter by 

sending  a  detailed  statement  and  sufficient  evidence  with  respect  thereto,  and 

promptly  of  any  subsequent  change  in  the  circumstances,  if  any.  The  affected  Party 

shall exercise its best efforts under the circumstances to remove or remedy the Events 

of Force Majeure and the effects thereof and resume full performance hereof as soon 

as possible. 

 

9.1.3  Notwithstanding Article 9.1.1 hereof, any such delay that has not been notified to the 

other  Party  pursuant  to  Article  9.1.2  hereof  shall  not  be  excused  for  any  reason 

whatsoever.  Notwithstanding  Article  9.1.1  hereof,  any  delay  of  performance  of  the 

affected  Party  falling  due  after  delay,  failure  or  incompleteness  in  exercising  the 

pertinent  best  efforts to  remove  or  remedy  the  pertinent  Events  of  Force  Majeure  or 

the effects thereof pursuant to Article 9.1.2 hereof shall not be excused for any reason 

whatsoever. 

 

9.1.4  The Party who has received or is entitled to duly receive the notice of Events of Force 

Majeure under Article 9.1.2 hereof may suspend performance of its obligations which 

shall  be  due  subsequent  to  such  Events  of  Force  Majeure,  until  the  other  Party  has 

effected such delayed performance to the full extent after and in view of such Events 

of Force Majeure. 

 

9.2 Non-Excusable Delay 

 

9.2.1  In the event that, unless otherwise excused by virtue of this Contract or the governing 

or Applicable law, Contractor delays the provision or delivery of Deliverable items as 

stipulated in this Contract, or performance of its other obligations under this Contract, 

Contractor  shall  be  responsible  for  damages  incurred  by  KARI  as  a  result  of  such 

delay. 

 


background image

KARI &                                                                                                                                        Page 15 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

9.2.2 

Non-Excusable Delay, Liquidated damages, shall be applied for late performance or 

non-performance at the rate of zero point fifteen (0.15) percent of total Contract price 

per calendar day, up to ten (10) percent of total price. 

 

9.2.3  For the purpose of this Article, any action or omission of Contractor’s Subcontractor, 

agent, or servant, de facto or de jure, shall be deemed to be Contractor’s own. 

 


background image

KARI &                                                                                                                                        Page 16 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

Article 10. Taxes and Duties 
 

10.1 

In the event taxes are charged in Korea, KARI shall be fully responsible for payment 

of such taxes. Contractor shall  be  fully responsible for the payment of all applicable 

taxes imposed outside Korea including any customs duties and charges.   

 

10.2 

Neither  Party  shall  be  responsible  for  paying  the  customs  duties,  and  related  taxes, 

fees, or charges for the personnel and the personal belongings of the other Party. 

 

10.3 

The Contractor shall  further comply with  instructions KARI  may  issue  from time to 

time in order to facilitate any exemptions or reductions from customs duties and other 

taxes  that  might  be  levied  on  KARI  and  shall  impose  the  same  obligations  on  its 

Subcontractors. 

 


background image

KARI &                                                                                                                                        Page 17 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

Article 11. Intellectual Property 
 

11.1 

KARI shall own and have a right to use, without any obligation, all the Deliverable 

Items  or  Data  provided  by  Contractor  in  its  performing  this  Contract.  Contractor 

shall take all necessary precautions so that all the Deliverable Items or Data supplied 

hereunder  shall  be  free  from  infringement  of  any  patent,  design  patent,  trademark, 

utility  model  or  any  other  industrial  property  right,  copyright,  license  or  any  other 

right thereunder of any third party or parties. 

 

11.2      In  the  event  that  any  party  other  than  Contractor  claims  or  threatens  to  claim 

infringement  by  KARI  with  respect  to  such  use  of  the  Deliverable  Items  or  Data, 

Contractor shall defend, hold harmless, and indemnify KARI from such infringement 

claims. 

 

11.3      This Article will survive the completion of the Contract, any termination, cancellation 

or expiration of the Contract in any manner whatsoever. 

 

 


background image

KARI &                                                                                                                                        Page 18 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

Article 12. Factory Acceptance 
 

12.1 

KARI, at all times during the performance of this Contract, shall have the right to do 

the  following  activities  at  the  Contractor’s  facilities,  Subcontractor’s  facilities, 

supplier’s facilities, or other relevant facilities under this Contract; 

 

(a)  Factory  acceptance  tests  and  inspections  in  accordance  with  in  Appendix  B-1 

“Statement of Works” 

(b) Monitor the Contract performance of Contractor, 

(c) Access the Items in progress, and any design, manufacturing, and testing activities 

and  data,  including  development  and  engineering  model  testing,  related to,  used 

for, prepared or generated in connection with this Contract, and 

(d)  Witness  all  qualification  and  acceptance  testing  of  all  Items  to  be  delivered  or 

provided  under  this  Contract  including  all  tests  used  for  the  purpose  of 

demonstrating qualification. 

 

12.2      Contractor  shall  make  such  data  and  documentation,  equipment  and  facilities 

available  to  KARI  upon  KARI’s  request  and  KARI’s  selection  for  such  purposes. 

Contractor  shall  deliver  copies  of  design  and  test  data  and  other  Technical  Data, 

excluding financial data, required to evaluate technical problems or non-performance 

that may occur during the performance of this Contract. Such documentation and data 

shall also be available for KARI to make copies thereof. For a period of six (6) years 

after termination or expiration of this Contract, to the extent that such documentation 

and data are of a type  normally retained by the Contractor and  its Subcontractors, it 

shall continue to be available under the same terms and conditions. 

 

12.3 

Contractor shall obtain  from any of  its Associates access by  KARI, upon reasonable 

advance  notice  to  Contractor,  to  any  pertinent  facilities,  Work  in  progress  and 

Technical  Data of  any  of  Contractor’s  Associates to  inspect  Work  in  progress  under 

this  Contract.  Contractor  shall  dispatch  its  representative  or  a  technical  manager 

authorized  to  act  on  behalf  of  its  representative  to  accompany  KARI’s  access 

hereunder. 

 

12.4 

KARI  shall  have  access  to  all  Technical  Data  in  the  Contractor’s  control  that  are 

required for this Contract. 

