Terms and Conditions 

 

 

 
 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 
 
 
 
 
 
 

Korea Aerospace Research Institute 

 


background image

KARI                                                                                                                                                      KARI Proprietary 
 

 

 
Korea  Aerospace  Research  Institute 

Preamble

 

 
This  Contract  made  on  December          ,  2014  and  will  be  valid  until  February  20,  2015  by  and  between  Korea 
Aerospace  Research  Institute,  established  under  the  law  of  the  Republic  of  Korea  with  its  principal  office  at  169-84 
Gwahakro, Yuseong-Gu, Daejeon 305-806, Korea, hereinafter referred to as “KARI” and xxx established under the law 
of the xxx with its principal office at xxx, hereinafter referred to as “Contractor”. 
 
     
Article 1.    Objective 
 
The  objective  of  this  Contract  is  to  carry  out  and  provide  the  technical  consulting  work  to  establish  the  quad-
shaker  system  of  vertical  configuration  under  the  Contractor’s  responsibility.  To  accomplish  this  objective, 
Contractor  shall  perform all the  works  under  this  Contract required  for  the  Appendix 1.  Request  for  Proposal  as 
well as Contractor’s proposal. 
 
 
Article 2.    Scope of Services 
 
2.1        Contractor shall accomplish the  Services and supply the following documents  under this Contract 

in a timely manner: 

 

(a) Statement of work and technical requirements for four-shakers; and 
(b) Acceptance test for four-shakers; and 
(c) List of manufacturing key inspection points for quad-shakers; and 
(d) Acceptance test for overall system; and 
(e) FMECA [Failure Modes, Effects and Critical Analysis on similar four shakers system; and 
(f) Review on shaker supplier proposal; and 
(g) Review on quad-shaker design.   

 
2.2        Contractor  shall  provide  as  sufficient  as  engineering  and  administrative  manpower  and  resources 

for  the  timely  completion  of  the  Services  under  this  Contract.  In  the  event  the  Services  are  not 
completed  with  manpower  and  resources  due  to  Contractor’s  fault,  Contractor  shall  provide  any 
additional manpower and resources to accomplish the Services free of charge to KARI. 

 
2.3        Contractor shall provide any technical data or technical information as may be needed for KARI to 

understand the results of Services free of charge to KARI. 

 
2.4        To  accomplish  this  Contract,  KARI  shall  cooperate  to  Contractor  in  order  for  it  to  obtain  any 

necessary  government  and  KARI’s  Associates  approvals,  if  necessary.  And  Contractor  shall 
obtain any government approvals required to accomplish and perform this Contract free of ch arge 
to KARI. 

 
 
Article 3.    Contract Price and Terms of Payment 
 
3.1          For  the  full,  satisfactory  and  timely  performance  of  all  obligations  by  Contractor  in  accordance 

with the provisions of this Contract, KARI shall pay to Contractor the Contract Price of USD or 
EUR XXX.00
.   

 
3.2 

 The  payment  of  Contract  amount  specified  in  Article  3.1  shall  be  made  after  delivering  the 


background image

KARI                                                                                                                                                      KARI Proprietary 
 

 

 
Korea  Aerospace  Research  Institute 

Services  as  required  in  Article  2.1  to  KARI  and  made  in  USD  or  EURO  by  telegraphic  transfer 
to  the  bank  account  as  designated  by  Contractor  in  its  invoices.  KARI  shall  remit  the  payment 
within thirty (30) days after KARI’s receipt of Contractor’s invoice. 

 
3.3   

The Contract Price is a firm and fixed amount not subject to any escalation or to any adjustment 

or  revision  for  any  reason  whatsoever,  including  but  not  limited  to  the  increase  of  actual  cost 
incurred by Contractor in the performance of the Contract. 

 
3.4          The Contract price excludes any VAT that may be applicable in Korea. 

 

3.5          All  banking  charges  incurred  in  Korea  shall  be  borne  by  KARI,  and  those  charges  incurred 

outside Korea shall be borne by Contractor. 

