Request For Proposal
for
Technical Consulting on
Quad-shaker Vibration System
November 2014
Space Environment Test Team
Korea Aerospace Research Institute
169-84 Gwahangno, Yuseong-gu, Daejeon, 305-806, KOREA
Phone : 82(42)860-2562, Fax : 82(42)860-2234
KARI PROPRIETARY
Request For Proposal
for
Technical Consulting on
Quad-shaker Vibration System
IMPORTANT
1. This RFP should be kept in confidentiality and should neither
be copied nor distributed to the third parties.
2. The questions and opinions on this RFP can be asked or
suggested to Korea Aerospace Research Institute before
submission of the proposal.
3. This RFP should be returned to Korea Aerospace Research
Institute with bidder
’s proposal.
4. This RFP shall be legal bind after the contract is awarded
unless the bidder explicitly expresses the differences from the
RFP in the compliance sheet.
November 2014
Space Environment Test Team
Korea Aerospace Research Institute
169-84 Gwahangno, Yuseong-gu
DAEJEON, 305-806, KOREA
Phone : 82(42)860-2562, FAX : 82(42)860-2234
e-mail :acoust@kari.re.kr
2014. 11
i
Space Environment Test Dept.
Table of Contents
I.
OVERVIEW ............................................................................................................................. 2
1.
OVERVIEW OF THE PROJECT ..................................................................................................... 2
2.
REQUISITES OF PARTICIPANTS .................................................................................................. 2
3.
SCOPE OF THE WORK ............................................................................................................... 2
II.
TECHNICAL REQUIREMENTS ...................................................................................... 4
1.
QUAD-SHAKER SYSTEM CONFIGURATION ............................................................................... 4
2.
WORK DESCRIPTION ............................................................................................................... 5
III.
FORMAT OF PROPOSAL .................................................................................................. 8
2014. 11
Technical Consulting on Quad-shaker Vibration System
2
Space Environment Test Dept.
I. OVERVIEW
1. Overview of the project
1.1
Korea Aerospace Research Institute
(hereinafter referred to as “KARI”) is located
at Daeduk Research Complex, 140 km south of Seoul.
1.2
KARI has a satellite assembly, integration and test center (hereinafter referred to
as “AITC”) for joint use by corporations and research institutes for the purpose of
the effective development of domestic satellites. And basic facilities and
equipment for satellite assembly and test have been supplied, installed and used.
1.3
To increase the vibration shaker capability and improve the accessibility to
satellite for the safe environmental testing, new guided expander system with
quad shakers will be designed and built.
1.4
The purposes of this project is to supply the technical consulting work to
establish the quad-shaker system of vertical configuration
1.5
All the descriptions in this RFP are minimum requirements and the supplier can
suggest the better one to improve the overall performance and cost. But in this
case, the proposal should clearly indicate the improvements from KARI’s
requirements.
2. Requisites of participants
2.1
The participants shall also have experience of management, integration,
installation and acceptance test for the 3m guided quad-shaker system equipped
with electro dynamic shakers of 640kN.
3. Scope of the work
3.1
The Contractor shall supply the technical consulting work as followings;
Statement of work and Technical requirements for four-shakers
Acceptance test for four-shakers
2014. 11
Technical Consulting on Quad-shaker Vibration System
3
Space Environment Test Dept.
List of manufacturing Key Inspection points for quad-shakers
Acceptance test for overall system
FMECA [Failure modes, effects and critical analysis] analysis on similar
four shakers system
Review on shaker supplier proposal
Review on quad-shaker design
2014. 11
Technical Consulting on Quad-shaker Vibration System
4
Space Environment Test Dept.
II. Technical Requirements
1. Quad-shaker System Configuration
To increase the shaker capability and improve the accessibility to test object, new
guided expander system with quad shakers shall be designed. The head expander
should be designed with magnesium material for reducing the weight. Seismic mass
should be designed to support dynamic load during the vibration test and also supply the
rigid support and load path for the hydraulic bearings. Quad-shakers should be used to
increase the capability. Top level of H/E is designed to same level of facility floor.
Figure 1 Concept for Quad-shaker System
Table 1. Technical requirements for Quad-shaker System
2014. 11
Technical Consulting on Quad-shaker Vibration System
5
Space Environment Test Dept.
2. Work Description
2.1 WP #1 Statement of work and Technical requirements
for four-shakers
Objective
To generate the SOW and technical requirements for four-
shakers
Activities
-
Generate the statement of work for four shakers
-
Generate the technical requirements for shakers
-
Generate the Amplifier requirements
-
Generate the system requirements
-
Generate the maintenance requirements
-
Generate the guidelines for preparing statement
of work
Outputs
-
Documentation on SOW and technical requirements
-
Guidelines for preparing SOW
2.2 WP #2 Acceptance test for four-shakers
Objective
To check the readiness of four-shaker and
review the results of acceptance test
Activities
-
Generate four shakers acceptance plan on site
-
Provide acceptance test results of similar system
Outputs
-
Four shakers acceptance test procedure
-
Similar four shakers acceptance test result report
2014. 11
Technical Consulting on Quad-shaker Vibration System
6
Space Environment Test Dept.