 

12.5 

If,  during  the  performance  of  this  Contract,  the  KARI  representative  or  any  person 


background image

KARI &                                                                                                                                        Page 19 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

designated by  KARI reasonably determines that any of the provisions or delivery of 

any  Items  or  Contractor’s  performance  of  its  other  obligations  under  this  Contract 

does not conform to the requirements of this Contract, the KARI representative shall 

promptly  notify  the  Contractor,  and  confirm  such  notification  in  writing  within  ten 

(10)  days,  of  the  particulars  in  which  such  provision,  delivery  or  performance  does 

not  meet  the  requirements  of  the  Contract.  The  Contractor,  upon  receipt  of  such 

notice, shall promptly make the corrections of such non-conformity and notify KARI 

of the result of such corrections, or, if such prompt corrections are not possible, notify 

KARI  of  the  reason  why  such  prompt  corrections  are  not  possible  and  the  period 

required for the corrections. 

 

 
Article 13. Final Acceptance and Inspection 
 

13.1 

The Final Acceptance of installation, Deliverable Items or Data shall occur only after: 

(a) installation, Deliverable Items or Data to be performed  by the Contractor under 

the  Contract  for  Works  have  been  completed  in  accordance  with  the  Contract; 

and 

(b) the Contractor has demonstrated to KARI that the installation, Deliverable Items 

or Data meet the specifications and requirements in this Contract; and 

(c)  all  Works  and  conditions  under  the  Contract  to  be  fulfilled  by  the  Contractor 

prior to the  Final  Acceptance  have  been  met,  in  which  case  KARI  shall  finally 

accept,  in  writing,  installation,  Deliverable  Items  or  Data  subject  to  the 

provisions set forth below. 

 

13.2 

Subject to the conditions as set forth in Article 13.1 above, The Final Acceptance of 

installation, Deliverable Items or Data shall be deemed to have occurred only when 

the  inspection  and  test of  installation,  Deliverable  Items  or  Data  have  successfully 

completed  at  KARI  site  and  KARI’s  authorized  representative  has  accepted 

installation,  Deliverable  Items  or  Data  in  writing.  If  KARI  determines  that  any 

installation, Deliverable Item or Data is unacceptable, it shall justify such refusal to 

the  Contractor,  in  writing.  If  such  written  Final  Acceptance  letter  is  not  given  to 

Contractor,  within  thirty  (30)  days  after  the  inspection  and  test  regarding  such 

installation,  Deliverable  Item  or  Data  or  if  such  installation,  Deliverable  Items  or 

Data are taken into use, such installation, Deliverable Items or Data shall be deemed 

to have been accepted by KARI. 

 


background image

KARI &                                                                                                                                        Page 20 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

13.3 

If  any  installation,  Deliverable  Item  or  Data  is  determined  to  be  unacceptable,  it 

shall  be  considered  as  non-delivery  and  the  Contractor  shall,  at  its  expense, 

promptly  repair  or  replace  such  Items  so  that  it  shall  comply  with  the  Contract 

specifications and requirements, and shall submit such repaired or replaced Items for 

its  confirmation.  The  repaired  or  replaced  Items  shall  be  accepted  in  accordance 

with the requirements of Article 13.1. 

 

13.4 

The  Parties  agree  that  the  acceptance  of  any  installation,  Deliverable  Item  or  Data 

under this Article shall not be interpreted or construed to mean that such installation, 

Deliverable Items or Data are free of all defects and conform in all respects with the 

requirements of this Contract, and Contractor shall not be entitled to any additional 

costs  incurred  or  to  recover  any  damages  suffered  due  to  defects  in  the  Items  or 

KARI’s rejection of the Items. 

 

 

Article 14. Spare Parts and Erection Tools 
 

14.1 

Contractor shall provide KARI with all list and delivery time of spare parts/erection 

tools for KARI's use for consumable and five (5) years of operation as per the Scope 

of supplies specified in Contract Specifications. 

 

14.2 

Contractor shall guarantee that spare parts/erection tools can  be  made available  for 

fifteen (15) years. 

 

 


background image

KARI &                                                                                                                                        Page 21 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

Article 15. Defect and Non-conformity 
 

15.1 

In  the  event  that  KARI  discovers  that  any  Deliverable  Item  provided  or  delivered 

pursuant  to  Article  8  “Deliveries”  are  defective  or  non-conformity,  KARI  shall 

promptly  notify  Contractor  thereof.  Until  KARI  has  made  the  Final  Acceptance, 

without  charge  to  KARI,  provided  that  such  defect  or  non-conformity  is  not 

attributable  to  KARI,  Contractor  shall  promptly  remedy  such  defect  or  non-

conformity  and  retest  in  the  presence  of  KARI's  authorized  representative.  In 

addition,  if  remedying  such  defect  or  non-conformity  would  substantially  delay  as 

compared  to  the  period  required  to  complete  such  substitution,  Contractor  shall 

promptly  provide  substitute  Items.  Upon  the  remedy  of  such  defect  or  non-

conformity that the requirements of this Contract are satisfied in all respects or upon 

the provision of substitute Items, Contractor shall notify KARI of the details of the 

remedy undertaken by Contractor. 

 

15.2 

The Parties  hereby agree that acceptance under this  Article shall  not be  interpreted 

or construed to mean that the Deliverable Items provided or delivered are free of all 

defects and conform in all respects with the requirements of this Contract. 

 

15.3 

If,  at  any  time,  during  the  performance  of  its  obligations  under  this  Contract 

Contractor becomes aware of such defects or non-conformity as provided for in this 

Article,  Contractor  shall  promptly  take  appropriate  corrective  measures  at  its  own 

expense  to  remedy  any  such  defects  or  non-conformity  in  the  same  manner  as 

stipulated  in  this  Article,  and  notify  KARI  of  the  details  of  such  defects  or  non-

conformity and the remedy thereof. 

 

15.4 

With regard to the Items after the remedy of  such defect or non-conformity, or the 

substitute  Items  provided  or  delivered,  or  the  performance  of  Contractor’s 

obligations  under  this  Contract  after the  remedy  of  such  defect  or  non-conformity, 

under Articles 15.1, 15.2 and 15.3 hereof, this Article 15 shall apply as appropriate. 

 

15.5 

For the purpose of this Article, any act or omission of a Party's Subcontractor, agent, 

or servant, de facto or de jure, shall be deemed to be that Party's own. 

 

 

 

   


background image

KARI &                                                                                                                                        Page 22 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

Article 16. Indemnification 
 

Contractor  shall  indemnify  and  hold  KARI,  its  officers,  agents,  servants,  employees, 

subsidiaries,  successors,  and  assignees,  or  any  of  them,  harmless  from  any  and  all  loss, 

damage,  liability  or  expense  resulting  from  damage  to  all  tangible  property  and  injuries 

including  death,  to  all  persons,  in  the  circumstances  caused  by  its  act  or  omission  in  the 

performance of the Work, and shall pay all expenses, including reasonable attorneys’ fees, and 

satisfy all judgments as may be incurred by or rendered against them, or any of them. 