 
 
Article 4.    Taxes and Duties 

 

4.1        If Korean income tax is required to be  withheld from amounts paid or payable to Contractor under 

this  Contract  (herein  referred  to  as  ‘Applicable  Tax’),  KARI  shall  withhold  the  Applicable  Tax 
and  pay  on  behalf  of  Contractor  the  relevant  Korean  taxing  authority  in  accordance  with 
applicable Korean law. 

 

4.2 

KARI  shall  forward  proof  of  the  withheld  Applicable  Tax  to  the  Contractor  within  ninety  (90) 
days of payment. 

 
4.3 

Neither Party shall be responsible for paying the customs duties, and related taxes, fees or charges 
for the personnel and the personal belongings of the other Party.  

 

4.4 

Each  Party  shall  further  comply  with  instructions  the  other  Party  may  issue  from  time  to  time  in 
order to facilitate any exemptions or reductions from customs duties and other taxes that might be 
levied on the other Party. 

 
 
Article 5.    Performance Bond 
 
5.1 

Contractor shall establish a performance bond within four (4) weeks after EDC in favor of KARI in the value 
of ten percent (10 %) of the Contract Price, in the form of an irrevocable and unconditional standby letter of 
credit available by KARI’s draft at sight. 

 
5.2 

The  entire  amount  covered  by  the  performance  bond  shall  be  unconditionally  payable  to  KARI  on  demand 
together with KARI’s written statement to the effect: 

 

(a)  that  there  was  a  breach  of  the  Contractor  in the  performance  of  the  Contract  (including  the  breach  of  its 

Subcontractor under the Subcontract); or 

(b) that this Contract was terminated by Contractor’s breach as specified in Article 9 ‘Termination’.   

 
5.3 

The letter of credit shall be issued by first class international bank acceptable to KARI. The letter of credit shall 
be drawn in favor of KARI and advised through the Woori Bank (Daejeon Branch at 1495 Dunsan-dong, Seo-
gu,  Daejeon, 302-173  Korea, Tel:  +82-42-488-9704,  Ext. 312,  email: the_banker@wooribank.com)  and  shall 
remain valid through the end of this Contract. The letter of credit shall not be amended, modified or canceled 
without KARI's prior written consent. 


background image

KARI                                                                                                                                                      KARI Proprietary 
 

 

 
Korea  Aerospace  Research  Institute 

5.4 

It is hereby agreed between the Parties that payment from the performance bond under this Article 5 shall not 
affect any other of KARI's rights, privileges, interests or remedies under this Contract. 

 
 
Article 6.    Delivery 
 
Contractor shall deliver any deliverable item for the technical consulting work in accordance with Article 2.1 
and the Appendix 1. Request for Proposal by e-mail. 
 
 
Article 7.    Delays in Performance 
 
7.1      Excusable Delay 

 

(a) Neither Party shall be responsible to the other Party for any delay in performing its obligations 

under this Contract due to any events of Force Majeure. 

(b)  ‘Force  Majeure’  means  any  act  of  God,  war,  act  or  failure  to  act  of  any  government  in  its 

sovereign  capacity,  fire,  flood,  earthquake,  strike,  epidemic,  quarantine,  embargo,  nuclear 
incident, or any other act unforeseeable and beyond the reasonable control without the fault of 
either Party or its Sub-Contractors. 

(c)  The  Party  whose  performance  of  obligations  hereunder  has  been  affected  by  any  events  of 

Force  Majeure  shall  notify  the  other  Party  within  ten  (10)  days  thereafter  by  sending  a 
detailed  statement  and  sufficient  evidence  with  respect  thereto,  and  promptly  of  any 
subsequent  change  in  the  circumstances,  if  any.  The  affected  Party  shall  exercise  its  best 
efforts  under  the  circumstances  to  remove  or  remedy  the  events  of  Force  Majeure  and  the 
effects thereof and resume full performance hereof as soon as possible.   

 
7.2        Non-Excusable Delay 

(a) In the event that, unless otherwise excused by virtue of this Contract or the governing or 

Applicable  law,  Contractor  delays  the  provision  of  Services  or  delivery  of  detailed  drawing 
and  deliverable  items  as  stipulated  in  this  Contract,  or  performance  of  its  other  obligations 
under this Contract, Contractor shall be responsible  for damages incurred by KARI as a result 
of such delay. 