2.3 WP #3 List of manufacturing Key Inspection points for quad-
shakers
Objective
To check the Key inspection points for quad-shakers
Activities
-
Generate the list of manufacturing key inspection
points for shakers
Outputs
-
List of manufacturing key inspection points
2.4 WP #4 Acceptance test for overall system in KARI
Objective
To check the readiness of overall system
Activities
-
Generate the list of manufacturing key inspection
points for overall system
-
Generate the overall system acceptance test
procedure
-
Provide similar system acceptance test results report
Outputs
-
Overall system acceptance test procedure
-
Similar system acceptance test result report
2014. 11
Technical Consulting on Quad-shaker Vibration System
7
Space Environment Test Dept.
2.5 WP#5 FMECA analysis on KARI quad-shaker system
Objective
To check the safety logic for overall system
Activities
-
Provide similar four shakers system FMECA report
Outputs
-
Similar four shaker system FMECA report
2.6 WP#6 Review on shaker supplier proposal
Objective
To review on shaker supplier proposal
Activities
-
Review the shaker supplier proposal
Outputs
-
Review report on shaker proposal
2.7 WP#7 Review on quad-shaker design
Objective
To review on quad-shaker design
Activities
-
Review the overall quad-shaker design
Outputs
-
Review report on quad-shaker design
2014. 11
Technical Consulting on Quad-shaker Vibration System
8
Space Environment Test Dept.
III. Format of Proposal
The proposal shall consist of 5 Sections (S).
S 1 : Bidder's Qualification Document
S 2 : Overview and Technical Proposal
S 3 : Work Schedule Plan
S 4 : Documentation
S 5 : Price Proposal
The bidder shall present 6 copies of the proposal. A4 or letter size paper shall be used. The bidder
is requested to strictly follow the following illustrated format (tabular form). This is very
important to compare and evaluate different bidders’ proposal. Consequently, disregard for this
rule may end up with disqualification. Also, well-prepared and well-organized proposal will be
highly appreciated and evaluated. The landscape orientation will be acceptable for tables. The
suggested contents in each WP are minimum requirements and works for reminiscences.
Ambiguous expression will act adversely to the bidder.
Note : The prices which are used in the proposal to calculate the final total and breakdown prices
shall be distinguished from the other prices (e.g. optionally suggested parts by the bidder
or KARI, . . . ) by marking a.p. (applied price) after the prices. In other words, the sum of
a.p. shall be the final total price proposed in the proposal.
(example)
Item
Price
Unit
Subtotal
Item #1
$ 5,000 a.p.
2
$ 10,000
Item #2
$ 4,000 a.p.
1
$ 4,000
Item #3
$ 2,000 a.p.
3
$ 6,000
:
:
:
:
Total
$ 20,000
2014. 11
Technical Consulting on Quad-shaker Vibration System
9
Space Environment Test Dept.
S1 : Bidder's Qualification Document
The followings shall be included in this WP.
(a) Bidder's experiences on the prescribed system in this "Request for Proposal" including :
- design/ management/ integration/ installation/ acceptance test
(b) Bidder’s Qualification Evidence Documents to show the capability to perform the technical
consultings.
S2 : Overview and Technical Proposal
Concise and clear expression is required. A long sentence should be broken down into several
sentences. Detailed block diagrams, figures and photos are recommended for clear illustration.
The bidder should prepare tables for the check list to show the bidder's compliance with the
"Request for Proposal [S1 to S5 in Work description]". The bidder’s compliance list shall be
legal bind. This table shall be located in the front of Overview part. The article numbers in the
"Part I. Overview" and "Part II. Technical Requirements" in the RFP should be completely
enumerated in the table. The table format to be followed is as follows:
Check List for "Part I. OVERVIEW", "Part II. TECHNICAL REQUIREMENTS", “Part Ⅲ.
Warranty,
Maintenance
and
other
Requirement”
and
“Part
Ⅳ
Terms
and
Conditions”(COMPLIANCE LIST)
ANR
: Article Number in the Part I and Part II in the RFP
Y/N
: Compliance (Yes or No)
CAP
: Corresponding Article number in the bidder's Proposal to ANR
AAM
: Article number of Added Material in the bidder's proposal which is not mentioned in
this RFP
(Exemple)
ANR
Y/N
CAP
Remark
AAM
Remark
I-1.
yes
I-1.1
Ditto
I-2.
yes
I-2.1.1
Ditto
I-2.1.
yes
I-2.1.2.
Ditto
…...
……
……
II-1.
yes
II-1.1
Ditto
II-2.
yes
II-2.1.2.
Ditto
II-2.1.
yes
II-2.1.3.
Ditto
II-2.1.1.
yes
II-2.1.5.
The specifications look old.
We updated them
2014. 11
Technical Consulting on Quad-shaker Vibration System
10
Space Environment Test Dept.
N/A
N/A
N/A
N/A
II-2.1.4.
We currently developed a
new method.
II-2.1.2.
yes
II-2.2.1.
Ditto
WP 3 : Work Schedule
The work schedule shall be shown as in detail as possible in chronological way.
- Table for work schedule
WP 4 : Documentation
9.1. Documentation
- document list (contents) to be delivered
WP 5 : Price Proposal
8.1.Total price :
All the Price Proposal shall be separately submitted being sealed.
Note :
The prices which are used in the proposal to calculate the final total and break-down prices shall be
distinguished from the other prices (e.g. optionally suggested parts by the bidder or KARI, . . . ) by
marking a.p.(applied price) after the prices. In other words, the sum of a.p. shall be the final total
price proposed in the proposal.
The total price is the sum of the break down prices hereafter.
APPENDIX
1. General Terms and Conditions