 

 

 

 

 


background image

KARI &                                                                                                                                        Page 23 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

Article 17. Licenses, Clearances and Permits 
 

17.1 

Unless otherwise specified in this Contract, each Party is responsible for obtaining all 

government  approvals  from  any  government  authority  which  has  jurisdiction  and 

authority to require such approvals, including, but not limited to, licenses, visas, and 

permits  necessary  to  carry  out  such  Party’s  obligations  in  accordance  with  this 

Contract.  KARI  is  responsible  for  obtaining  any  necessary  Korean  government 

approvals, and Contractor is responsible for all other government approvals.   

 

17.2 

The Parties shall cooperate and provide each other, upon request of and without cost 

to  the  other  Party,  all  reasonable  and  necessary  assistance  in  obtaining  any  and  all 

governmental  approvals,  which  they  respectively  are  required  to  obtain  pursuant  to 

this Contract.   

 

17.3 

Each  Party  shall  be  solely  responsible  for  any  expenses  incurred  in  obtaining  the 

approvals,  which  are  required  under  this  Article.  The  Parties  shall  provide  to  each 

other, upon request of and without cost to the other Party, suitable documents or other 

reasonable  evidence  to  show  that  they  have  obtained  any  and  all  governmental 

approvals, which they respectively are required to obtain pursuant to this Contract. 

 

 


background image

KARI &                                                                                                                                        Page 24 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

Article 18. Confidentiality 
 

18.1 

Each  party  shall  confidentially  treat  all  documents,  data,  materials  and  information 

supplied  by  one  to the other,  and  shall  not  disclose  the  above  to  any  third  party,  and 

shall not use the above for any other purpose than for the performance of this Contract 

without  prior  written  consent  from  the  other  party.  However  this  Confidentiality 

obligation shall not be apply to the information which is made available to the general 

public. 

 

18.2 

If  specified  by  written  consent,  both  parties  agree  to  enter  into  Non-Disclosure 

Agreement. 

 


background image

KARI &                                                                                                                                        Page 25 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

Article 19. Warranty 
 

19.1 

The  installation,  Deliverable  Items  or  Data  supplied  by  Contractor  or  its 

Subcontractors hereunder shall be in good working order and free from all defects in 

workmanship and materials and shall comply with the requirements of this Contract. 

Warranty period  for the  installation, Deliverable Items or Data shall  be one (1)  year 

from on the date of Final Acceptance letter. 

 

19.2 

Warranty  covers  the  replacement  of  faulty  parts,  the  labor  required  for  repair, 

traveling cost, living fees and all associated necessary costs.   

 

19.3 

For  the  upgrading  of  three  shakers  used  in  quad-shakers,  Contract  shall  take  the 

responsibility  for  the  normal  operation  especially  in  amplifiers  system  for  five  (5) 

years.  In  case  of  new  shakers  including  amplifiers  supplied,  it  shall  be  applied  to 

Articles 19.1. 

 

19.4 

Contractor or A/S teams shall submit the written plan for repair within 48 hours after 

the  reception  of  the  notification  of  fault.  The  Contractor  or  A/S  teams  shall 

completely finish the repair within thirty (30) days after the reception of the written 

notification of fault. 

 

19.5 

For an urgent service during important testing period, The deadline for action is five 

(5)  days  from  the  reception  of  the  written  notification  of  service.  To  meet  the 

deadline of the urgent service, KARI will notify Contractor of the test start date and 

the period two (2) weeks before the test start date. Contractor shall stand by the A/S 

crews at Contractor's convenient place during the test period (up to four (4) weeks). 

Contractor shall include a plan for these requirements in the proposal. 

 

19.6 

To meet these requirements, Contractor shall propose a detailed plan  for the prompt 

repair in the proposal. The detailed information (location, number of crews, resume, 

phone and FAX numbers, e-mail address, etc.) of the A/S teams shall be shown in the 

proposal and shall be approved by KARI. 

 

 


background image

KARI &                                                                                                                                        Page 26 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

Article 20. Termination 
 

20.1 

Termination for Events of Force Majeure 

 

20.1.1  In the event that the excusable delay under Article 9 “Delay” exceeds six (6) months 

for  any  single  Events  of  Force  Majeure  or  nine  (9)  months  in  the  aggregate  for  all 

Events of Force Majeure, KARI, at its sole discretion, may declare frustration of this 

Contract, and terminate the whole or any part of this Contract by sending a three (3) 

days prior notice to the Contractor. 

 

20.1.2  In the event that Contract is terminated for Events of Force Majeure, Contractor shall 

return one hundred percent (100%) of the amount paid by KARI under this Contract. 

KARI shall return all Deliverable Items to Contractor, in the manner of “AS IS”. 

 

20.2 

Termination for Breach 

 

20.2.1  KARI may, by written notice to the Contractor, terminate the whole or any part of the 

Contract, if any of the following circumstances occurs; 

(a) Contractor fails to deliver any Deliverable Item under Contract in accordance with 

the delivery schedule; or   

(b) Contractor fails to perform any Work under this Contract or fails to progress with 

the  Work  in  a  manner  which  satisfies  KARI  that  Contractor  will  perform  the 

Contract  within  the  time  specified  and  in  accordance  with  the  terms  of  the 

Contract; or 

(c)  Contractor  fails  to  remedy  any  or  all  defects  and  non-conformity  on  the 

Deliverable Item in accordance with Article 20.2. 

 

20.2.2  In the event of the circumstances  in Article 20.2.1, KARI  may  notify the Contractor 

and may suspend any further performance of its obligation under this Contract. If the 

Contractor fails, within ten (10) days from the dispatch of the notice, to produce and 

notify KARI of reasonable evidence of its intent and ability to effect due performance 

of the obligation in breach within sixty (60) days from due dispatch of written notice, 

then  KARI  may  terminate  this  Contract  with  three  (3)  days’  prior  notice  of 

termination. 

 

20.2.3  In the event this Contract is terminated for Contractor’s breach, the Contractor shall 

return all the amounts paid by KARI under the Contract and also pay the termination 


background image

KARI &                                                                                                                                        Page 27 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

charge  of  ten  percent  (10%)  of  the  total  Contract  Price.  KARI  shall  return  the 

Deliverable Item to Contractor, if any. 