(b)  Non-Excusable  Delay,  Liquidated  damages,  shall  be  applied  for  late  performance  or  non-

performance  at  the  rate  of  zero  point  twenty-five  (0.25)  percent  of  total  Contract  price  per 
calendar day, up to ten (10) percent of total price. 

 
 

Article 8.    Final Acceptance 
 
8.1 

Final Acceptance of this Contract shall occur only after: 
(a)  The technical  consulting  work  to  be  performed  by  the  Contractor  under  the  Contract  has  been 

completed in accordance with this Contract; and 

(b)  Contractor  has  demonstrated  to  KARI  that  the  technical  consulting  work  meets  the 

specifications and requirements in this Contract. 

 
8.2 

If  the  technical  consulting  work  is  determined  to  be  unacceptable,  it  shall  be  considered  as  non-

delivery and the Contractor shall, at its expense, promptly repair or replace such items so that it 
shall  comply  with  the  Contract  specifications  and  requirements,  and  shall  submit  such  repaired 
or  replaced  items  for  its  confirmation.  The  repaired  or  replaced  items  shall  be  accepted  in 


background image

KARI                                                                                                                                                      KARI Proprietary 
 

 

 
Korea  Aerospace  Research  Institute 

accordance with the requirements of Article 8.1. 

 
8.3 

The  Parties  agree  that  the  acceptance  of  any  item  under  this  Article  shall  not  be  interpreted  or 

construed  to  mean  that  such  items  are  free  of  all  defects  and  conform  in  all  respects  with  the 
requirements  of  this  Contract,  and  Contractor  shall  not  be  entitled  to  any  additional  costs 
incurred  or  to  recover  any  damages  suffered  due  to  defects  in  the  items  or  KARI’s  rejection  of 
the items. 

 
 

Article 9.    Termination 
 
9.1          KARI may terminate this Contract upon written notice to Contractor; 

(a)  if Contractor commits a material breach of any of its obligations under this Contract which shall 

not be remedied within thirty (30) days from the giving of written notice requiring such breach to 
be remedied; or 

(b) Contractor fails to obtain the export or re-export license from any government other than Korean 

government or conditionally obtains in accordance with Article 2.4; or 

(c)  if  Contractor  or its  creditors  or any  other  eligible  party  shall  file  for  its liquidation,  bankruptcy, 

receivership, reorganization,  dissolution  or  similar  proceedings,  or  if  Contractor's  creditors have 
taken over its management. 

 
9.2          In the event of such termination, Contractor shall return to KARI all materials, Data and documentation 

provided by KARI, at no cost to KARI, and KARI may perform the Services to completion. In addition, 
KARI, at its sole discretion, may; 

(a) either retain the Services  which have already been or are supposed to  be provided  by Contractor 

up to the date of such termination by paying the payments which have already become due up to 
the date of such termination. Any and all terms and conditions of this Contract shall apply to such 
Services as if it had not been terminated; or 

(b)  Contractor  shall  return  to  KARI  all  the  amounts  received  from  KARI  up  to  the  date  of  such 

termination, and KARI shall return all Services provided by Contractor under this Contractor up 
to the date of such termination, in the manner of “AS IS”. 

 
 

Article 10.    Intellectual Property 
 
10.1 

KARI  shall  own  and  have  a  right  to  use,  without  any  obligation,  all  the  deliverable  items  or  data 

provided  by  Contractor  in  its  performing  this  Contract.  Contractor  shall  take  all  necessary 
precautions  so  that  the  Services  supplied  hereunder  shall  be  free  from  infringement  of  any  patent, 
design  patent,  trademark,  utility  model  or  any  other  industrial  property  right,  copyright,  license  or 
any other right thereunder of any third party or parties. 

 
10.2          In the event that any party  other than Contractor claims or threatens to claim infringement by KARI 

with respect to such use of the deliverable items or data, Contractor shall defend, hold harmless, and 
indemnify KARI from such infringement claims. 

 
10.3          This Article will survive the completion of the Contract, any termination, cancellation or expiration 

of the Contract in any manner whatsoever. 