 

20.3 

Termination for Special Circumstances 

 

20.3.1  Either Party may terminate this Contract anytime upon or after due dispatch of notice 

of  such  effect,  without  any  other  conditions,  in  the  event  that  the  other  Party  falls 

within any of the following categories: 

 

(a) the other Party has fallen bankrupt or insolvent;   

(b)  the  other  Party  passed  a  resolution  for  its  reorganization  (bankruptcy  related), 

dissolution, liquidation or winding-up; or 

(c)  a  court  order  for  proceedings  for  the  bankruptcy,  reorganization  (bankruptcy 

related), dissolution or winding-up of the other Party has been applied for by any 

person and such application has not been dismissed within sixty (60) days. 

 

20.3.2  In  the  event  this  Contract  is  terminated  by  Article  20.3.1  above,  each  Party  shall 

effect the restitution to the other Party of whatever is provided, delivered, or paid to it 

in  the  same  manner  and  types  as  such  provision,  delivery  or  payment  was  made. 

However,  both  Parties  may  also  agree  otherwise  and  if  KARI  wants  to  retain  the 

results  of  the  Works  or  any  Deliverable  Item,  then  corresponding  payment  shall 

remain with Contractor or be made by KARI. 

 

20.4 

Termination for Convenience 

 

20.4.1  KARI may terminate this Contract, in whole or in part, ONLY IF GOVERNMENT 

TERMINATES THE PROGRAM WHICH IS DIRECTLY RELATED TO THIS 

CONTRACT  for  its  convenience,  with  sixty  (60)  days’  prior  written  notice  to 

Contractor.  In  case  of  such  termination  for  convenience,  Contractor  is  entitled  to 

receive  payment  due  which  Contractor  has  already  done  in  accordance  with  Article 

6.1.2  within  thirty  (30)  days  from  the  date  of  termination  and  KARI  shall  release 

performance bond at the same time. 


background image

KARI &                                                                                                                                        Page 28 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

Article 21. Resolution of Disputes and Governing Law 
 

21.1 

In cases any controversy or claim arises out of or in relation to this Contract or with 

respect  to  a  breach  hereof,  the  Parties  shall  seek  to  resolve  the  matter  amicably 

through  discussions  between  themselves.  In  the  event  of  any  disagreement  between 

KARI and Contractor about the interpretation of the provisions or definitions used in 

this  Contract,  the  interpretation  of  KARI  shall  govern  until  and  unless  otherwise 

decided by arbitration conducted pursuant to the following provisions.   

 

21.2 

If  the  Parties  cannot  resolve  such  controversy  or  claim  in  accordance  with  Article 

21.1 above, it shall be finally settled by arbitration in Seoul, Korea, before the Korean 

Commercial Arbitration Board in accordance with its rules. The proceedings shall be 

conducted in English. The award rendered by the board shall be final and binding on 

the Parties and may be entered in any court of competent jurisdiction for execution. 

 

21.3 

The validity, performance, construction, and effect of this Contract shall be governed 

by the laws of Korea. 

 

 


background image

KARI &                                                                                                                                        Page 29 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

Article 22. Language and Units 
 

22.1 

This Contract shall be executed in English. 

 

22.2 

All  documents,  drawings,  plans  and  other  writings  as  well  as  communications 

between both Parties shall be in English. 

 

22.3 

Measurements and quantities for deliverable documentation shall be recorded in units 

of Système Internationale. 

 

 


background image

KARI &                                                                                                                                        Page 30 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

Article 23. Effective Date of Contract 
 

23.1 

The  effective  date  of  this  Contract  ("EDC")  is  the  date  on  which  all  of  the           

following conditions have been satisfied: 

 

(a) The duly authorized representatives of both Parties have signed this Contract, and   

(b)  The  appropriate  governmental  authorities  of  the  Republic  of  Korea  and 

Contractor’s country have duly approved this Contract, if required. 

 

23.2 

Any amendment to this Contract shall  be effective upon signature by the authorized 

representatives of both Parties. 

 

 


background image

KARI &                                                                                                                                        Page 31 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

Article 24. Changes 
 

24.1 

Changes Requested by KARI 

 

24.1.1  Any changes requested by KARI during the performance of this Contract, within the 

general scope of this Contract, which would add or delete Work, affect the design of 

Work, change the method of shipment or packing, place or time of delivery, duration 

of Contract, or would affect any other requirement of this Contract, shall be submitted 

in writing to Contractor. Contractor shall respond to any changes KARI requested in 

writing within thirty (30) days after receipt of such request. If such change requested 

by  KARI  causes  an  increase  or  decrease  in  the  Contract  Price  and/or  an  impact  of 

schedule, Contractor shall submit to KARI at the time the response to the requested 

change is submitted, the details of such increase or decrease. 

 

24.1.2  KARI  shall  notify  Contractor  in  writing,  within  thirty  (30)  days  after  receipt  of 

Contractor’s  response,  whether  it  agrees  with  and  accepts  Contractor’s  response.  If 

KARI agrees with and accepts Contractor’s response, an amendment to the Contract 

reflecting  such  change,  Contract  Price  and/or  schedule  adjustment,  if  any,  shall  be 

issued, and Contractor shall proceed with the performance of the Contract as changed. 

Contractor shall provide updated information that reflects the final agreed price of the 

change,  if  KARI  requests.  In  the  event  the  Parties  are  unable  to  agree  on  a  change 

requested by KARI or price adjustment, if any, or both, Contractor shall proceed with 

the performance of the Contract as unchanged. 

 

24.2 

Changes Requested by Contractor 

 

24.2.1  Any changes requested by Contractor during the performance of this Contract, within 

the general scope of this Contract, that would add or delete Work, affect the design of 

Work, change the method of shipment or packing, place or time of delivery, duration 

of Contract, or would affect any other requirement of this Contract, shall be submitted 

in writing to KARI thirty (30) days prior to the proposed date of the change. If such 

change requested by Contractor causes an increase or decrease in the Contract Price, 

Contractor  shall  submit  to  KARI  at  the  time  the  requested  change  is  submitted,  the 

details of such increase or decrease. 

 

24.2.2  KARI  shall  notify  Contractor  in  writing  within  thirty  (30)  days  after  receipt  of  the 

requested change and Contract Price adjustment, if any, whether or not it agrees with 


background image

KARI &                                                                                                                                        Page 32 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

and  accepts  such  change.  If  KARI  agrees  with  and  accepts  change  requested  by 

Contractor, an amendment to the Contract reflecting such change, and Contract Price 

adjustment, if any, shall be issued, and Contractor shall proceed with the performance 

of  the  Contract  as  changed.  Contractor  shall  provide  updated  information  which 

reflects the final agreed price of the change, if KARI requests. In the event the Parties 

are  unable  to  reach  an  agreement  on  a  change  requested  by  Contractor, or  Contract 

Price  adjustment,  if  any,  or  both,  Contractor  shall  proceed  with  the  performance  of 

the Contract as unchanged. 

 

 


background image

KARI &                                                                                                                                        Page 33 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

Article 25. Notices 
 

25.1 

All notices, requests, demands, approvals, reports, invoices, and other correspondence 

to  be  provided  pursuant  to  this  Contract  shall  be  in  writing  and  shall  be  deemed  to 

have  been  duly  given  to  the  Party  to  be  notified:  (i)  on  the  date  of  delivery  if 

delivered in person, (ii) on the date of dispatch if by facsimile, telex or e-mail, or (iii) 

on the date of receipt if by registered airmail or overnight courier. 

 

All notices shall be addressed to the appropriate Party at its address as follows: 

 

  For KARI: Korea Aerospace Research Institute 

169-84 Gwahakro, Yuseong-gu, Daejeon 305-806, Korea 

 

Commercial matters 

Technical matters 

Mr. Jung-Nam Cho 
 
Tel: +82-42-860-2613 
Fax:+82-42-860-2666   
E-mail: jncho@kari.re.kr 

Mr. Jong-Min Im 
 
Tel: +82-42-860-2562   
Fax:+82-42-860-2234 
E-mail: acoust@kari.re.kr 

 

For Contractor: Company name 

      Adress 
 

Commercial matters 

Technical matters 

Mr.   
 
Tel: +   
E-mail:   

Mr.   
 
Tel: + 
E-mail:   

 

25.2 

Each Party may change its address for notice by notice given to the other Party in the 

manner set forth above. And any notices given as provided herein shall be considered 

effective seven (7) days after the registered postage pre-paid airmailing thereof or the 

day  of  actual  receipt  thereof,  whichever  occurs  first,  or  on  the  day  of  personal 

delivery, or the day of sending if by facsimile, telex or e-mail. 


background image

KARI &                                                                                                                                        Page 34 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

Article 26. Miscellaneous 
 

26.1 

Assignability 

 

This  Contract  and  each  and  every  covenant,  term  and  condition  hereof  shall  be 

binding  upon  and  inure  to the  benefit  of  the  Parties  and  their  respective  successors, 

and neither this Contract nor any rights and obligations hereunder shall be assignable 

or delegable directly or indirectly by either Party without the prior written consent of 

the other Party. 

 

26.2 

Entire  Agreement 

 

This  Contract  embodies  the  entire  agreements  of  the  Parties  with  respect  to  the 

subject matter hereof and supersedes and cancels any and all prior understandings or 

agreements, oral or written,  in relation  hereto, which  may exist between the Parties. 

No oral explanation or oral information by any of the Parties shall alter the meaning 

or interpretation of this Contract. 

 

26.3 

Unenforceable  Terms 

 

If  any  term  or  provision  of  this  Contract  shall  for  any  reason  be  invalid,  illegal  or 

unenforceable  in  any  respect,  this  Contract  shall  be  interpreted  and  construed  as  if 

such term or provision had never been included herein. 

 

26.4 

Non-waiver 

 

The  failure  or  delay  of  any  Party  to  require  performance  by  the  other  Party  of  any 

provision  of, or of  any  right or obligation  under  this  Contract,  shall  not  constitute  a 

waiver  thereof,  nor  shall  such  affect  that  Party’s  right  to  thereafter  require 

performance of such or any other provision, right or obligation. 

 

26.5 

Disclaimer  of  Agency 

 

This Contract shall not be deemed to constitute any Party the agent of the other Party. 

 


background image

KARI &                                                                                                                                        Page 35 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

26.6 

Headings 

 

The  headings  in  this  Contract  have  been  inserted  for  convenience  of  reference  only 

and are not to be used in consulting or interpreting this Contract. 

 

26.7 

Time  Limits 

 

Unless otherwise indicated, any time limits to which this Contract binds Contractor or 

KARI  shall  be  counted  in  calendar  days  from  the  day  following  that  of  the  event 

marking  the  start  of  the  time  limit,  and  shall  end  on  the  last  day  of  the  period 

specified. When the last day of a time limit is a Saturday or Sunday, or a legal holiday 

in the country in which the particular contractual performance is required, such time 

limit shall be extended to the first working day following. 

 

26.8 

Subcontractors 

 

Each  Party  shall  be  fully  responsible  for  the  work  of  its  Subcontractors  under  this 

Contract, and such subcontracting shall  not relieve that Party of  its obligation under 

this Contract. 

 

26.9 

Limitation  of  Liability 

 

Contractor  shall  not,  under  any  circumstances,  have  any  liability  to  KARI  for  any 

indirect,  special,  consequential  and/or  incidental  or  punitive  damages  resulting  from 

the  performance,  non-performance  or  bad  performance  of  this  Contract,  including 

without  limitation  loss  of  profits,  loss  of  revenues  and  any  other  similar  loss. 

However,  in  case  of  Contactor’s  act  of  intentional,  gross  negligence  or  willful 

misconduct,  the  foregoing  provision  shall  not  apply  for.  Contractor’s  aggregate 

liability  under  this  Contract  shall  be  limited  to  one  hundred  percent  (100%)  of  the 

Contract Price.   

 

 

 

 

 

 

 


background image

KARI &                                                                                                                                        Page 36 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

 

IN WITNESS WHEREOF this Contract has been issued in two (2) signed English originals 

of  equivalent  validity,  executed  on  behalf  of  KARI  and  the  Contractor  by  their  respective 

persons authorized on that behalf. 

 

Korea Aerospace Research Institute 

Contract Company 

 

 

By : ______________________ 

Name : Dr. Gwang-Rae Cho 

Title : President 

Date : 

 

 

 

By : ______________________ 

Name :   
Title :   

Date :   

 

 


background image

KARI &           

   

 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Appendix B-1. Statement of Works 

 


background image

KARI &                                                                                                                                        Page 38 
 
 
 
 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

1. Work description 

 

1.1 WP S1000 Shakers, Amplifiers and Interface Management 

 

1.1.1 General 

An  effective  and  economical  management  of  the  Project  shall  be  conducted.  A  Project  Manager  shall  be 

responsible for the management and execution of the work to be performed. 

 

1.1.2 Access 

The KARI shall be allowed free access to any plan, procedure, specification or other documentation relevant to 

the  work.  Areas  and  equipment  used  during  the  development/testing  activities  shall  also  be  available  for 

inspection and audit. 