 

 
 


background image

KARI                                                                                                                                                      KARI Proprietary 
 

 

 
Korea  Aerospace  Research  Institute 

Article 11. Governing Law 
 
The validity, performance, construction, and effect of this Contract shall be governed by the laws of the Republic 
of Korea. 
 
 
Article 12.    Notice 
 
Any  and  all  notice  to  be  given  to  either  party  shall  be  given  to  the  following  addresses  by  register ed 
airmail  or  other  telecommunication  media.  Either  party  may  change  its  address  by  giving  prior  notice  to 
the other party in the manner provided for herein. 

 

  For KARI: Korea Aerospace Research Institute 

169-84 Gwahakro, Yuseong-gu, Daejeon 305-806, Korea 

 

Commercial matters 

Technical matters 

Mr. Jung-Nam Cho 
 
Tel: +82-42-860-2613 
Fax:+82-42-860-2666   
E-mail: jncho@kari.re.kr 

Mr. Jong-Min Im 
 
Tel: +82-42-860-2562   
Fax:+82-42-860-2234 
E-mail: acoust@kari.re.kr 

 

For Contractor: xxx Company 

      Address 
 

Commercial matters 

Technical matters 

Mr.   
 
Tel: +   
E-mail:   

Mr.   
 
Tel: + 
E-mail:   

 
 
 
IN WITNESS WHEREOF, the Parties hereto have executed this Contract in duplicate in English by causing these 
presents to be signed by their duly authorized representatives as of the day and year first above written.

 

 

 

Signed for and on behalf of KARI 

 

Signed for and on behalf of Contractor 

 

By:   

 

 

 

 

By: 

 
 

Name: Dr. Gwang-Rae CHO   

 

Name:   

 

Title:    President 

 

 

 

 

Title:   


background image

KARI                                                                                                                                                      KARI Proprietary 
 

 

 
Korea  Aerospace  Research  Institute 

Appendix 1. Request for Proposal 
 

OVERVIEW 

 
1.  Overview of the project 
 

1.1 

Korea  Aerospace  Research  Institute  (hereinafter  referred  to  as  “KARI”)  is  located  at  Daeduk 
Research Complex, 140 km south of Seoul. 

 

1.2 

KARI  has  a  satellite  assembly,  integration  and  test  center  (hereinafter  referred  to  as  “AITC”)  for 
joint  use  by  corporations  and  research  institutes  for  the  purpose  of  the  effective  development  of 
domestic  satellites.  And  basic  facilities  and  equipment  for  satellite  assembly  and  test  have  been 
supplied, installed and used. 

 

1.3 

To  increase  the  vibration  shaker  capability  and  improve  the  accessibility  to  satellite  for  the  safe 
environmental testing, new guided expander system with quad shakers will be designed and built. 

 

1.4 

The purposes of this project is to supply the technical consulting work to establish the quad-shaker 
system of vertical configuration 

 

1.5 

All the descriptions in this RFP are minimum requirements and the supplier can suggest the better 
one  to  improve  the  overall  performance  and  cost.  But  in  this  case,  the  proposal  should  clearly 
indicate the improvements from KARI’s requirements. 
 

2.  Requisites of participants 
 

2.1 

The  participants  shall  also  have  experience  of  management,  integration,  installation  and 
acceptance test for the 3m guided quad-shaker  system equipped with electro dynamic shakers of 
640kN. 

 
3.  Scope of the work 
 

3.1 

The Contractor shall supply the technical consulting work as followings; 

 

  Statement of work and Technical requirements for four-shakers   

  Acceptance test for four-shakers 

  List of manufacturing Key Inspection points for quad-shakers 

  Acceptance test for overall system 

  FMECA  [Failure  modes,  effects  and  critical  analysis]  analysis  on  similar  four  shakers 

system 

  Review on shaker supplier proposal 

  Review on quad-shaker design 

 
 

 


background image

KARI                                                                                                                                                      KARI Proprietary 
 

 

 
Korea  Aerospace  Research  Institute 

Technical Requirements 

 
1.  Quad-shaker System Configuration 
 

To  increase  the  shaker  capability  and  improve  the  accessibility  to  test  object,  new  guided  expander 

system  with  quad  shakers  shall  be  designed.  The  head  expander  should  be  designed  with  magnesium 
material  for  reducing  the  weight.  Seismic  mass  should  be  designed  to  support  dynamic  load  during  the 
vibration  test  and  also  supply  the  rigid  support  and  load  path  for  the  hydraulic  bearings.  Quad-shakers 
should be used to increase the capability. Top level of H/E is designed to same level of facility floor.   