 

The KARI shall be notified at least three weeks before the start of any test program, or as mutually agreed, in 

order to enable the KARI to select those tests that it wishes to witness. The KARI shall notify its  visit at least 

three week in advance. 

 

 

1.2 WP S2000 Shakers, Amplifiers and Interface Design 

 

1.2.1 Design 

The design of the shakers, amplifiers, interface shall be carried out. Since the four shakers shall be integrated in 

the seismic foundation to be designed and connected to the table under the Upgrading of the Multishaker Vertical 

Configuration Contract, a complete mass-spring model of the shaker shall be provided. 

 

1.2.2 Design Review (DR) 

Upon  successful  completion  of  the  Design  Review  (DR)  meeting  the  KARI  shall  authorise  manufacturing and 

assembling of the relevant equipment. From that time on, a configuration control system for the documentation 

and  drawings  shall  be  established.  All  changes  to  the  design  shall  be  processed  via  Contract  Change  Notice 

(CCN) to be approved by KARI. 

 

1.2.3 Deliverables: Design Review Data Package 

The following documents shall be handed over to the KARI 2 weeks prior to the DR: 


background image

KARI &                                                                                                                                        Page 39 
 
 
 
 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

1.2.3.1 Exhaustive list of equipment to be delivered   

1.2.3.2 Technical justification for the selected components 

1.2.3.3 Functional description of the main and auxiliary equipment 

1.2.3.4 Individual shaker performance specifications 

1.2.3.5 Quad Vibration System performance specifications 

1.2.3.6 Detailed internal and external interfaces document   

1.2.3.7 Mass-spring model of one shaker used in quad-shaker 

1.2.3.8 Measurements supporting the equipment performance specifications 

1.2.3.9 Certificates supporting the compliance with EMC requirements 

1.2.3.10 Electrical load list for equipment and auxiliary equipment 

1.2.3.11 Calculation of reactive power and mains filters (if applicable) 

1.2.3.12 Detailed description of the safety devices and interlocks 

1.2.3.13 Design Specifications and FMECA report for the Interlock Supervisory Kit   

1.2.3.14 Cable list with cable number, type, size, length and destination (cable length to be verified at KARI site) 

1.2.3.15 Factory Acceptance Plan 

 

 

1.3 WP S3000: Shakers, Amplifiers and interface Manufacturing   

During this work package the following tasks shall be performed: 

 

1.3.1 Manufacturing 

The system hardware shall be manufactured according to the design accepted under WP S3000. 

All manufacturing operations shall be planned in co-ordination with inspections and tests. This planning shall be 

documented in a concise Manufacturing and Inspection Plan. 

 

1.3.2 Factory acceptance 

The  Factory  Acceptance  objective  is  to  verify  that  the  requirements  detailed  in  technical  requirements  are 

fulfilled.   

The factory acceptance tests and inspections shall be performed according to a Factory Acceptance Plan, which 

shall identify all the activities to be performed and the requirements intended to be verified. 

The  Factory  Acceptance  Review  meeting  in  order  to  review  the  results  of  the  implementation  of  the  Factory 

Acceptance plan shall be organised.   

A board composed of members to be agreed with the KARI’s representatives shall attend the Factory Acceptance 

Review meeting and confirm that: 


background image

KARI &                                                                                                                                        Page 40 
 
 
 
 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

1.3.2.1 All the equipment to be delivered is ready to be shipped. 

1.3.2.2 The functional requirements are fulfilled. 

1.3.2.3 The shakers perform individually as specified   

1.3.2.4 The Quad vibration system perform as specified   

 

This task shall be completed upon a successful Factory Acceptance Review. 

 

 

1.3.3 Deliverables: 

 

1.3.3.1 Exhaustive list of the equipment to be shipped 

1.3.3.2 Factory Acceptance test reports 

1.3.3.3 Factory Acceptance Review minutes of meeting 

1.3.3.4 KARI on site Acceptance Plan 

 

 

 

1.4 WP S4000 Shakers, Amplifiers and Interface Installation and Testing 

During this work package the following tasks shall be performed: 

 

1.4.1 Mechanical installation. 

 

The mechanical installation comprises the: 

  Connection of the cooling units to the interfaces with KARI supplies.   

 

1.4.2 Amplifiers: 

The  amplifiers and  cooling  units  shall  be  installed  in  KARI  basement  Room.  The amplifier related  equipment 

shall be brought in the basement room through a loading bay by means of a cargo crane. 

 

1.4.3 Shakers: 

The shakers shall be installed in the seismic foundation procured under Part 2. 

The  shakers  shall  be  transported  at  the  ground  floor  level  and  lowered  inside  the  seismic  foundation  using  a 

20,000 Kg [10,000kg x 2EA] crane supplied by KARI. 


background image

KARI &                                                                                                                                        Page 41 
 
 
 
 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

1.4.4 Electrical installation 

 

The electrical installation comprises the: 

1.4.4.1 Routing, installation and termination of input and output power cables and control cables.   

1.4.4.2 Connection of power cables (feeder) of the amplifiers to KARI RFI filters. 

1.4.4.3 Continuity and insulation testing according to the Contractor specifications. 

1.4.4.4 Labeling and marking of installed cables and wires. 

1.4.4.5 Connection of earthing cables to the existing KARI dedicated network 

 

 

1.5 WP S5000: Shakers, Amplifiers and Interface Acceptance testing 

Upon  completion  of  the  installation  of  the  shakers  and  auxiliary  equipment,  the  provisional  acceptance  of  the 

shakers, not connected to the table, shall take place according to the Acceptance Plan.   

The  acceptance  tests  shall  be  performed  in  accordance  with  formal  test  procedures  and  documented  in  test 

reports. 

The  draft  operation  manual  will  be  used  during  the  acceptance  test  to  confirm  its  suitability  to  support  the 

operation of the system. KARI staffs and other authorized persons will be trained on the operation of the system 

during the acceptance test. 

   

The  Acceptance  Plan  shall  cover  all  tests  and  verifications,  which  were  already  performed  during  Factory 

Acceptance but are invalidated by the installation at KARI. 

During this work package the following tasks shall be performed: 

 

 

1.5.1 Interlock/ External trip acceptance 

   

1.5.1.1 The proper functioning of the internal and external interlocks shall be verified individually; external trips 

may be checked by simulation. 

1.5.1.2  The  individual  shaker  amplifiers  behavior  shall  be  recorded  during  a  soft  and  hard  shut  down  and 

checked  against  specifications.  To  this  end  armature  and  vibrator  body  acceleration  responses  during 

soft and hard shutdown of a typical sine vibration test run shall be measured. 