 

Figure 1 Concept for Quad-shaker System 

 

Table 1. Technical requirements for Quad-shaker System 

 


background image

KARI                                                                                                                                                      KARI Proprietary 
 

 

 
Korea  Aerospace  Research  Institute 

Work Description 
 

WP #1 Statement of work and Technical requirements   

for four-shakers 

 

Objective 

To  generate  the  SOW  and  technical  requirements  for  four-

shakers 

Activities 

Generate the statement of work for four shakers 

Generate the technical requirements for shakers 

Generate the Amplifier requirements 

Generate the system requirements 

Generate the maintenance requirements 

Generate the guidelines for preparing statement 

of work   

Outputs 

Documentation on SOW and technical requirements   

Guidelines for preparing SOW 

 

WP #2 Acceptance test for four-shakers   

 

Objective 

To check the readiness of four-shaker and   

review the results of acceptance test 

Activities 

Generate four shakers acceptance plan on site 

 

Provide acceptance test results of similar system   

Outputs 

Four shakers acceptance test procedure 

Similar four shakers acceptance test result report 

 
 


background image

KARI                                                                                                                                                      KARI Proprietary 
 

 

 
Korea  Aerospace  Research  Institute 

10 

WP #3 List of manufacturing Key Inspection points for quad-shakers 

 

Objective 

To check the Key inspection points for quad-shakers 

Activities 

Generate  the  list  of  manufacturing  key  inspection 

points for shakers 

Outputs 

List of manufacturing key inspection points 

 
 

WP #4 Acceptance test for overall system in KARI 

 

Objective 

To check the readiness of overall system 

Activities 

Generate  the  list  of  manufacturing  key  inspection 

points for overall system 

Generate  the  overall  system  acceptance  test 

procedure 

Provide similar system acceptance test results report 

Outputs 

Overall system acceptance test procedure 

Similar system acceptance test result report 

 
 


background image

KARI                                                                                                                                                      KARI Proprietary 
 

 

 
Korea  Aerospace  Research  Institute 

11 

WP#5 FMECA analysis on KARI quad-shaker system 

 

Objective 

To check the safety logic for overall system 

Activities 

Provide similar four shakers system FMECA report 

Outputs 

Similar four shaker system FMECA report 

 

WP#6 Review on shaker supplier proposal 

 

Objective 

To review on shaker supplier proposal 

Activities 

Review the shaker supplier proposal 

Outputs 

Review report on shaker proposal 

 

WP#7 Review on quad-shaker design 

 

Objective 

To review on quad-shaker design   

Activities 

Review the overall quad-shaker design 

Outputs 

Review report on quad-shaker design 

 


background image

KARI                                                                                                                                                      KARI Proprietary 
 

 

 
Korea  Aerospace  Research  Institute 

12 

Format of Proposal 

 
The proposal shall consist of 5 Sections (S). 
 
 

S 1      : Bidder's Qualification Document 

 

S 2      : Overview and Technical Proposal 

 

S 3      : Work Schedule Plan 

S 4      : Documentation 

 

S 5      : Price Proposal 

 
The  bidder  shall  present  6  copies  of  the  proposal.  A4  or  letter  size  paper  shall  be  used.  The  bidder  is  requested  to 
strictly follow the following illustrated format (tabular form)
. This is very important to compare and evaluate different 
bidders’  proposal.  Consequently,  disregard  for  this  rule  may  end  up  with  disqualification.  Also,  well-prepared  and 
well-organized  proposal  will  be  highly  appreciated  and  evaluated.  The  landscape  orientation  will  be  acceptable  for 
tables.  The  suggested  contents  in  each  WP  are  minimum  requirements  and  works  for  reminiscences.  Ambiguous 
expression will act adversely to the bidder.   
 
Note : The prices which are used in the proposal to calculate the final total and breakdown prices   
            shall be distinguished from the other prices (e.g. optionally suggested parts by the bidder 
            or KARI, . . . ) by marking a.p. (applied price) after the prices. In other words, the sum of   
            a.p. shall be the final total price proposed in the proposal. 
(example) 

Item 

Price 

Unit 

Subtotal 

Item #1 

$ 5,000 a.p. 

$ 10,000 

Item #2 

$ 4,000 a.p. 

$ 4,000 

Item #3 

$ 2,000 a.p. 

$ 6,000 

 

 

Total 

$ 20,000 

 
 
 
S1 : Bidder's Qualification Document 
 
The followings shall be included in this WP. 
(a) Bidder's experiences on the prescribed system in this "Request for Proposal" including : 
 

- design/ management/ integration/ installation/ acceptance test 

(b) Bidder’s Qualification Evidence Documents to show the capability to perform the technical consultings. 
 
S2 : Overview and Technical Proposal 
 
Concise and clear expression is required. A long sentence should be broken down into several sentences. Detailed block 
diagrams, figures and photos are recommended for clear illustration. 
 
The bidder should prepare tables for the check list to show the bidder's compliance with the "Request for Proposal [S1 
to S5 in Work description]
". The bidder’s compliance list shall be legal bind. This table shall be located in the front 
of  Overview  part.  The  article  numbers  in  the  "Part  I.  Overview"  and  "Part  II.  Technical  Requirements"  in  the  RFP 
should be completely enumerated in the table. The table format to be followed is as follows: 
 
Check  List  for  "Part  I.  OVERVIEW",  "Part  II.  TECHNICAL  REQUIREMENTS",  “Part  Ⅲ.  Warranty,  Maintenance 
and other Requirement” and “Part  Ⅳ  Terms and Conditions”(COMPLIANCE LIST
 
ANR 

: Article Number in the Part I and Part II in the RFP 

Y/N 

: Compliance (Yes or No) 

CAP 

: Corresponding Article number in the bidder's Proposal to ANR 


background image

KARI                                                                                                                                                      KARI Proprietary 
 

 

 
Korea  Aerospace  Research  Institute 

13 

AAM 

: Article number of Added Material in the bidder's proposal which is not mentioned in this RFP 

(Exemple) 
 
ANR 

Y/N 

CAP 

Remark 

AAM 

Remark 

I-1. 

yes 

I-1.1 

Ditto 

 

 

I-2. 

yes 

I-2.1.1 

Ditto 

 

 

I-2.1. 

yes 

I-2.1.2. 

Ditto 

 

 

…... 

…… 

…… 

 

 

 

II-1. 

yes 

II-1.1 

Ditto 

 

 

II-2. 

yes 

II-2.1.2. 

Ditto 

 

 

II-2.1. 

yes 

II-2.1.3. 

Ditto 

 

 

II-2.1.1. 

yes 

II-2.1.5. 

The  specifications  look  old. 
We updated them 

 

 

N/A 

N/A 

N/A 

N/A 

II-2.1.4. 

We  currently  developed  a 
new method. 

II-2.1.2. 

yes 

II-2.2.1. 

Ditto 

 

 

 
WP 3 : Work Schedule   
 
The work schedule shall be shown as in detail as possible in chronological way. 
- Table for work schedule 

 

 
WP 4 : Documentation 
 
9.1. Documentation 
 

- document list (contents) to be delivered 

   
 
WP 5 : Price Proposal 
 
8.1.Total price : 
 
All the Price Proposal shall be separately submitted being sealed. 
 
Note :   
The prices which are used in the proposal to calculate the final total and break-down prices shall be distinguished from 
the other prices (e.g. optionally suggested parts by the bidder or KARI, . . . ) by marking a.p.(applied price) after the 
prices. In other words, the sum of a.p. shall be the final total price proposed in the proposal. 
The total price is the sum of the break down prices hereafter. 
 