1.5.1.3 The Multishaker amplifiers behavior, not connected to the table, shall be recorded during a soft and hard 

shut down and checked against specifications. To this end each armature and vibrator body acceleration 

responses during soft and hard shutdown of a typical sine vibration test run shall be measured. 

 


background image

KARI &                                                                                                                                        Page 42 
 
 
 
 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

1.5.2 Vibration acceptance test sequence 

The  vibration acceptance  tests  shall  verify  the  capability  of  the  amplifiers to  drive  the  vibrators in  compliance 

with KARI specification. The following vibration tests have to be performed: 

1.5.2.1 Individual shaker full performance tests 

1.5.2.2 Quad Multishaker bare armatures, performance tests 

1.5.2.3  Quad  Multishaker  loaded  by  interconnecting  the  four  shaker  armature  with  a  KARI  furnished  plate, 

performance tests 

1.5.2.4 Abort sequence verification 

 

 

During the test runs the following measurements shall be recorded: 

1.5.2.5 Amplifier AC input voltage and current 

1.5.2.6 Amplifier signal output voltage and current (amplitude and phase) 

1.5.2.7 Matching transformer output voltage and current (if applicable) 

1.5.2.8 Acceleration, amplitude and phase, for each armature 

 

1.5.3 Cooling units acceptance test 

The  adequacy  of  the  amplifier  forced  air-cooling as  well  as  water  and  oil  cooling has to  be  proven.  Therefore 

temperatures  at  essential  locations  shall  be  measured  and  recorded  while  performing  a  vibration  test  run  at 

maximum shaker performance (Multishaker configuration) over a period of time, relevant to the test duration. 

 

1.5.4 Acceptance review and acceptance data package 

An Acceptance Review (AR) shall be performed to review the results of the implementation of the Acceptance 

Plan. A Board composed of KARI representatives, including PA Representatives and other member to be agreed 

shall perform the Acceptance Review. 

 

1.5.5 Deliverable 

The AR shall be supported by an Acceptance Data Package (ADP). The ADP shall be provided two weeks prior 

to the review in 2 paper copies and 5 electronic copies. The ADP shall comprise the following documents: 

 

1.5.6 System Description Document 

A  system  description  document  containing  the  Quad  Multishaker  and  Lateral  single  shaker  performance 

specifications, the general functional description including block diagrams, layouts and principal schematics as 

necessary.   


background image

KARI &                                                                                                                                        Page 43 
 
 
 
 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

1.5.6.1 For each component a document covering: 

- Product Application: Details the product regarding type and serial number. 

- Installation and Operation: Concise information on the installation, the adjustment and the operation of the 

product 

- Test Instructions: Manufacturer’s standard test procedure for the product 

- Test reports: Results from the manufacturer’s standard test procedures for the product. 

-  CE  Compliance  Certification:  Formal  certification  stating  that  the  equipment  provided  complies  with  CE 

requirements. 

- Parts List and Drawings: Complete bill of materials listing including assembly drawings associated with the 

product 

 

1.5.6.2 Mechanical Drawings 

-  All  mechanical  drawings  necessary  for  the  installation  and  maintenance  of  the  equipment,  stating 

dimensions, weights and attachment points 

- All mechanical interface drawings for cable trays, cable entry and termination   

- Electrical drawings comprising: 

- Overall functional block diagram (with reference to the equipment by drawing, or equipment number) 

- Block or simplified functional diagram of the individual equipment (amplifiers) 

- Test points and test values 

- Terminal lists 

- Cable list comprising cable number, cross section and quality, length and destination 

- Drawing list of the delivered drawings 

 

1.5.6.3 Copies of all Non-conformance Reports and Requests for Waiver 

1.5.6.4 Manufacturing Inspection Report 

1.5.6.5 Acceptance test plans, test procedures and test reports 

1.5.6.6 System Operation Manual 

The  system  operation  manual  shall  describe  the  aspects  of  the  operation  of  the  equipment  in  a 

logical order, to ensure a safe and proper use. This manual shall contain the following chapters: 

  Pre-operational checks 

  Start-up and safe shut-down 

  Operation of equipment and auxiliaries 

  Inspections 

Note: This document should be written such that it can be used as a stand-alone manual for the facility operator 

without necessarily consulting the other documents. 


background image

KARI &                                                                                                                                        Page 44 
 
 
 
 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

1.5.6.7 Maintenance manual 

The  maintenance  manual  shall  describe  the  aspects  of  preventive  and  corrective  maintenance.  This  document 

shall  clearly  distinguish  between activities  that require  the special  knowledge  of  the  supplier and  the  activities 

that can be done by trained KARI personnel.   

In  addition  specific  needs  for  tools  or  instrumentation  shall  be  included  in  this  section.  The  shakers’ 

Subcontractor shall identify parts with a limited lifetime. 

 

1.5.6.8 Amplifier and shaker foot print manual 

The  amplifier  and  shaker  footprint  manual  section  shall  describe  activities,  to  be  performed  by  trained  KARI 

personnel, to carry out periodic amplifier and shaker signature tests.   

 

1.5.6.9 Repair manual 

The repair manual section shall assist the maintenance engineer in case a malfunction has to be corrected. It shall 

advise on the steps to be done to replace or repair, with references to the spare parts list and functional checks 

required thereafter. 

 

1.5.6.10 Spare part list   

A recommendation  concerning the  spare-parts  list  covering a  period  of  5  years  of  operation  shall  be made  and 

the guarantee that spare-parts can be made available for another 10 years thereafter shall be given. 

Delivery time shall be stated for all for spare parts.   

 

1.5.6.11 Attached documents 

The attached documents which compile information, data sheets, instruction for use, of those deliverable items, 

which are not covered by the above manual sections (e.g. instruments, auxiliary equipment etc.) 

 

1.5.6.12 Minutes of the Acceptance Review Board 

 


background image

KARI &                                                                                                                                        Page 45 
 
 
 
 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

1.6 WP S6000 Assistance to Installation and Commissioning of the Integrated System 
Support  shall  be  given  during  the  installation  of  the  integrated  system  and  associated  auxiliaries  and  to  the 
System Provisional Acceptance tests of the integrated system, as well as during the guarantee period leading to 
the System Final Acceptance. 

The work package shall include giving support for: 

1.6.1 Fixing interfaces issues 

1.6.2 Bolting the shakers inside the seismic foundation 

1.6.3 Aligning the shakers with respect to the QHE 

1.6.4 Attending integrated acceptance test campaign 

1.6.5 Any other related activities necessary to ensure a successful Provisional and Final acceptance of 

the integrated system. 

 


background image

KARI &                                                                                                                                        Page 46 
 
 
 
 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

2. Management reporting Meetings and Deliverables 
 

The hardware deliveries shall include, as a minimum, the following: 

Item 

No. 

Part name 

Qty 

Description 

One shaker & amplifier system for Quad 

Vibration System 

 

-      160 kN Electrodynamic shaker   

-      Including amplifier and related auxiliaries 

-      Including matching transformer 

All needed Cables for new installation place 

Improvement of existing three shakers & 

amplifiers of LDSV984(Quad Vibration 

System)   

160 kN Electrodynamic shaker 

All needed Cables for new installation place 

Same lifetime as new ones 

One shaker & amplifier system for Large 

Vibration System 

More than 280kN Electrodynamic shaker 

Including amplifier and related auxiliaries 

Including matching transformer 

All needed Cables for new installation place 

Shaker Interface equipment 

2.0m Head-expander   

1.3 or 1.2m Head-expander 

1.2m Slip table   

Related auxiliaries for interface 

 

Kick-off/PDR/CDR/MRR/TRR/FAR reviews shall be held. 

Review 

Purpose 

Kick-off 

-Review the requirements of the system 

-Understand and agree the design baselines 

Design Review 

- Verify the compatibility of the design definition 

and predicted performance with system requirements 

- Verify the coherency of the equipment 

specifications with the subsystem specification 

Test Readiness 

Review 

- Review test plans, sequences and procedures 

FAR (Factory 

Acceptance Review) 

Review test results (Checking key requirements’ performance consistency) 

- Final acceptance of quad-shakers in Factory 

FAR (Final 

Acceptance Review) 

-Review test results (Checking key requirements’ performance consistency) 

- Final acceptance of quad-shakers in KARI 


background image

KARI &                                                                                                                                        Page 47 
 
 
 
 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

3. KARI’s undertakings related to the shakers 
 

The following items are provided as KARI’s Undertakings: 

1.  PCU4 and MACU 

2.  Amplifier modules 

3.  Access to existing overhead cranes, lifting eyes and lifting slings 

4.  One office with 1 telephone and 1 PC connected to Internet + access to 1 FAX machine during the 

installation and commissioning 

5.  Raw water cooling outlets in the amplifier room 

6.  Disposal facilities for water and consumables 

7.  Cable trays located as per system layout drawing 

8.  Compressed air outlets located close to the vibrators 

9.  Electrical mains supply at agreed outlets in the plant room and vibrator area 

10.  Dedicated earth star point located in the plant area close to equipment 

11.  Four shaker armature interconnecting plate (if required) 

12.  Qualified operators for instrumentation, operation and data acquisition during acceptance testing 

13.  On-site access to the existing vibration system data package if required 

14.  Access to building layout if required 

15.  Specialized equipment required to complete the agreed acceptance procedure 

16.  Access to on-site workshop for small mechanical correction work 

17.  On-site car parking for company vehicle 

18.  Finished final location to allow the installation of the shakers   

 

 

 

 


background image

KARI &                                                                                                                                        Page 48 
 
 
 
 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

4. Warranty   

 

4.1 

The system shall be warranted for a duration of 1 years from the date of definitive acceptance 

on the site against any operational faults. The date of acceptance is the date when the whole 

system is completely installed and its function is approved perfect in a written format by KARI 

or its representative. 

 

4.2 

The  warranty  covers  the  replacement  of  faulty  parts,  the  labor  required  for  repair,  traveling 

cost, living fees and all associated necessary costs.   

 

4.3        For the upgrading of three shakers used in quad-shakers, contract shall take the responsibility 

for  the  normal  operation  especially  in  amplifiers  system  for  5  years.  In  case  of  new  shakers 

including amplifiers are supplied, it take Warranty 6.1. 

 

4.4 

The  contractor  or A/S  teams  shall  submit the  written plan for  repair  within  48  hours  after the 

reception  of  the  notification  of  fault.  The  contractor  or  A/S  teams  shall  completely  finish  the 

repair within 30 days after the reception of the notification of fault.   

 

4.5 

For  an  urgent  service  during important testing  period,  the  deadline for  action  is  5  days  from 

the  reception  of  the  notification  of  service. To meet the  deadline  of the  urgent  service, KARI 

will notify the contractor of the test start date and the period 2 weeks before the test start date. 

The  contractor  shall  stand  by  the  A/S  crews  at  contractor's  convenient  place  during  the  test 

period  (up  to  4  weeks).The  contractor  shall  include  a  plan  for  these  requirements  in  the 

proposal. 

 

4.6 

To meet these requirements, the contractor shall propose a detailed plan for the prompt repair 

in the proposal. The detailed information (location, number of crews, resume, phone and FAX 

numbers, e-mail address, etc.) of the A/S teams shall be shown in the proposal and shall be 

approved by KARI. 

 


background image

KARI &                                                                                                                                        Page 49 
 
 
 
 
 

Korea Aerospace Research Institute                                                                                  CONTRACT COMPANY 

 

5. Product supply schedule   

The contractor shall meet the key points schedule as below; 

Items 

Key Points Schedule 

Quad vibration 

System   

(Item #1 & #2) 

Arrival at KARI : by January 31, 2016 

Installation & Finish site acceptance : by February 29, 2016 

Existing three shakers are available to contractor from November 2015 

Large Vibration 

System 

  (Item #3) 

Arrival at KARI : by January 31, 2017 

Installation & Finish site acceptance : by February 28, 2017 

Interface equipment 

(Item #4) 

Arrival at KARI : by April 30, 2017 

Installation & Finish site acceptance : by May 31, 2017 

*For the detailed description for item #, refer to hardware deliveries in 2.Management reporting Meetings 

and Deliverables 

 

6. Payment Condition 

 

6.1 

KARI  may  terminate  this  Contract,  in  whole  or  in  part,  ONLY  IF  GOVERNMENT 

TERMINATES THE  PROGRAM WHICH  IS  DIRECTLY  RELATED  TO THIS  CONTRACT for 

its  convenience,  with  sixty  (60)  days’  prior  written  notice  to  Contractor.  In  case  of  such 

termination for convenience, Contractor is entitled to receive payment due which Contractor 

has  already  done  in  accordance  with  this  Contract  within  thirty  (30)  days  from  the  date  of 

termination and KARI shall release performance bond at the same time. 

 

6.2 

KARI’s Payment Schedule for this Contract can be adjusted by Government budget profile.